CONSUMERS POWER COMPANY MIDLAND ENERGY CENTER NU Transmittal No:
CSC-7301
@-3N
~
Date:
February 8, 1984 To:
Stone & Webster P O Box 1963 Midland, MI 48640 JtlNCIPAL STAFF 0 ( A*,A JPRP 3/RF
}E Attached Ist X
Partial Response To fWA DRIiSF
~
DRMA S4(g43 Complete Response To f?-
5CS L-
,AL
[
For Your Information
'* Y-Other
==
Description:==
Tracked Information Item 046.
g/I Signature:
NGkdhler[NRCRegionIII'w/respon'se,w/olists
~
~
cc:
JJHarris'on, NRC 'Re gion ' III ' w/ response', ' w/ o lis t's RJCook, NRC Site w/ response, w/o lists RAWells, MPQAD w/ response, w/o lists BHPeck, MEC w/ response, w/o lists NIReichel, MEC w/ response, w/o lists DDJohnson, MEC w/ response, w/o lists 8402220199 840200 FEB16 G84
/
PDR An?CK 05000329 i
PDR ltDl' g S
Sheet 1 of 1
lg" " f " " "
STONE & WEBSTER o
CONSTRUCTION IMPLEMENTATION O TRACKED ACTION ITEM OVERVIEW G TRACKED INFORMATION ITEM MIDldND NUCLEAR PLANT./.0. N0.14509 O TRACKED RECOuuENDATION ITEM REFERENCE (S)
O UNTRACKEDITEM CIO Weekly Report Number 4 I O HOLD POINT NOTIFICATION CONDITION DETAILS In CIO Weekly Report #4 we indicated that the CIO considers receipt of a complete listing of the NRC Commitments a constraint to the Quality Verification Program (QVP) and a prerequisite to the Construction Completion Program (CCP).
As of this date, the CIO has only received a partial list of these commitments. Also, it is our understanding that development of the total commitment list and responsibility for tracking has been transferred to CP Co's Licensing Department.
In order to facilitate our efforts, we are requesting to be placed on distribution for documentation and orocedures pertinant to the NRC Project Commitment Tracking Program, to be notified one (1) day in advance of upcoming meetings important to the subject, and to be provided a schedule that addresss the completion of these events.
O vES rot.",5 x NO ATTACHMENTS DATE RESPONSE REQ'D. yTIAT R/DATE INITI ATION APPROVED /DATE Feb. 1, 1984
/g 47////X/fcff
/,hf/W / y'[_
j./ f.p y
~
Includedasana'ttachmen[totheresponsetot[rtrackedinformationitem
RESPONSE
is a copy of all currently a6rembled NRC commitment lists. except those previously provided.
The development of the commitment management system is currently in its initiation stages with gathering of information and development of procedures being the priorities presently.
It is estimated based on the amount of information collected that the time frame for implementation of the management system will be 8 to 12 months.
The projected manpower requirements for this program are:
1.
6 permanent licensing people 2.
8 people from the various departments assigned temporarily to assist with system input. The duration is dependant of the number of entries from the individual departments.
A report of the status of the system will be issued periodically (duration not set at this time) and a copy will be supplied to you.
YES $o. s NO (continued)
ATTACHMENTS EST. CORRECTIVE ACTION RES J
'4 T TITLE DATE f
l COMPLETION DATE
/
j g
i l
RESPONSE ACCEPTED DATE RESFM.d,$ s k D/ CLOSED DATE l
P4
- y ?.
e*
R spon00 to CIO It'22 46 Continued-I The single point contact for the conunitment management system will be Ken Brewster who although is with the Licensing Department will be responsible to the Site Management Organization.