,0 0
DUKE Powna GoxPm 15.0. nox 33180 CIIARLOTTE. N.C. 28242 IIAL II. TIJCKEI{
TELEPHONE (70-6) 073-4531 viam emenssar=r
.mu..
r."
August 8, 1983 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Attention:
Ms. E. G. Adensam, Chief Licensing Branch No. 4 Re: Catawba Nuclear Station Docket Nos. 50-413 and 50-414
Dear Mr. Denton:
My letter of May 18, 1983 described Duke Power Company's plans for modification of the Catawba Unit 1 steam generators. The purpose of this letter is to update two items discussed in that letter.
At the time of our previous submittal, it was expected that work would begin on the steam generators in September 1983. Because the work has proceeded smoothly on other units with Westinghouse Madel D2/D3 steam generators, we now expect to begin preliminary work on the Catawba Unit 1 steam generators the week of August 8, 1983.
As discussed in section 4.1 of the May 18, 1923 submittal, we had proposed to inspect the first five rows of the preheater after completion of the modification on each steam generator. The purpose of this inspection was to identify any damage to the tubes resulting from the modification. As a result of experience in modifying other Model D2/D3 steam generators, Westinghouse has recommended that we inspect only the first row of tubes in each steam generator for damage.
If any damage is noted, additional rows would be inspected. This more limited inspection is considered adequate since any modification related damage to the tubes would be evident in the first row and a 100% eddy current baseline inspection using multi-frequency techniques was previously performed on these steam generators.
Very truly yours, G
/
?
G a4 /
e kw Hal B. Tucker ROS/php cc:
Mr. James P. O'Reilly, Regional Administrator U. S. Nuclear Regulatory Commission Region 11 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30303 Bool I
8308110067 830808 PDR ADOCK 05000413
)
A A
PDR F
(#
e O
Mr. Harold R. Denton, Director August 8, 1983
.Page 2 cc: NRC Resident Inspector Catawba Nuclear Station Mr. Robert Guild, Esq.
Attorney-at-Law P. O. Box 12097 Charleston,-South Carolina 29412 Palmetto Alliance 2135 Devine Street Columbia, South Carolina 29205 Mr. Jesse L. Riley Carolina Environmental-Study Group 854 Henley Place Charlotte, North Carolina 28207 s
i
,