ML20078P054

From kanterella
Jump to navigation Jump to search
Forwards Plans for Interim Operation of HVAC Sys,For Concurrence.Plans Describe Manner in Which Interconnected Available HVAC Equipment Will Be Tested & Operated to Support Fuel Load of Unit 1
ML20078P054
Person / Time
Site: Byron  Constellation icon.png
Issue date: 10/27/1983
From: Tramm T
COMMONWEALTH EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20078P057 List:
References
7510N, NUDOCS 8311030182
Download: ML20078P054 (1)


Text

.

  1. h Commonwealth Edison

, [iC ) one First National P!arl Chicago, lilinois Addr:ss R; ply to: Post Othca Box 767

\ Chicago, lifinois 60690 October 27, 1983 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Byron Generating Station Units 1 and 2 Interim Operation of HVAC Systems NRC Docket Nos. 50-454 and 50-455

Dear Mr. Denton:

This letter is to inform the NRC of our plans for interim operation of the Byron Station ventilation systems. NRC concurrence is requested.

As documented in the Byron /Braidwood FSAR, parts of the Unit 1 and Unit 2 auxiliary building HVAC ductwork are interconnected. Not all of the HVAC equipment for both units will be available for service at the time of Unit 1 fuel loading. Operation of Unit 1 without full operability of all HVAC equipment was not contemplated in the FSAR. Therefore, Attachments A, B, and C to this letter describe the manner in which the available HVAC equipment will be tested and operated to support fuel load of Byron Unit 1. Our basis for concluding that these plans are adequate is also provided.

Please indicate in the acceptability of these plans at your earli-est convenience. Questions should be directed to this office.

Very truly yours, h, f/K T. R. Tramm Nuclear Licensing Administrator im Attachment

([l 8311030182 831027 PDR ADOCK 05000454

. A. .PDR; ,

7510N

,-, ,