/LL/NOIS POWER COMPANY 0982~L jgtr CLINTON POWER STATION, P.O. B04 678, CLINTON. ILLINOIS 61727 January 26, 1984 Docket 50-461 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555
Subject:
Clinton Unit I Construction Schedule Update
Reference:
USNRC letter dated 5/29/81, H. R. Denton to W. J. Kelley, Illinois Power Company
Dear Mr. Denton:
The referenced letter requested Illinois Power Company to provide a quarterly update concerning the Clinton Unit I construction schedule.
As of December 31, 1983, the target dans for Unit I fuel load remains at January 3, 1986, with commercial operation scheduled for November 1, 1986.
We will continue to submit quarterly updates of the Unit I construction schedule.
Sincerely yours, all l
Vice President RPR/jt cc:
Mr. G. Harrison, NRC Clinton Project Manager NRC Resident Office Illinois Department of Nuclear Safety flovl 4