STONE & WEBSTER MICHIGAN, INC.
P.O. Box 2325. BOSTON. MASSACHUSETTS O2107
" United States Nuclear 'tegulatory Commission August 17,"1983
. Midland Site Resident Office
" Route 7 J. O. No. 14358 Midland, MI. 48640 Ref. MPF 4'/
Attention Mr. R.
Cook RE: DOCKET NO. 50-329/330 MIDLAND PLANT - UNITS 1 & 2 INDEPENDENT ASSESSMENT OF UNDERPINNING REPORT NO. 47 A copy of the Independent Assessment nf Underpinning, Weekly Report No. 47 for the period of August 7, 1983 through August 13,1983 is enclosed with this letter. Included as attachments, are the minutes of the daily meetings held during the week between members of the Assessment Team and Site Engineering, Construction, and Quality Assurance personnel.
If you have any questions with respect to this report, please contact me at 617-589-2067.
V y truly yours, hd4 Yhe A. Stanle ucks Project Manager Enclosures ASL/pd I
t 5:
l 5
8310170634 831003 PDR ADOCK 05000329 G
J. O. No. 14358 Midland Plant Units 1 & 2
- Jnde' pendent Assessment of Underpinning Weekly Report No. 47 August 7, 1983 through August 13, 1983
~
P}ersonr.-1onSite
- ~
Stone & Webster Michigan, Inc.
P.
Barry 8/11 - 8/13 W.
Kilker 8/8 - 8/13 B.
Holsinger 8/8 - 8/11 S.
Lucks 8/11 - 1/12 P.
Majeski 8/10 - 8/13 Parsons, Brinckerhoff Michigan, Inc.
J.
Ratner 8/10 - 8/13 F.
Balsamo 8/10 - 8/12 Meetings Attended Date Represented Purpose 8/8 8/10 Stone & Webster Daily Meetings 8/12 Bechtel Consumers Power Parsons 8/10 Stene & Webster Weekly Engineering Bechtel Construction Coord-Consumers Power ination Meeting 8/12 Stone & Webster Direct-hire Personnel Bechtel Training Commitments Consumers Power Activities Construction:
Pier E8:
Load transfer to turbine building and routine rejacking completed.
E8 Grillage: Post and cap beam installed on edge of containment mat.
Pier E10:
The Pier remained on active jacking throughout the week to obtain ehgineering information.
Kh-10 Drift:
Drift excavation and drift support systee nearly complete.
Pfer W8: Load transfer to turbine building completed.
Three diy period of routine rejacking in progress.
1 W8 Grillage:
Post and cap beam installed on edge of containmenf mat.
Pier W10:
The pier remained on active jacking throughout the week to obtain engineering information.
2 J. O. No. 14358 Midirnd Plcnt Units 1 & 2
, Independent Assessment of Underpinning KC-3:
Drift excavation begun but work is slow because excavation face is 100 percent fill concrete.
SWPS:
Dewatering wells and soldier pile installation continued; Work on service water pipe replacement was stopped to re-evaluate construction o'[rocedures and retrain Contractor direct hire. and supervisory personnel.
BWST:
Installation of shear connector bolts continued.
Backfilling was l'nitiated. Work curtailed late in the week to permit re-evaluation of construction procedures and retrain Contractor direct hire and supervisory personnel.
Quality Control 1.
Visually checked welding for comparison with welding inspection reports for E/W8 transfer frames.
~
2.
Attended training session for PQCI 1,018 (6), installation of structural s teel.
3 Reviewed material receiving report.
Observations Construction:
A number.of NCR's written on welding performed in the UAT's resulted in FSO's voluntary suspension of Contractor direct hire work.
The purpose of this suspension was to allow time to evaluate and revise construct-ion and supervisory methods, and for retraining of direct hire and supervisory personnel.
The NCR's apparently were as much a result of commanication gaps between FSO personnel and between FSO and MPQAD as they were deficiencies in the work. The FSO response to this situation was proper and the contemplated changes are correct in the opinion of the Assessment Team.
During load transfer of E/W8 to the turbine building, a small upward movement of a few mils en the EPA was noted. Movement of this magnitude which is not excessive, can be expected.
In fact, this movement reduced the differential settlement across the Auxiliary Building.
Quality Control 1.
The welding inspection reports for the E/WB transfer frames were found to be complete and accurate.
2.
The training session for revisions to PQCI 1.018 (6), installation of structural steel, was complete and the presentation was clear.
3 A review by the Assessment Team of QCIR No. R-1CO 20818 resulted in NfR No. 14 because of two instances where nuts were supplied and accepted that do not meet the specified requirements.
~:
Work Activity Packages Resolution of the comments / question of WAP's 44,50 and 51 remaig open.
Nonconformance, Identification Report NIR No.
Description Date 14 Auxiliary Building Underpinning (Opened) ( Closed) 8/11/83 h
3 J. O. No. 14358 Midicnd Plcnt Units 1 & 2
. Independent Assessment of Underpinning Open Items The following is a listin6 of all open items from ' he Daily Meeting Notes with t
Bechtel and the Weekly Meeting with MPQAD.
Carry over items from east weeks which have been closed out this week are also listed.
~. '
Item No.
Description Closure Reference W'R.25,pg.5 Commitment to assess Open training and personnel records.
W.R. 42, pg.3 Commitment to evaluate open response to Grillage Installation PQCI.
43-4Q Receipt Package Inspection Open 43-50 Grillage Installation open Questions 44-7 Request for Chronology Open of Events Surrounding Reoccurrence of Loose Washers on W8 N-S Bulkhead 44-20 Resolution of a Question Open on the Adequacy of the Procedure on the Tieback and Strut Installation.
44-20 Grillage Beam Receipt Open Inspection Package 44-30 Status of Questions on Open Grillage Beam PQCI 45-17 Existing Concrete Mix 47-19 Slump Inadvertency Margin 45-7Q Status of QA NCR on QC 47-10 0
Certification 4 8Q Discussion on Mechanism Open r
of Identifying Quality Concerns.
5 2
46-14 Leveling Plate Overlap 47 2 onto FIVP Mat
4 J. O. Ns. 14358 Midicnd Plcnt Unito 1 & 2 Independent Assessment of Underpinning Item No.
Description Closure Reference 47-22 Direct Hire Work
.Open Retraining i
i l
l l
i O
.I
~:
$0*- WC Vdko-h A-)
l Woject T.ngineer Projectpnager
Not33 cf Daily Mesting Independent Assessment of Underpinning j
Midland Plant Units 1 & 2 Cdnsumers Power Company Held at Midland Site Location Midland, Michigan August 8, 1983 Pr:e}sentFor:
Cossumers Power Bechtel MPQAD Stone & Webster D.
Puhalla J.
Fisher W.
Lytle W.
Kilker E.
Cviki B.
Holsinger J.
Gaydos Parsons None Purpose This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant, Units 1 & 2.
Discussion Item 47 Status of E/W8 Load Transfer.
J.
Fisher reported that rework on certain welding, completion of the instrumentation and the required FSO and QC inspections were completed over the weekend. Load transfer is expected to commence today.
( CLOSED Item )
Item 47 Leveling Plate FIVP Overlap.
E.
Cvikl stated that measurements confirmed a slight overlap of the leveling plate nearest the containment from the EPA onto the FIVP mat. A FCR will likely be written to block out this corner prior to grout placement.( CLOSES OUT ITEM 46-14 )
Item 47 SWPS Well Installations.
J.
Fisher reported 2 shifts are working again on well installations. However, due to recent commitments on work coverage by FSO Field Engineers, outside work will be done by day shift crews and inside the structure work by night shift crews. ( CLOSED ITEM )
Item 47 MPQAD Welding Consultant.
W.
Kilker requested a status report on the activities of the consultant. W.
Ly,tle will respond. ( OPEN ITEM )
It'em 47 Status of Grillage Beam Rework.
Wh Kilker requested the status of the grillage beam rework. J.$ Fisher will respond. ( OPEN ITEM )
Item 47 Material Storage Procedure.
W.
Kilker reported that V.
Madill questioned the clarity of the Level B storage requirement section of the SWP procedure on material handling, storing, and controlling.
J.
Fisher agreed the present structure of the section could be misleading. FSO will respond. ( OPEN ITEM )
2
.Notsa of Daily Me ting Independent Assessment of Underpinning
. Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Location Midland, Michigan August 8, 1983
~_
Ithm 47 E8 Lower Leveling Plate Grout Repair.
~
Wi)Kilkerquestionediftheminorcosmetic-typegroutrepair(greatest dimension was 2 inches } required the same testing verificatiLn as an initial installation. For example, on this repair of a few cubic inches i 20 test specimens were taken.
J.
Gaydos replied that a less commonly used grout type
( Set 45) was used and this usage probably resulted in the higher number of test specimens.
In any case, procedural test requirements would not be any less for a repair than for an initial installation ( CLOSED ITEM )
Item 47 E/W8 Grillage Leveling Plates.
In response to a question by W. Kilker on the plate modification required to pressure grout the grillage leveling plates, J.
Fisher stated an' FCR is being processed and in addition a procedural change is required to designate fabrication changes. ( CLOSED ITEM )
7.-
2
~
b
---J
NatOs of Daily Me: ting Independent Assessment of Underpinning
. Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Location Midland, Michigan
~
August 9, 1983
~.
No meeting.tas held on this date.
.E; e
d, e
i i.,
~
t Not22 cf Daily Mesting Independent Assesement of Underpinning tudlahd' Plant Units 1 & 2 Consume *rs Power Company Held at Midland Site Location Midland, Michigan J.
Au.6ust 10, 1983 Present For:
Consumers Power Bachtel MPQAD Stone & Webster G.
Murray J.
Fisher None W.
Kilker E.
Cviki P.
Majeski J.
Gaydos Parsons None Purpose This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant, Units 1 & 2.
Discussion Item 47 Status of Grillage Installation.
l All NPS fabricated materials have been released to the Subcontractor for installation.
J.
Fisher explained that FCRs have been prepared to address tolerances on the beam, frame, bracing and column installation. Discussions are on-going to understand the intent of the tolerances to avoid misinterpre-tations once the pieces are in-place. ( CLOSES OUT ITEM 47-5 )
Item 47 Superplasticized Concrete.
J.
Gaydos reported that the grout used to " slick" the pumplines in conjunct-ion with the new mix design must be qualified.
Completion of the testing is expected this week. ( CLOSED ITEM )
Item 47 Installation Accessories.
i J.
Fisher explained that installation accessories used by construction will not be shown on design drawings but rather will be designated on vendor drawings or field sketches. ( CLOSED ITEM )
Item 47 EPA Settlement Trends.
E.
Cviki reported the EPA portions of the auxiliary building moved upward
[
a few mills during the recent load transfer of the E/W8 piers.
In addition, i
the recent trend has been toward a significant reduction in the differential settlement rate across the auxiliary building. ( CLOSED ITEM )
It$m47 Inspection of UAT Work Platform Installation.
l J.
Fisher explained that the inspection of the welding at the ult revealed j
a number of deficiencies. Discussions are underway within FSO t6r. determine the cause of this situation and what action is required to prevent reoccurrence.
( OPEN ITEM )
l l
l
2 J
Notas cf Daily Mesting Independent Assessment of Underpinning Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Location Midland, Michigan
^
August 10, 1983
' Item 47 Clarification of Storage Requirements.
J.
Fisher said the appropriate section of the SWP procedure will be clarified to more clearly reflect the material storage requirements,
( CLOSES OUT ITEM 47-6 )
5 ese e*
e e
o O.
e
,c--,-
Nstco cf Daily Meating Independent Assessment of Underpinning Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Location Midland, Michigan
[. '
Apgust 11, 1983 P[, resent For:
Consumers Power Bechtel MPQAD Stone & Webster G.
Murray E.
Cviki J.
Moran P.
Majeski J.
Gaydos P.
Barry Parsons J.
Ratner Purpose This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant, Units 1 & 2.
Discussion Item 47 Slope Layback.
J.
Ratner asked if slope laybacks will be used in the future.
G.
Murray indicated that no additional laybacks are anticipated.
Existing layback areas, which will be excavated in the future, have been left open. Laybacks which will not be excavated have been grouted.
( CLOSED ITEM )
Item 47 Service Water Pipes.
J.
Ratner inquired about the schedule for completion for the service water pipes.
J.
Gaydos indicated that he did not have that information but would obtain it.
( OPEN ITEM )
Item 47 Carlson Meter Calibrations.
P.
Barry stated that J.
Darby requested a clarification to V.
Vennhs4 statement in Item 2 of the Notes of Daily Meeting from June 16, 1983 It was agreed that the statement should read " V.
Verma stated that the meter tests conducted at WJE on the meters to be used in pier E/W8 will provide data to determine the acceptance criteria for the remaining Carlson meter calibrations." ( CLOSED ITEM )
i m
7
_-,y
______~y,
Not7o of Daily Hesting Independent Assessment of Underpinning
, Mid1And Plant Units 1 & 2 Eonsumers Power Company Held at Midland Site Location Midland, Nichigan Augu:t 12, 1983
[-
3 Present For:
Consumers Power Bechtel MPQAD Stone & Webster G.
Murray E.
Cviki G.
Carpenter W.
Kilker J.
Gaydos P.
Majeski P.
Barry Parsons J.
Ratner F.
Balsamo Purpose This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant, Units 1 & 2.
Discussion Item 47 Status of Piers E/W8 Load Transfer.
J.
Fisher reported that the load transfer has been completed on pier E8 but is still underway at pier W8. ( CLOSED ITEM )
Item 47 SCN on Existing Concrete Mix Design.
E.
Cviki stated the 1973 design date revealed the mix design slump was 5 inches.
P.
Barry replied this resolved the Team concern over the slump inadvertency margin. ( CLOSES OUT ITEM 45-17 )
Item 47 KC3 Drift Concrete.
P.
Barry questioned if a determination had been made of the status of the concrete in the upper portion of the drift cut.
A well defined joint was mrt encountered at the usual elevation and a membrane was located some 3 ft. lower than normal.
E.
Cviki stated Resident Engineering had evaluated the situation and determined structural concrete extended only to Et 610.
( CLOSED ITEM )
Item 47 Inspection of UAT Work Platform Installation.
J.
Gaydos advised that FSO initially inspected the items in the UAT and marked it up for rework.
FSO Civil Engineers reported that work was c6mplete, but the FSO Welding Engineer had not gone back to reinspect the 15 ems. QC was called for the final inspection, resulting in the NCR.
(yCLOSESOUTITEM47-13)
Item 47 Direct-hire Work Training.
-[
~
J.
Fisher reported that FSO is undertaking a program to further the train-ing of all personnel assigned to this work in light of the recent UAT weld-ing inspection problems. Until this action is completed no further direct hire work will be performed. J.
Fisher will update. ( OPEN ITEM )
2 3
Notes of Daily Mesting Independent Assessment of Underpinning
- Mpdihqd Plant Units 1 & 2 Censumers Power Company Held at Midland Site Location Midland, Michigan Angust 12, 1983 item 47 NIR # 14 Issue.
P.
Barry reported that NIR # 14 was issued today'on the type of bolt nuts supplied with the NPS grillage beams and accessories.
W.
Kilker said the last statement on the NIR on " reportability " has been determined by the Assessment Team to be an unnecessary recommendation.
That is, in the Team's opinion, the item.is not reportable.
( CLOSED ITEM ),
Item 47 Service Water Pipe Repair Status.
In response to a previous question by J.
Ratner, J.
Fisher will supply the pipe repair schedule to the Assessment Team.( CLOSES OUT ITEM 47-16 )
O y
5,
.J
Notss of MPQAD Mesting Independent Assessment of Underpinning Miq1and Plant Units 1 & 2 Held at Midland Site Location Midland, Michigan August 9, 1983
~
fresent For:
(stone & Webster MFQAD I
- B.
Holsinger J.
Meisenheimer D.
Forn M.
DeWitt Purpose This meeting is held each week to obtain information from MPQAD regarding the soils underpinning work at the Midland Plant Units 1 & 2.
Discussion Item 47 Status of QA NCR's on QC certification.
J.
Meisenheimer_ stated the NCR's were written as a result of programmatic paper work not being completely filled out. The inspectors had received all required training / examination and were considered certifiable by the QA Level III Engineer. To prevent reoccurrence, a daily certification matrix is available so that all leads can ascertain whether inspectors are certified prior to performing inspectors.
Additionally, an inspector cannot withdraw an open I.R. from the Q.A.
Document Control unless his name appears on the certification list for that inspection report.
( CLOSES ITEM 45 -7Q )
Item 47 Status of Q.C. Welding Inspections.
J.
Meisenheimer responded to a question contained in Stone & Webster's Notes of Daily Meeting dated 8-8-83 ( Item 47 h ).
A welding consultant has been retained by MPQAD to provide an assessment of welding inspections and quality instructions to the code requirements.
The assessment was requested, in part, to address the need for more consistency in the inspections. In the cast, reinspections have revealed occasional deficiencies after initial acceptance.
Meisenheimer maintained, in any case, that the QC/QA personnel will not be restricted from rajecting an item anytime and issuing nonconformances on previously accepted items. ( CLOSES OUT ITEM 47-4 )
Item 47 Information on NCR's.
B.
Holsinger stated that NCR's are quoting sections of the parent document and explained that earlier remarks by Stone & Webster were aimed towards makiry; a clear reference to the section(s) of the parent document that contain the requirement. ( CLOSED ITFM )
er
~. -
d
.