Requests Exception to ANSI-B30.2-1976 Section 2-2.2.2.b(3), Rated Load Test, Per Re Control of Heavy Loads.Requirements Unnecessary & Too Stringent.Response Requested Prior to Mar 1984 Unit 2 Outage
ML20080F468
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 02/06/1984
From: Zimmerman S
CAROLINA POWER & LIGHT CO.
To: Vassallo D
Office of Nuclear Reactor Regulation
References
REF-GTECI-A-36, REF-GTECI-SF, RTR-NUREG-0612, RTR-NUREG-612, TASK-A-36, TASK-OR NLS-84-042, NLS-84-42, NUDOCS 8402130001
Download: ML20080F468 (2)


Text

'

CfEL Carolina Power & Light Company SERIAL: NLS-84-042 FEB 061984 Attention:

Mr. D. B. Vassallo, Chief Operating Reactors Branch No. 2 Office of Nuclear Reactor Regulation United States Nuclear Regulatory Commissim Washington, DC 20555 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-325 AND 50-324 LICENS8 NOS. DPR-71 AND DPR-62 CONTROL OF HEAVY LOADS

Dear Mr. Vassallo:

By letter dated November 16, 1982, Carolina Power & Light Company (CP&L) provided supplemental information regarding Control of Heavy Loads at Brunswick Stene. Electric Plant (BSEP) Unit Nos. I and 2.

Brunswick's response to Section 2.l(3)e read in part, "The crane inspection, testing, and maintenance program at BSEP is in conformance with ANSI-B.30.2-1976, Chapter 2-2 and the Occupational Safety and Health Standards, Section 179, 29CFR, Part 1910."

The purpose of this letter is to inform you that CP&L intends to take an exception to ANSI-B30.2-1976, Overhead and Cantry Cranes, Section 2-2.2.2.b(3) Rated Load Test. The above referenced code requirement states:

b.

The rated load test, if made, shall consist of the following operations as a minimum requirement.

3.

Transport the test load by means of the bridge for the full length of the runway in one direction with the trolley as close to the extreme right-hand of the crane as practical and in the other direction with the trolley as close to the left-hand end of the crane as practical.

After extensive repair of a crane, compliance with Requirement b(3) above would, in some cases, require lifting loads in excess of 200 tons and transporting these loads over vital pieces of equipment. A specific example would be the lifting of a large tonnage test load by the Turbine Building overhead cranes and then passing this test load over both BSEP turbines.

8402130001 840206

~

PDR ADOCK 05000324 P

PDR

/,g fp k

411 Fayetteville S' eet

  • P. O. Box 1551
  • Raleigh, N. C. 27602 o m sw.sm N.

.~

From an equipment availability standpoint and as a personnel safety 3

hazard, CP&L believes that the requirements of b(3) above are unnecessary and too stringent.

Therefore, in order to meet the intent of ANSI-B30.2-1976, Section 2-2.2.2.b(3), CP&L proposes that bridge travel along the runway will be specified as "a measurable distance which is practical to demonstrate crene operability under load."

Carolina Power & Light Company will be completing repairs to the crane system in the near future. Ilence, should you find the above proposed alternative unacceptable please inform a member of our licensing staff prior to start of the March 1984 Unit 2 outage.

Yours very truly,

}n--"
=

S.

immerman Manager Nuclear Licensing Section i

.PPC lev (9384PPC)

/