Final Deficiency Rept Re Contact Leads on GE Hma Relays. Initially Reported on 820818.Evaluation Revealed No Instances of Insufficient Lead to Terminal Spacing.Potential Deficiency Not Applicable to Unit 2 Hma Relays
ML20078N360
Person / Time
Site: Perry 
Issue date: 10/18/1983
From: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, RDC-61(82), NUDOCS 8310250483
Download: ML20078N360 (1)


Text

T [t [

A{

!)?, i i?

i'

.1 61 #

l' V i 1 (2

(' p F " ().

'9 V r

, k t 's i! p L L L !> si ' I p>

I i~ L. 'i iti s is ti ! I 1i (~

d It G s ii ii e t i s I,

l/ u i

1 -

.s r

P.o. Box 5000 - CLEVELAND. OHIO 44101 - TELE. PHONE (216) 622-9800 - ILt *;MINATING BLDG.

- 5$ PUBIICSQUARE Serving The Best location in the Nation MURRAY R. EDELMAN er M, UM vicE PRESIDENT NUCLE A R Mr. James G. Keppler Regional Administrator, Region III Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 RE: Perry Nuclear Power Plant Docket Nos. 50-440; 50-441 Contact Leads on HMA Relays Supplied by General Electric

[RDC 61(82)]

Dear Mr. Keppler:

This letter serves as the final report pursuant to 10CFR50.55(e) on the potential significant deficiency concerning HMA relays supplied to Perry Nuclear Pcver Plant by the General Electric Company (GE) for use in Unit 2.

Mr. E. Riley of The Cleveland Electric Illuminating Company (CEI) originally notified Mr. P. Pelke of your of fice on August 18, 1982, that this potential deficiency was being evaluated by CEI.

The first interim report, dated September 17, 1982, contained a description of the deficiency and the method planned for completion of the evaluation. The final report fer the Unit I relays was contained in our letter dated November 24, 1982.

This letter contains the results of the evaluation for the Unit 2 relays.

Evaluation of Deficiency The inspection of the Unit 2 HMA relays was completed as required by GE Field Disposition Instruction (FDI) WPMM, The evaluation revealed no occurrences of insufficient lead to terminal spacing in the relays. This indicates the identified potential significant deficiency is not applicable to Perry's Unit 2 HMA relays.

Please call if you have any questions.

Sincerely, 8310250403 831018 Murray R. Edelman PDR ADOCK 05000441 Vice President S

PDR Nuclear Group MRE:pab cc:

Mr. M. L. ?.,11dner U.S. Nuclear Regulatory Commission NRC Site Office c/o Document Management Branch Washington, D.C.

20555 Director Office of Inspection and Enforcement Records Center, SEE-IN U.S. Nuclear Regulatory Commis ion Institute of Nuclear Power Operations 1100 circle 75 Parkway, Suite 15 p op / ]

Washington, D.C.

20555 g%

30339 Atlanta, Georgia