Withdraws 891010 Amend Request to Raise Allowable Containment Leak Rate Limit Due to NRC Delays in Completing Review & Closure of MSIV Leakage Issue Noted in BWR Owners Group Licensing Topical Rept.Request Will Be Resubmitted
ML20079P105
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 11/05/1991
From: Floyd S
CAROLINA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NLS-91-265, TAC-M74109, TAC-M74110, NUDOCS 9111120227
Download: ML20079P105 (2)


Text

_ _ _ _ . . .. -

y -s e<

Carolina Powet & 13ght Compey SERIAL: NLS 91265 NOV 051991 TSC 89TSB02 United States Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, DC 20555 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS.1 AND 2 DOCKET NOS. 50 325 & 50 324/ LICENSE NOS. DPR-71 & DPR-62 WITHDRAWAL OF LICENSE AMENDMENT REQUEST CONTAINMENT LEAKAGE LIMIT (NRC TAC NOS 74109 AND 75110) v4 m Gentlemen:

By letter dated October 10,1989 (Serist: NLS 89 097), Carolina Power & Light Company submitted a license amendment request to raise the allowable containment leak rate (L) for the Brunswick Steam Electric Plant, Units 1 and 2 from 0.5 volume percent per day to 1.0 volume percent per day. On March 5,1990, CP&L received a request for information, via telecopy, concerning the amendment request. The information was requested by the Staff to support independent offsite and control toom operator dose calculations.

During subsequent discussions with the NRC Staff, CP&L was informcd that its response could make use of certain assumptions used by the BWR Owners' Group in their licensing topical report for the MSIV leakage issue, once the topical report was approved by the Staff. The Company acknowledged the need for Staff approval of this BWR Owners' Group initiative before a response to the March 5,1990 request could be provided.

Due to NRO Staff delays in completing review and c.losure of the MSIV leakage rate issue for the BWR Owners' Group, the Con pany has been unable to complete its response to the March 5, 1990 request. As a result of these delays, the NRR Project manager has recently requested that CP&L either respond to the March 5,1990 request or withdraw the October 10,1989 license amendment request. - Accordingly, the Company hereby withdraws its license amendment request dated October 10,1989; however, the Company intends to resubmit this amendment request for expeditious Statf approval following completion of the Staff's review of the BWR Owners' Group MSIV leakage licensing topical report.

Please refer any questions regarding this submittal to Mr. W. R. Murray at (919) 546-4661.

Yours very truly, S. D. Floyd Manager Nuclear Licensing Section WRM/wrm fitrt-wd.wpf) ligm W PycSm'EC E:IiW#rdi=ILErm @ =EC u t er fweme see . p o N ,159 . w y oC ' ' h 9111120227 911105 PDR-- ADOCK 03000324 P pga

+

t-Document Control Desk NLS-91-265 / Page 2 cc: Mr. Dayne Brown Mr. S. D. Ebneter Mr. N. B. Le Mr. R. L. Prevatte