Amends 195 & 186 to Licenses DPR-77 & DPR-79,respectively, Removing 900 Rpm EDG Surveillance Test Criteria & Requirement That Plant Be Shut Down for Performance of Interdependence DG Tests
ML20078M839
Person / Time
Site: Sequoyah  
(DPR-77-A-195, DPR-79-A-186)
Issue date: 02/09/1995
From: Hebdon F
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20078M841 List:
References
NUDOCS 9502140415
Download: ML20078M839 (10)


Text

e aug g!

UNITED STATES 3

j NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C.11eeH001 TENNESSEE VALLEY AUTHORITY DOCKET NO. 50-327 SE000YAH NUCLEAR PLANT. UNIT 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No.195 License No. DPR-77 1.

The Nuclear Regulatory Commission (the Commission) has found that:

A.

The application for amendment by Tennessee Valley Authority (the licensee) dated December 16, 1994, with supplemental information supplied January 19, 1995, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act),

and the Commission's rules and regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

9502140415 950209 DR ADOCK 05000327 PDR

2.

Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment and paragraph 2.C.(2) of Facility Operating License No. DPR-77 is hereby amended to read as follows:

(2) Technical Soecifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No.195, are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications.

3.

This license amendment is effective as of its date of issuance, to be implemented within 45 days.

FOR THE NUCLEAR REGULATORY COMMISSION b

yjn-y m Fr Wick J. Hebdon, Direct Project Directorate 11-4 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation

Attachment:

Changes to the Technical Specifications Date of Issuance: February 9, 1995 j

a l

l ATTACHMENT TO LICENSE AMENDMENT NO. los FACILITY OPERATING LICENSE NO. DPR-77 i

DOCKET NO. 50-327 Revise the Appendix A Technical Specifications by removing the pages identified below and inserting the enclosed pages. The revised pages are identified by the captioned amendment number and contain marginal lines indicating the area of change.

REMOVE INSERT-3/4 8-3 3/4 8-3 3/4 8-5 3/4 8-5 1

[

p i

~

ELECTRICAL IM ER SYSTEMS M MJIREMENTS (Continued) 4.8.1.1.2 Each diesel generator set shall be demonstrated OPERABLE:

a.

In accordance with the frequency specified in Table 4.8-1 on a STAGGERED TEST BASIS by:

1.

Verifying the fuel level in the engir.e-mounted day tanks.

2.

Verifying the fuel level in the 7 day tank.

3.

Verifying the fuel transfer pump can be started and transfers fuel from the storage system to the engine mounted fuel tanks.

4.

  • Verifying the diesel starts from ambient condition and achieves in less than or equal to 10 seconds generator voltage and frequency of 6900 i 690 volts and 60 i 1.2 Hz. The diesel generator shall be started for this test by using one of the following signals with startup on each signal verified at least once per 124 days:

a)

Manual.

b)

Simulated loss of offsite power by itself, c)

An ESF actuation test signal by itself.

5.

  • Verifying the generator is synchronized, loaded between 3960 kw and 4400 kw in less than or equal to % seconds, and operates for greater than or equal to 60 minutes, and 6.

Verifying the diesel generator is aligned to provide standby power to the associated shutdown boards.

b.

At least once per 31 days and after each operation of the diesel where the period of operation was greater than or equal to I hour by checking for and removing accumulated water from the engine-mounted i

fuel tanks.

c.

At least once per 92 days and from new fuel oil prior to addition to the 7-day tanks by verifying that a sample obtained in accordance with ASTM-D270-1975 has a water and sediment content of less than or equal to.05 volume percent and a kinematic viscosity 9100*F of l

greater than or equal to 1.8 but less than or equal to 5.8 centi-stokes when tested in accordance with ASTM-D975-77, and an impurity level of less than 2 mg. of insolubles per 100 ml. when tested in accordance with ASTM-D2274-70.

  • The diesel generator start (10 sec) and load (60 sec) from standby conditions shall be performed at least once per 184 days in these surveillance tests.

All other diesel generator engine starts and loading for the purpose of this surveillance testing may be preceded by an engine idle start, followed by gradual acceleration to synchronous speed (approximately 900 rpm),

l synchronization, and gradual loading.

SEQUOYAH - UNIT 1 3/4 8-3 Amendment No. 52,64,99,109, 137,173, 195 i

FLECTRICAL 20WER SYSTEMS SURVEILLANCE REQUIREMENTS (Continued) c)

Verifying that all automatic diesel generator trips, except engine overspeed and generator differential, are automati-cally bypassed upon loss of voltage on the shutdown board and/or safety injection actuation signal.

7.

Verifying the diesel generator operates for at least 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

During the first 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to 2.25 hours2.893519e-4 days <br />0.00694 hours <br />4.133598e-5 weeks <br />9.5125e-6 months <br /> of this test, the diesel generator shall be loaded between 4620 kw and 4840 kw and between 2380 kvar and 2600 kvar and during the remaining hours of this test, the diesel generator shall be loaded between 3960 kw and 4400 kw and between 2140 kvar and 2370 kvar.

The generator voltage and frequency shall be 6900 i 690 volts and 60 i 1.2 Hz within 10 seconds after the start signal; the steady state generator voltage and frequency shall be maintained within these limits during this test. Within 5 minutes after completing this 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> test, perform Specification 4.8.1.1.2.d.4.b.

8.

Verifying that the auto-connected loads to each diesel generator do not exceed the continuous rating of 4400 kw.

9.

Verifying the diesel generator's capability to:

a)

Synchronize with the offsite power source while the genera-

)

tor is loaded with its emergency loads upon a simulated i

restoration of offsite power.

b)

Transfer its loads to the offsite power source, and c)

Be restored to its shutdown status.

10. Verifying that the automatic load sequence timers are OPERABLE with the setpoint for each sequence timer within i 5 percent of its design setpoint.
11. Verifying that the following diesel generator lockout features prevent diesel generator starting only when required:

a)

Engine overspeed b) 86 GA lockout relay e.

At least once per 10 years or after any modifications which could affect diesel generator interdependence by starting the diesel generators simultaneously and verifying that each diesel generator achieves in less than or equal to 10 seconds, 6900 1 690 volts and 60 i 1.2 Hz.

SEQUOYAH - UNIT 1 3/4 8-5 Amendment No. 52,64,109,114, 137,173, 195

,p.cy't g'

UNITED STATES y

,, j NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 30006 0001

/

TENNESSEE VALLEY AUTHORITY DOCKET NO. 50-328 SE000YAH NUCLEAR PLANT. UNIT 2 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No.186 License No. DPR-79 1.

The Nuclear Regulatory Commission (the Commission) has found that:

A.

The application for amendment by Tennessee Valley Authority (the licensee) dated December 16, 1994, with supplemental information supplied January 19, 1995, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act),

and the Commission's rules and regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

t i

~. '

2.

Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment and paragraph 2.C.(2) of Facility Operating License No. DPR-77 is hereby amended to read as follows:

1 (2) Technical Soecifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No.186 are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications.

3.

This license amendment is effective as of its date of issuance, to be implemented within 45 days.

FOR THE NUCLEAR REGULATORY COMMISSION f

)

Q Fre r ck J. Hebd., Director Project Directorate 11-4 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation

Attachment:

Changes to the Technical Specifications Date of Issuance: February 9, 1995 9

4 i

l

1 ATTACHMENT TO LICENSE AMENDMENT NO.186 FACILITY OPERATING LICENSE NO. DPR-79 DOCKET N0. 50-328 Revise the Appendix A Technical Specifications by removing the pages identified below and inserting the enclosed pages. The revised pages are

' identified by the captioned amendment number and contain marginal lines indicating the area of change.

REMOVE INSERT 3/4 8-3 3/4 8-3 3/4 8-5 3/4 8-5 i

t 1

1 m.,...

ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS Montinued)

J 4.8.1.1.2 Each diesel generator set shall be demonstrated OPERABLE:

a.

In accordance with the frequency specified in Table 4.8-1 og a STAGGERED T'ST BASIS by:

2 1.

Verifying the fuel level in the engine-mounted day tanks.

2.

Verifying the fuel level in the 7 day tank.

3.

Verifying the fuel transfer pump starts and transfers fuel from the storage system to the engine mounted fuel tanks.

4.

  • Verifying the diesel starts from ambient condition and achieves in less than or equal to 10 seconds generator voltage and j

frequency of 6900 i 690 volts and 60 i 1.2 Hz. The diesel generator shall be started for this test by using one of the

)

following signals with startup on each signal verified at least once per 124 days:

a)

Manual.

b)

Simula+ed loss of offsite power by itself.

c)

An ESF actuation test signal by itself.

5.

  • Verifying the generator is synchronized, loaded between 3960 kw and 4400 kw in less than or equal to 60 seconds, and operates for greater than or equal to 60 minutes, and 6.

Verifying the diesel generator is aligned to provide standby power to the associated shutdown boards.

b.

At least once per 31 days and after each operation of the diesel where the period of operation was greater than or equal to I hour by checking for and removing accumulated water from the engine-mounted fuel tanks.

c.

At least once per 92 days and from new fuel oil prior to addition to the 7-day tanks by verifying that a sample obtained in accordance with ASTM-D270-1975 has a water and sedimed content of less than or equal to.05 volume percent and a kinematic viscosity 9 100*F of greater than or equal to 1.8 but less than or equal to 5.8 centistokes when tested in accordance with ASTM-D975-77, and an impurity level of less than 2 mg. of insolubles per 100 ml. when tested in accordance with ASTM-D2274-70.

  • The diesel generator start (10 sec) and load (60 sec) from standby conditions shall be performed at least once per 184 days in these surveillance tests.

All other diesel generator engine starts and loading for the purpose of this surveillance testing may be preceded by an engine idle start, followed by gradual acceleration to synchronous speed (approximately 900 rpm),

l synchronization, and gradual loading.

l SEQUOYAH - UNIT 2 3/4 8-3 Amendment No. 44,56,88,99, 123,1f,4, 186 l

ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS (Continued) c)

Verifying that all automatic diesel generator trips, except engine overspeed and generator differential, are automati-cally bypassed upon loss of voltage on the shutdown board and/or safety injection actuation signal.

7.

Verifying the diesel generator operates for at least 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

During the first 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to 2.25 hours2.893519e-4 days <br />0.00694 hours <br />4.133598e-5 weeks <br />9.5125e-6 months <br /> of this test, the diesel l

generator shall be loaded between 4620 kw and 4840 kw and between 2380 kvar and 2600 kvar and during the remaining hours of this test, the diesel generator shall be loaded between 3960 kw and 4400 kw and between 2140 kvar and 2370 kvar.

The generator voltage and frequency shall be 6900

  • 690 volts and 60
  • 1.2 Hz within 10 seconds after the start signal; the steady state generator voltage and frequency shall be maintained within these limits during this test. Within 5 minutes after completing this 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> test, perform Specification 4.8.1.1.2.d.4.b.

8.

Verifying that the auto-connected loads to each diesel generator do not exceed the continuous rating of 4400 kw.

9.

Verifying the diesel generator's capability to:

a)

Synchronize with the offsite power source while the generator is loaded with its emergency loads upon a simulated restoration of offsite power.

b)

Transfer its loads to the offsite power source,. and c)

Be restored to its shutdown status.

10. Verifying that the automatic load sequence timers are OPERABLE with the setpoint for each sequence timer within
  • 5 percent of its design setpoint.
11. Verifying that the following diesel generator lockout features prevent diesel generator starting only when required:

a)

Engine overspeed b) 86 GA lockout relay e.

At least once per 10 years or after any modifications which could affect diesel generator interdependence by starting the diesel generators simultaneously and verifying that each diesel generator achieves in less than or equal to 10 seconds, 6900

  • 690 volts'and 60
  • 1.2 Hz.

SEQUOYAH - UNIT 2 3/4 8-5 Amendment No. 41,56,123,164, 186

.