Special Rept:On 940901,determined That Fire Damper Visual Insps Not Performed as Required Due to Fire Protection SRs Being Originally Misinterpreted.Requirements for Visual Insps Incorporated Into Periodic Test Procedures
ML20077S399
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 01/17/1995
From: Ohanlon J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
94-720, NUDOCS 9501240074
Download: ML20077S399 (2)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _____ -

r'.. <

VINGINIA ELECTRIC AND POWEH COMi%NY HIcuxoxn,VIROINIA 20261 January 17, 1995 U. S. Nuclear Regulatory Commission Serial No.94-720 Attention: Document Control Desk NAPS /MPW/GSS R3 Washington, D. C. 20555 Docket Nos. 50-338 50-339 License Nos. NPF-4 NPF-7 Gentleman:

VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS 1 and 2 FIRE DAMPER SPECIAL REPORT A Special Report dated April 6,1994, Letter No.94-176 Fuel Oil Pump House High Pressure Carbon Dioxide System and Control Room Halon System, informed the NRC of our systematic review of the Fire Protection surveillance requirements. This review involved a line-by-line examination, of the station controlled Technical Requirements Manual, to verify surveillance requirements are completely addressed by station procedures. We further informed the NRC that any similar situations identified during the examination would be submitted upon completion of the review in a single report.

The review of the Fire Protection surveillance requirements is now complete.

On Thursday, September 1,1994, Station Deviation Report (DR) N94-1139 dated August 25,1994, was determined to be reportable by the Station Nuclear Safety and Operating Committee. The subject DR documented the missed surveillance for fire damper inspections required to be conducted every 18 months. The cause of the missed surveillance was due to the fire protection surveillance requirements being originally misinterpreted as not to require a visual inspection of the fire dampers. This misinterpretation was carried forward from the Updated Final Safety Analysis Report to the Technical Requirements Manual. This issue was identified in the Notice of Violation in NRC Inspection Report Nos. 50-338/94-21 and 50-339/94-21. Pursuant to North Anna Technical Requirements Manual specification TR 7.2C and GR 1.0.10, a Special Report is hereby submitted because the surveillance requirement for fire damper visual inspections had not been performed as required.

Requirements for visual inspections have been incorporated into periodic test procedures specific to fire dampers. Subsequently, the fire damper surveillance was satisfactorily completed. No other missed surveillance's were identified following completion of the Fire Protection surveillance requirements review.

2f.0054 9501240074 950117 DR ADOCK o500 B l0

i o

^

I 4

l . l 4

4 This Special Report has been reviewed by the Station Nuclear Safety and Operating a

Committee and will be provided to the Management Safety Review Committee.

Should you have any questions regarding this report, please contact us.

1 4

Very truly yours, 4

James P. O'Hanlon <

Senior Vice President - Nuclear l I

cc: U.S. Nuclear Regulatory Commission )

Region 11 101 Marietta Street, N.W.

i Suite 2900 Atlanta, Georgia 30323 i

R. D. McWhorter

, NRC Senior Resident inspector

! North Anna Power Station  ;

1 i