Interim Deficiency Rept DER 83-10 Re Main Steam Relief Valve Tests Exceeding 5% Blowdown Limit.Initially Reported on 830228.Final Rept Will Be Delayed Until 840301 Due to Extensive Investigation & Evaluation
ML20080A061
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 01/12/1984
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-28609-BSK, DER-83-10, NUDOCS 8402030365
Download: ML20080A061 (2)


Text

Ft

.sj-r TECMED URC Arizona Public Service Company P o. box 21666 e PHOENIX ARIZONA 85036 g

January 12,1984 pgg;yy' ANPP-28609-BSK/TRB U. S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek; CA 94596-5368 Attention: Mr. T. W. Bishop, Director Division of Resident Reactor Projects and Engineering Programs

Subject:

Time Extension For Report - DER 83-10 A 50.55(e) Potentially Reportable Deficiency Relating To Main Steam Relief Valves Tests Exceed Specified 5 Percent Blowdown Limit.

File: 84-019-026; D.4.33.2

Reference:

(A) Telephone conversation between P. Narbut and G. Duckworth on February 28, 1983 (B) ANPP-23271, dated March 17, 1983 (Interim Report)

(C) ANPP-24004, dated June 8, 1983 (Time Extension)

(D) ANPP-27394, dated July 25, 1983 (Time Extension)

(E) ANPP-27975, dated October 7, 1983 (Time Extension)

(F) ANPP-28258, dated November 18, 1983 (Time Extension)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Reference (A), an Interim Report was transmitted by Reference (B), and Time Extensions were requested in References (C), (D), (E), and (F). At that time, it was estimated that a Final Report would be available by January 18. 1984.

Due to the extensive investigation and evaluation required, it is now expected that this information will be finalized by March 1,1984, at which tf aie a complete report will be submitted.

There is no new information or change to the Interim Report at this time.

Very truly yours h

ALAA E. E. Van Brunt, Jr.

APS Vice President, Nuclear ANPP Project Director

.EEVB/TRB:ru cc:. See Page Two 9402030365 840112

.PDR ADOCK 05000528

) g 16_ _2 /

u PDR l

m:

Mr. T. W. BishopL DER 83-10 Page Two ec:

Richard DeYoung, Director Office ~ of Inspection and Enforcement

-U. S. Nuclear Regulatory Commission Washington, D.-C. 20555 T. G. Woods, Jr.

J. A. Roedel.

'D. B. Fasnacht

.A.

C. Rogers B.. S. Kaplan W. E. Ide J. - Vo ree s J. R. Bynum D. D. Green P.'P. Klute A;

C.' Gehr W.J.

Stubblefield W. G. Bingham R.~L. Patterson R. W. Welcher H. Foster D. R. Hawkinson L. E. Vorderbrueggen G..A.

Fiorelli S. R. Frost J. Self D. Canady Recorde Center Institute of Nuclear Power Operations 1100 Circle 75 Parkway, Suite 1500 Atlanta, CA 30339 r