Interim Deficiency Rept DER 83-25 Re Instrumentation Tubing W/O Boundary Class Break.Initially Reported on 830421.Final Rept Will Be Delayed Until 831023 Due to Extensive Investigation & Evaluation
ML20080D414
Person / Time
Site: Palo Verde 
Issue date: 08/19/1983
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Sternberg D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
10CFR-050.55E, 10CFR-50.55E, ANPP-27592-RQT, DER-83-25, NUDOCS 8308300442
Download: ML20080D414 (2)


Text

,

U' 7

ll

' Arizona Public Service Company po Box vece. PHOENIX, AFil2ONA B5036 h

I?I?:

e y",

August 19, 1983 ANPP-27592-RQT/BS,K

)'f

' U. S. Nuc1 car Regulatory Commission

. Region V r

.Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 Attention:

Mr. D. M. Sternberg, Chief Reactor Projects Branch 1

Subject:

Time Extension for Report - DER 83-25 A 50.55(e) Potentially Reportable Deficiency Relating to Instrumentation Tubing Does Not Have A Boundary

C1.aas Break As Required

- File:

83-019-026 D.4.33.2 Reference

.(A) Telephone Conversation between P. Narbut and O. Duckworth on April 21, 1983 4

-(B) ANPP-23911, dated May 26, 1983 (Interim Report)

-(C) ANPP-24229, dated July 1,1983 (Time Extension)

Dear Sir:

.The NRC was notified of a Potentially Reportable Deficiency in Reference (A), an Interim Report was transmitted by Reference (B), and a Time Extenalon was requested by Reference (C). At that time, it was estimated that a Final Report would be available by August 19, 1983.

Due_to the extensive investigation and evaluation required, it is now expe:ted that this information will be finalized by October 23, 1983, c

when a complete report will be submitted.

There is no new information or change to the Interim Report at this time.

Very truly yours,

(

CA.AA A

P

[.'

E. E. Van Brunt, Jr.

[

p APS Vice President Nuclear Projects Management

.s ANPP Project Director EEVBJr/RQT:ske cc: See Attached Page 2 8308300442 830819 PDR ADOCK 05000528 l

1p S

PDR 187

U. S. Nuclear Regulatory Commission Attention:

Mr. D. M. Sternberg, Chief ANPP-27592-RQT/BSK August 19, 1983 Page 2 cc:

Richard DeYoung, Director Of fice of Inspection and Enforcement U. S. Nuclear Regulatory Cummission Washington, D. C. 20555 T. G. Woods, Jr.

C. C. Andognini J. A. Roedel D. B. Fasnacht A. C. Rogers B. S. Kaplan W. E. Ide J. Vorces J. R. Bynum P. P. Klute/D. D. Green A. C. Gehr W. J. Stubblefield W. C. Bingham R. L. Patterson R. W. Welcher R. M. Grant D. R. Hawkinson L. E. Vorderbrueggen G. A. Fiorelli Records Center Institute of Nuclear Power Operations 1100 Circle 75 Parkway - Suite 1500 Atlanta, Georgia 30339 J. C. Self S. R. Frost