ML20077M187

From kanterella
Jump to navigation Jump to search
Temporary Instruction 2515/194 Report 05000354/2020010
ML20077M187
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 03/20/2020
From: Glenn Dentel
NRC Region 1
To: Carr E
Public Service Enterprise Group
References
IR 2020010
Download: ML20077M187 (10)


See also: IR 05000354/2020010

Text

March 20, 2020

Mr. Eric Carr

President and Chief Nuclear Officer

PSEG Nuclear, LLC

P.O. Box 236

Hancock's Bridge, NJ 08038

SUBJECT: HOPE CREEK GENERATING STATION - TEMPORARY INSTRUCTION

2515/194 REPORT 05000354/2020010

Dear Mr. Carr:

On March 5, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

Hope Creek Generating Station and discussed the results of this inspection with Mr. Steven

Poorman, Plant Manager and other members of your staff. The results of this inspection are

documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

X /RA/

Signed by: Glenn T. Dentel

Glenn T. Dentel, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No. 05000354

License No. NPF-57

Enclosure:

As stated

cc w/ encl: Distribution via LISTSERV

ML20077M187

Non-Sensitive Publicly Available

SUNSI Review

Sensitive Non-Publicly Available

OFFICE RI/DRS RI/DRP RI/DRS

NAME CHobbs per email BBickett GDentel

DATE 3/18/20 3/19/20 3/20/20

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number: 05000354

License Number: NPF-57

Report Number: 05000354/2020010

Enterprise Identifier: I-2020-010-0012

Licensee: PSEG Nuclear, LLC

Facility: Hope Creek Generating Station

Location: Hancock's Bridge, NJ 08038

Inspection Dates: March 2, 2020 to March 5, 2020

Inspectors: C. Hobbs, Reactor Inspector

J. Patel, Senior Resident Inspector

Approved By: Glenn T. Dentel, Chief

Engineering Branch 2

Division of Reactor Safety

Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting a Temporary Instruction 2515/194 at Hope Creek Generating

Station , in accordance with the Reactor Oversight Process. The Reactor Oversight Process is

the NRCs program for overseeing the safe operation of commercial nuclear power reactors.

Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

2

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors reviewed selected procedures and records,

observed activities, and interviewed personnel to assess licensee performance and compliance

with Commission rules and regulations, license conditions, site procedures, and standards.

OTHER ACTIVITIES - TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

2515/194 - Inspection of the Licensees Implementation of Industry Initiative Associated with the

Open Phase Condition Design Vulnerabilities in Electric Power Systems (NRC Bulletin 2012-01)

The inspectors reviewed the licensees implementation of the Nuclear Energy Institute

Voluntary Industry Initiative, (ADAMS Accession No. ML15075A454) dated March 16,

2015. This included reviewing how the licensee updated their licensing basis to reflect the need

to protect against open phase conditions.

Inspection of the Licensees Implementation of Industry Initiative Associated with the Open

Phase Condition Design Vulnerabilities in Electric Power Systems (NRC Bulletin 2012-01)

(1 Sample)

(1) Hope Creek electrical power distribution system is divided into four voltage levels:

500 kV, 13 kV, 7 kV, and 4kV. The offsite electrical power system consists of the

500 kV and 13 kV voltage levels which are contained inside the Hope Creek

switchyard, while the onsite electrical power distribution system consists of the 7 kV

system and the 4 kV system, outside of the Hope Creek switchyard. Electrical power

enters the Hope Creek switchyard at the 500 kV system which consists of a 500 kV

ring bus with two seperate offsite power transmission lines supplying power to

different sections of the 500 kV ring bus. In addition, there is a third connection which

is an inter-tie to the Salem 500 kV switchyard that is normally open. The 500 kV ring

bus supplies power to four Station Power Transformers (SPTs) which step the voltage

down to 13 kV. There are eight Station Service Transformers (SSTs) which then step

down the voltage to either 7 kV or 4 kV. Two SSTs supply two 7.2 kV buses that

supply large auxiliary loads such as motor generator sets for reactor recirculation

pumps and condensate pumps. Two SSTs supply power to four vital 4 kV buses that

supply power to Engineered Safeguard Features (ESF) 480 V loads that are

necessary for safe shutdown of the nuclear unit. The other four SSTs supply power

to various non-vital 4 kV buses. The plant electrical distribution is such that each vital

and non-vital 4 kV bus is supplied from two SSTs, so that there is a redundant power

source to each 4 kV bus in the electrical distribution system. Normal configuration is

for 500 kV SPT T1 to feed 13 kV SST 1BX501 which is the normal source of power

for 4 kV vital buses 10A402 and 10A404, and the alternate source of power for 4 kV

vital buses 10A401 and 10A403. 500 kV SPT T4 normally feeds 13 kV SST 1AX501

which is the normal source of power for 4 kV vital buses 10A401 and 10A403 and the

alternate source of power for 4 kV vital buses 10A402 and 10A404.

3

In the event the normal source of offsite power is lost to the SST supplying any non-

vital 7kV or 4 kV bus, an automatic fast transfer will occur to the alternate SST power

source. In the event the normal source of offsite power is lost to either individual SST

1AX501 or 1BX501 supplying the vital 4 kV buses, an automatic fast transfer will

occur to the alternate 13 kV SST. Each 4 kV vital bus is equipped with a standby

diesel generator that is capable of automatically starting and sequencing onto its

respective 4 kV vital bus within 10 seconds. In the event both sources of offsite

power are lost to a vital 4 kV bus, its respective standby diesel generator will start and

sequence onto its respective 4 kV vital bus. For safe plant shutdown, three out the

four 4 kV vital buses are necessary. The extra fourth 4 kV vital bus is for

redundancy.

The Open Phase Protection (OPP) system utilized at Hope Creek consists of a hybrid

design with protection at both the 500 kV level and protection at the 13 kV level. At

the 500 kV level, the OPP system utilizes the Power Systems Sentinel Technologies,

LLC (PSSTech) design. This design consists of a neutral current injection method, in

which a small neutral current is injected to the primary (high) side neutral bushing.

Changes in the neutral impedance are then monitored to determine if an open phase

condition exists. This method of protection is designed to work in both high and low

transformer loading conditions. At Hope Creek Generating Station, each PSSTech

system control cabinet contains single channel protection, with one Schweitzer

Engineering Laboratories (SEL) protection relay. One PSSTech system control

cabinet is installed at each of the four 500 kV transformers (SPTs T1, T2, T3, and T4)

in the Hope Creek switchyard. The active trip capability on each control cabinet

would open the upstream 500 kV switchyard breaker supplying power to that 500 kV

SPT in the event an Open Phase Condition (OPC) was detected. The PSSTech

system was functioning in alarm only mode at the time of inspection, with the active

trip feature disabled by hand switch on the front of the control cabinet.

At the 13 kV level, OPP is provided by SEL-751 multifunction negative sequence

relays (59Q) that monitor vital 4 kV bus infeed through potential transformers. Eight

relays total, four for SST 1AX501, and four for SST 1BX501. In order to actuate the

lockout relay for one of the two SSTs, each group of four relays must have an active

trip signal on two of the 59Q relays, in a one-out-of-two-taken-twice coincidence logic.

This coincidence relay logic prevents spurious actuations of the active trip portion of

the system. Relay settings have been adjusted to account for normal system grid

imbalance. If the coincidence logic is met, the SST lockout relay will open the

upstream 13 kV breakers feeding either 1AX501 or 1BX501. At the time of the

inspection, the 59Q relays were operating in alarm function only, with the active trip

feature disabled by the opening of knife switches located next to the relays.

INSPECTION RESULTS

Detection, Alarms, General, and Protective Actions Criteria 2515/194

Based on discussion with PSEG staff, review of design and testing documentation, and

walkdowns of installed equipment, the inspectors had reasonable assurance that PSEG is

appropriately implementing, with noted exceptions discussed below, the Voluntary Industry

Initiative at Hope Creek Generating Station. The inspectors determined that:

03.01(a)(1) Open Phase Conditions are detected and alarmed in the main control room at

Hope Creek Generating Station.

4

03.01(a)(2) Open Phase Condition detection circuits are sensitive enough to identify an OPC

for all credited transformer loading conditions (high and low loading). In addition, enhanced

monitoring criteria have been proceduralized for taking an OPP PSST panel out of service,

as well as for non-functional SEL-751 relays.

03.01(a)(3) Open Phase Condition design schemes minimize misoperation and spurious

operation in the range of voltage unbalance normally expected in the transmission system.

Misoperation and spurious operation have been accounted for in calculation, implemented

through protective relay settings and utilization of coincidence logic at the 13 kV level of the

system.

03.01(a)(4) No Class-1E circuits were replaced with non-Class-1E circuits during the

implementation of the OPC modification.

03.01(a)(5) The Hope Creek UFSAR was updated to discuss the design features and

protection schemes for the OPP system under UFSAR change notice 18-003.

03.01(b)(1) Hope Creek Generating Station has determined that an OPC is a credible failure

and has installed an Open Phase Protection system.

03.01(b)(2) With an OPC occurence and no accident condition signal present, an OPC will

not adversely affect the function of important-to-safety SSCs. The OPP system at Hope

Creek is designed to actuate an existing transformer lockout relay at both the 500 kV and

13 kV level if the active trip feature of the system is enabled. The trip function, if enabled,

would provide an additional input to the associated transformer lockout relays, however, the

credited plant response is unaffected and will be the same regardless of the conditions that

generated the lockout of the transformer.

No findings were identified.

Protective Actions Exceptions 2515/194

03.01(b)(3) With an OPC occurrence and an accident condition signal present, the inspectors

could not verify that automatic detection and actuation will transfer loads as required to

mitigate postulated accidents to an alternate source and ensure safety functions are

preserved. At the time of the inspection, the OPP system at Hope Creek was operating in

alarm mode only with the active trip features of the system disabled. Alarm response

procedures are in place to have operators manually separate the station from offsite power if

it is determined that an OPC exists. The OPP system was still in the 24 month monitoring

period described in the Nuclear Energy Institute (NEI) Voluntary Industry Initiative (VII). The

monitoring period is scheduled to end in December 2020, at which time the station will decide

to enable active trip features of the system or adopt the risk informed operator manual action

methodology described in NEI technical report 19-02. This exception was documented in

NOTF 20846124.

03.01(b)(4) Periodic tests, calibrations, and setpoint verifications had not been established for

the OPP system at the time of the inspection. This exception was identified in the station self

assessment conducted prior to the start of the inspection and documented in NOTFs

20845340 and 20846125.

5

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

to Mr. Steven Poorman, Plant Manager and other members of the licensee staff.

6

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

2515/194 Calculations E-15.17 Hope Creek Open Phase Protection Analysis 0

E-15.19(Q) Hope Creek 1E Motor Operability Analysis for Unbalanced 0

Voltage

Corrective Action NOTFs

Documents 20844710,

20840066,

20840428,

20840429,

20844603,

20845002,

20845013,

20845014

Corrective Action NOTFs

Documents 20845340,

Resulting from 20846124,

Inspection 20846125

Drawings E-0001-0 (Q)-25 Hope Creek Generating Station - Single Line Diagram 25

E-0046-1-8 Hope Creek Generating Station - Schematic Meter & Relay 8

Diagram - 4.16 kV Class 1E Station Power System

Switchgears 10A401 & 10A403

E-0047-1-7 Hope Creek Generating Station - Schematic Meter & Relay 7

Diagram - 4.16 kV Class 1E Station Power System

Switchgears 10A402 & 10A404

Engineering HCN 18-003 Hope Creek UFSAR change notice for Open Phase 01/10/18

Changes Condition protection system

Engineering DCP 80119206 50.59 Review Hope Creek Unit 1 Open Phase Protection 0

Evaluations

Procedures HC.OP-AR.ZZ- Window Location E1-C4 - 500 kV System Open Phase 33

0015(Q)

HC.OP-AR.ZZ- Window Location E3-F1 - 4.16 kV System Open Phase Trip 15

0016(Q)

HC.OP-DL.ZZ- Hope Creek Control Console Log 3 - Condition 1, 2, and 3 94

7

Inspection Type Designation Description or Title Revision or

Procedure Date

0003(Q)

HC.OP-DL.ZZ- Hope Creek Auxiliary Building Log 6 30

0006-F1

HC.OP-DL.ZZ- Hope Creek Switchyard Log 7 22

0007-F1

HC.OP-SO.PB- Hope Creek 4.16 kV System Operation 29

0001(Q)

8