Monthly Operating Rept for Aug 1983
ML20078K698
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 09/01/1983
From: Brons J, Kelley L
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
IP-LK-2958, NUDOCS 8310190202
Download: ML20078K698 (7)


Text

..

8 .

OPERATING DATA REPORT DOCKET NO. 50-286 DATE 09/01/83 COMPLETED BY L. Keliv TELEPHONE '914) 739-8200 OPERATING STATUS Notes

1. Unit Name: Indian Point No. 3 Nuclear Power Plant
2. Reporting Period: August 1983
3. Licensed Thermal Power (MWt): 3025
4. Nameplate Rating (Gross MWe): 1013
5. Design Electrical Rating (Net MWe): 965
6. Maximum Dependable Capacity (Gross MWe): 1000
7. Maximum Dependable Capacity (Net ,MWe): 965
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:
9. Power Level To Which Restricted,If Any (Net MWe):
10. Reasons For Restrictions.If Any:

This Month Yr.-to-Date Cumulative

11. Hours in Reporting Period 744 5831.0 61,392.0
12. Number Of Hours Reactor Was Critical 0 333.7 34,424.5
13. Reactor Reserve Shutdown Hours 0 0 0
14. Hours Generator On Line 0 229.1 33,142.2
15. Unit Reserve Shutdown Hours 0 0 0
16. Gross Thermal Energy Generated (MWH) 0 282,244 86,425,645
17. Gross Electrical Energy Generated (MWH) 0 68,310 26,366,610
18. Net Electrical Energy Generated (MWH) 0 60,735 25,244,178
19. Unit Service Factor 0 3.9 54.0
20. Unit Availability Factor o 3.9 54.0
21. Unit Capacity Factor (Using MDC Net) 0 1.1 42.6
22. Unit Capacity Factor (Using DER Net) 0 1.1 42.6
23. Unit Forced Outage Rate 100 88.6 18.0
24. Shutdowns Scheduled Over Next 6 Months (Type. Date.and Duration of Each1:

25 If Shut Down At End Of Report Period. Estimated Date of Startup: Januaw 1984 26 Units In Test Status (Prior to Commercial Operation): Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION 8310190202 830901 ]d

(

PDR ADOCK 05000286 R PDR

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-286 UNIT = Indian Point #3 DATE September 1, 1983 COMPLETED BY L- Keliv TELEPHONE - (914)739-8200 MONTH Auoust 1983 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 1 0 17 0

'2 0 gg 0 3 _ 0 39 0 4 0 20 0

. 5 0 0 21 0

6 22 0

._ 7 0 3 o 8 0 24 0 9 0 25 0 10 0 26 0 11 0 27 0 12 0 0 28 13 0 29 0 14 0 0 30 15 0 33 0 16 0 l

( INSTRUCTIONS On this format, list the average daily unit power levelin MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.

(9/77)

~

DOCKET NO. 50-286 .

UNIT SifUTDOWNS AND POWER REDUCTIONS No. 3 .

UNIT NAME DATE september 1, 1983 COMPLETED BY f, . Kelly .

REPORT MONTH August 1983 TELEPHONE 914-739-R200 c e. 4 u, E c

~

?jg Licensu gg gm,< Cause & Corrective No Date F k _$ $

6gx Event 3.? Action to

  1. Ei 3 0 O CO "

$ 5l Report a mO @"3 Prevent Recurrence 6

03 830618 F 744 A 3 N/A N/A Electrical malfunction in the main generator.

I 2 3 4 F: Forced Reason: Method: Exhibit F-Instructions S: Ssheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B Maintenance of Test 2 Manual Scram. Entry Sheets for Licensee C-Refueling 3 Automatic Scram. Event Repost ILER) File tNUREG-D-Regulatory Restriction 4-Other (Explain) 0161)

E-Operato Training & License Examination F-Administ rative 5 G-Operational Estor (Explain) 1:xhibit II- Same Source 19/77) Il Other (Explain)

H N 3 T O 8 N I 9 O T 1 M C e A r t i s E w u V g I n u T e A C k E o R r R b O

C d e

r i

p a

e R

N O

I T

e T r R C i O N w P U E F e R L c A a E M r C t N

A t N a E e T h N

I n A e M k o

Y r L B H

T N

O M

T N e E c O M a e P r .

I T U t Q

E a I

e I

3 d3 i#

c

_ Ati cu i c

_ rr oi BC E

T A 3 D 8

/

9

/

8 I 2 R 1 W 8 M 3

MONTHLY I & C CATEGORY I REPORT August 1983 Month W.R. # DATE EQUIPMENT HALFUNCTION CORRECTIVE ACTION l IC-1-2118 l 6-15-83 l Component Cooling Radiation Local meter in control room Replaced meter I  ! Monitor (R17B) defective IC-1-2196 ! 7-21-83 Reactor Protection Train A Relay blows fuses on control Replaced relay Source Range Trip Relay NC31DX drawer l l I I

'IC-1-2222 l 6-20-83 Steam Cenerator Blowdown Meter reads low Cleared ground on i Radiation Monitor (R19) detector cable l l I l

! I i i I

l l

l i

l l

l I

SUMMARY

OF OPERATING EXPERIENCE August 1983 Indian Point Unit 3 remains in a forced outage caused by a malfunction in the main electrical generator.

Repairs are now in nrogress an'd it is estimated that the unit will be returned to service in January 1984.

i i

l l

D .

Indian Point 3

. Nuclear Power Plant P.O. Box 215 Buchanan, Newttk 10511 D 914 739.8200

  1. > NewYorkPbwer 4# Authority September 9, 1983 IP-LK-2958 Director, Nuclear Reactor Regulation Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Dear Sir:

Encloseo you will find two copies of the monthly operating report relating to Indian Point 3 Nuclear Power Plant for the month of August, 1983.

Verytrulyyo ,

, N Yt N#

jJohn C. Brens Resident Manager LK/gg Enclosures cc: Director, Office of Inspection & Enforcement (40 Copies) c/o Distribution Services Branch, DDC, ADM U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Dr. Thomas E. Murley, Regional Administrator Region 1 U. 3. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pennsylvania 19406 Mr. Leroy W. Sinclair New York Power Authority 123 Main Street White Plains, New York 10601 IP 3 Resident Inspector's Office George Wilverding (SRC), WP0 pLf J. P. Bayne, WP0 INPO Records Center Suite 1500 1100 circle 75 Parkway Atlanta, Georgia 30339

-