_
r U- 0696 0982-L L30-84(02-10)-L ILLINDIS POWER 00MPANY IP CLINTON POWER STATION, P.O. BOX 678. CLINTON. ILLINOIS 61727 i-February 10, ]98(
Docket No. 50-461 h
Director of Nuclear Reactor Regulation Attention:
Mr. A. Schwencer, Chief Licensing Branct4 No. 2 Division of Licensing p
U. S. Nuclear Regulatory Commission Washington, D. C. 20555
Subject:
Clinton Power Station Unit 1 Control of Heavy Loads (NUREC-0612)
Dear Mr. Schwencer:
NRC Generic Letter 83-42, December 19, 1983, indicated that the guidelines of NUREG-0612 concerning " Single Failure Proof Cranes" may be deficient because single failures in the electrical power / control system were not considered.
Illinois Power Company (IP) took credit for a single failure proof handling system for lifts made by the Containment Polar Crane Main Hook.
IP has reviewed the elementary diagrams of the crane and_the description of the motor brakes and has concluded that no single failure in the electrical power / control system could result in the uncontrolled motion of the crane or the release of a load.
IP is in compliance with the intent of NUREG-0612 concerning single failure proof handling systems.
Sincerely yours, hz c
C. D. Geier ts Manager Nuclear Station Engineering GEW/ lam cc:
G. A. Harrison, NRC Clinton Licensing Project Manager NRC Resident Office Illinois Department of Nuclear Safety N. E. Fioravante, NRC ASB T. Stickley, EC&G h
DOC 0
,\\.
l