Significant Deficiency Rept SD 413-414/82-26 Re Unit 2 Diesel Generator Piston Skirts.Completion Now Scheduled for 831001.Delay Caused by Freight Time Delays & Problems W/Starting Air Compressors
ML20077H652
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 07/29/1983
From: Tucker H
DUKE POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
10CFR-050.55E, 10CFR-50.55E, SD-413-414-82-2, NUDOCS 8308110181
Download: ML20077H652 (1)


Text

,f

@MPAW

'f P.O. box 33189 CHARLOTTE, N.O. 28242 HALH. TUCKER 83 AUG 4 glO +

TELEPitONE

<>o4> oro-4=oi vics nasinen 862y 9, 1983

===.

o-no-Mr. James P. O'Reilly, Regional Administrator U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30303 Re: Catawba Nuclear Station Units 1 and 2 Docket Nos. 50-413 and 50-414

Dear Mr. O'Reilly:

In the supplemental response to Significant Deficiency Report SD 413-414/82-26 dated June 22, 1983, it was stated that the work on the Unit 2 diesel generator piston skirts would be complete by August 1, 1983. However, there have been further delays encountered due to freight time delays, problems with the starting air compressors and priority work on Unit 1.

The completion date for the work on Unit 2 diesels is now October 1, 1983.

Very truly yours, fA B. LA~+p Hal B. Tucker RWO/php cc: Director INPO Records Center Office of Inspection & Enforcement Suite 1500 U. S. Nuclear Regulatory Commission 1100 Circle 75 Parkway Washington, D. C. 20555 Atlanta, Georgia 30339 NRC Resident Inspector Mr. Rotert Guild, Esq.

Catawba Nuclear Station