A' vg Telephone (412) 393-6000 Nuclear Group P,0 Box 4 Shippingport. PA 15077-0004 e
December 7,1994 Beaver Valley Power Station Unit 1 -' Docket No. 50-334, License No. DPR-66 Unit 2 - Docket No. 50-412, License No. NPF-73 Monthly Operating Report U. S. Nuclear Regulatory Commission Document Control Desk -
Washington, D.C. 20555 Gentlemen:
In accordance with Appen' dix A,
Technical Specifications, the Monthly.
Operating - Report is submitted for Unit 1 and Unit 2 for the month of November,1994.
Respectfully, nd
' T. P. Noonan Division Vice President, Nuclear Operations /
Plant Manager DTJ/mmg Enclosures i
cc: NRC Regional Office King of Prussia. PA
)
e3,re,
.t.v G v 0 3 Q
w :
The Nuclear Professionals b
9412120280 94113o DR ADOCK 0500 3 4 i
NARRATIVE
SUMMARY
OF IOtmILY OPERATDG EXPERIDICE UNIT 1 POVD4BER 1994 November 1
'Ihe. Unit operated at a nominal value of 100% output for the through entire report period.
November 30
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
50-334 UNIT BVPS Unit 1 DATE Dec. 1, 1994 COMPLEITD BY Davirl T. Jones TELEPHONE (412) 393-7553 MONIE November 1994 DAY AVERAGE DAILY POWER I1 VEL DAY AVERME DAILY POWER LEVEL (We-Net)
(We-Net) 1 833 17 831 2
838 18 829 3
829 19 821 4
817 20 829 5
808 21 821 6
813 22 833 7
829 23 829 8
825 24 833 9
829 25 825 10 825 26 817 11 825 27 829 12 825 28 833 13 821 29 829 14 821 30 829 15 833 31 16 833 INSTRUCTIONS On this form, list the average daily unit power level We-Net for each day in the reporting month. Compute to the nearest whole megawatt.
OPERATING DATA REPORT DOCKET NO :
50-334 REPORT DATE:
12/02/94.
COMPLETED BY: David T. Jones TELEPHONE:
(412) 393-7553 OPERATING STATUS
- 1. UNIT NAME: BEAVER VALLEY POWER STATION, UNIT 1 Notes
- 2. REPORTING PERIOD: NOVEMBER 1994
- 3. LICENSED THERMAL POWER (MWt):
2652
- 4. NAMEPLATE RATING (Gross MWe):
923
- 5. DESIGN ELECTRICAL RATING (Net MWe):
835
- 6. MAX. DEPENDABLE CAPACITY (Gross MWe):
860
- 7. MAX DEPENDABLE CAPACITY (Net MWe):
810
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS SINCE IAST REPORT, GIVE REASONS:
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (Net MWe):
None
- 10. REASONS FOR RESTRICIIONS, IF ANY:
N/A THIS MONTH YEAR TO DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD:
720.0 8016.0 162912.0
- 12. NO. OF MRS. REACTOR WAS CRITICAL:
720.0 6281.9 105812.8
- 13. REACTOR RESERVE SHUTDOWN HOURS:
0.0 0.0 4482.8
- 14. HOURS GENERATOR WAS ON LINE:
720.0 6250.5 103793.7
- 15. UNIT RESERVE SKUTDOWN HOURS:
0.0 0.0 0.0
- 16. GROSS THERMAL ENERGY GEN. (MWH):
1902781.0 16197103.0 249602579.5
- 17. CROSS ELECT. ENERGY GEN. (MWH):
630040.0 5300234.0 80457757.0
- 18. NET ELECTRICAL ENERGY GEN. (MWH):
595030.0 4969904.0 75189424.0
- 19. UNIT SERVICE FACTOR: (PERCENT) 100.0 78.0 65.6
- 20. UNIT AVAILABILITY FACTOR:(PERCENT) 100.0 78.0 65.6
- 22. UNIT CAPACITY FACTOR (DER): PCT 99.0 74.3 57.7
- 23. UNIT FORCED OUTAGE RATE: (PERCENT) 0.0 22.0 16.2
- 24. SHUTDOWNS SCHEDULED OVER NEXT SIX MONTHS (TYPE,DATE,AND DURATION OF EACH):
The unit is scheduled to shutdown for its tenth refueline outace on January 2.
1995.
The refueline outace is scheduled to last for 60 days.
- 25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):
j FORECAST ACHIEVED j
INITIAL CRITICALITY N/A N/A i
INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A
UNIT SHUTDOWNS AND POWER REDUCTIONS (220%)
Docket No.
50-334 Unit Name SVPS Unit #1 Date December 2.
1994 Completed By David T.
Jones REPORT MONTH November 1994 Telephone (412) 395-7553 Method of Licensee Cause & Corrective Duration Shutting Event System C omponent Action to No.
Date Typel (Hours)
Reason 2 Down Reactor 3 Report #
Code?
Code 5 Prevent Recurrence NONE 1
2 3
4 F-Forced Reason:
Method:
Exhibit F-Instructions for S-Scheduled A-Equipment Fasture (Explain) 1-Manual Preparation of Data Entry Sheets 8-Maintenance or Test 2-Manoat Scram for Licensee Event Report (LER) File C-Refueling 3-Automatic Scram (NUREG0161).
D-Regulatory Restriction 4-Cont'd.'from Previous Month E-Operator Training & License Exam 5-Reduction 5
F-Administrative 9-Other Exhibit H-Same Source.
G-Operational Error (Explain)
H-Other (Explain)
l
?@RRATIVE SUFMARY OF MotfIHLY OPERATDC EXPERIDICE UNIT 2 IKN H4BER 1994 November 1
'Ihe Unit operated at a nantinal value of 100% output for
- through, the entire report period, tiovember 30
1 AVEAGE DAILY UNIT POWER LEVEL 1
DOCKET 10.
50-412 UNIT BVPS Unit 2 DATE Dec. 1. 1994 COMPLETED BY David T. Jones TELEPHONE (412) 393-7553 i
i
!OtTIll November 1994 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY 10WER LEVEL (MWe-Net)
(MWe-Net) 1 831 17 833 2
834 18 830 3
829 19 833 4
824 20 832 5
823 21 826 6
829 22 837 7
836 23 828 8
829 24 825 9
829 25 818 10 837 26 827 11 838 27 824 12 834 28 827 13 828 29 832 14 825 30 834 15 830 31 26 835 INSTRUCTIONS On this form, list the average daily unit power level MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
4 e
OPERATING DATA REPORT DOCKET No.:
50-412 REPORT DATE:
12/02/94 COMPLETED BY: David T. Jones TELEPHONE:
(412) 393-7553 OPERATING STATUS
- 1. UNIT NAME: BEAVER VALLEY POWER STATION, UNIT 2 Notes
- 2. REPORTING PERIOD: NOVEMBER 1994
- 3. LICENSED THERMAL POWER (MWt):
2652
- 4. NAMEPIATE RATING (Gross MWe):
923
- 5. DESIGN ELECTRICAL RATING (Net MWe):
836
- 6. MAX DEPENDABLE CAPACITY (Gross MWe):
870
- 7. MAX. DEPENDABLE CAPACITY (Net MWe):
820
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS SINCE IAST REPORT, GIVE REASONS:
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (Net MWe):
None
- 10. REASONS FOR RESTRICTIONS, IF ANY:
N/A THIS MONTH YEAR TO DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD:
720.0 8016.0 61695.0 12, NO. OF HRS. REACTOR WAS CRITICAL:
720.0 7750.2 53080.5
- 13. REACTOR RESERVE SHUTDOWN HOURS:
0.0 0.0 0.0
- 14. HOURS GENERATOR WAS ON LINE:
720.0 7737.0 52733.6
- 15. UNIT RESERVE SHUTDOWN HOURS:
0.0 0.0 0.0
- 16. GROSS THERMAL ENERGY GEN. (MWH):
1894630.0 20327867.0 130559752.0
- 17. GROSS ELECT, ENERGY GEN. (MWH):
627701.0 6746549.0 42398554.0
- 18. NET ELECTRICAL ENERGY GEN. (MWH):
597408.0 6403533.0 40053812.0
- 19. UNIT SERVICE FACTOR: (PERCENT) 100.0 96.5 85.5
- 20. UNIT AVAILABILITY FACTOR:(PERCENT) 100.0 96.5 85.5
- 22. UNIT CAPACITY FACTOR (DER): PCT 99.3 95.6 77.7
- 23. UNIT FORCED OUTAGE RATE:-(PERCENT) 0.0 3.5 3.1
- 24. SHUTDOWNS SCHEDULED OVER NEXT SIX MONTHS (TYPE,DATE,AND DURATION OF EACH):
The unit is scheduled to shutdown for its fif th refueline outare on March 24. 1995.
The refueline outare is scheduled to last for 60 days.
l
- 25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):
FORECAST ACHIEVED INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A
Uhli SHUIDOW45 AhD POWER REDUCTIONS (120%)
Docket No.
50-412 Unit Name BVPS Unit #2-Date December 2, 1994 Completed By David T.
Jones REPORT MONTH November 1994 Telephone (412) 393-7553
~ ~ ~ - - -
T Duration shutting Event System Component Action to No.
Date Typel (Hours)
Reason 2 Down Reactor 3 Report #
Code 4 Code 5 Prevent Recurrence NONE i
1 2
3 4
F-Forced Reason:
Method:
Exhibit F-Instructions for S-Scheduled A-Equipment Failure (Explain) 1-Manual Preparation of Data Entry Sheets B-Maintenance or Test 2-Manual Scram for Licensee Event Report (LER) File C-Refueling 3-Automatic Scram (NUREG0161).
D-Regulatory Restriction 4-Cont'd. from Previous Month E-Operator Training & License Exam 5-Reduction 5
F-Administrative 9-Other Exhibit H-Same Source.
G-Operational Error (Explain)
H-Other (Explain) s