Interim Deficiency Rept DER 83-10 Re Main Steam Relief Valve Tests Exceeding Specified 5% Blowdown Limit.Initially Reported on 830228.Due to Extensive Investigation Required, Final Rept Will Be Delayed Until 831011
ML20080B348
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 07/25/1983
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Sternberg D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
10CFR-050.55E, 10CFR-50.55E, ANPP-27394-RQT, DER-83-10, NUDOCS 8308050416
Download: ML20080B348 (2)


Text

_ _ _ _ _ _ _ _ _ - _ _

'f@fE0 Arizona Public Service Company

/# 'y, l P o DOX 21666. PHOENIX. ARIZONA 85036 G! (:,,

m July 25,1983 ANPP-27394-RQT/BSK WJ ! '

U.S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 Attention:

Mr. D. M. Sternberg, Chief Reactor Projects Branch 1 1

Subject:

Time Extension for Report - DER 83-10 A 50.55(e) Potentially Reportable Deficiency Relating to Main Steam Relief Valve Testa Exceed Specified Five Percent Blowdown Limit File: 83-019-02 6, D.4.3 3.2.

Re ference:

(A) Telephone Conversation between P. Narbut and G. Duckworth on February 28, 1983 (B) ANPP-23271 dated March 17, 1983 (Interim Report)

(C) ANPP-24004 dated June 8,1983 (Time Extension)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Reference (A), an Interim Report was transmitted by Reference (B), and a Time Extension was requested by Reference (C). At that time, it was estimated that a Final Report would be available by August 18, 1983.

Due to the extensive investigation and evaluation required, it is now expected that this information will be finalized by October 11, 1983, when a complete report will be submitted.

There is no new information or change to the Interim keport at this time.

Very truly y urs, C C2.

CLU._

nu.A)

C.

E. E. Van Brunt, Jr.

APS Vice President Nuclear Projects Management ANPP Project Director EEVBJr/RQT/rb cc:

See Page 2

/[O G308050416 830725 PDR ADOCK 05000528 S

PDR

~Jf07

V U.S. Nuclear Regulatory Commission Page 2 cc:

Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 T. G. Woods, Jr.

G. C. Andognini J. A. Roedel D. B. Fasnacht A. C. Rogers B. S. Kaplan W. E. Ide J. Vorees J. R. Bynum P. P. Klute/D. D. Green A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher R. M. Grant D. R. Hawkinson L. E. Vorderbrueggen G. A. Fiore111 S. R. Frost J. Self Records Center Institute of Nuclear Power Operations 1100 Circle 75 Parkway - Suite 1500 Atlanta, Georgia 30339 l

l l

I