Informs That Final Response to 830525 Notice of Noncompliance from Insp on 830301-0430 Will Be Delayed Until 830725 Due to Extensive Investigation & Evaluation Required
ML20077C931
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 06/27/1983
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Sternberg D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-24182-BSK, NUDOCS 8307260291
Download: ML20077C931 (1)


Text

,.

iiECEIVED liRC Arizona Public Service Company P.O. box 21666 e PHOENIX. ARIZONA 85036 133 JU:130 Pit 12: 69 June 27, 1983 ANPP-24182-BSK/ JAR EEGIGHVIGE U. S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 Attention:

Mr. D. M. Sternberg, Chief Reactor Projects Branch No. 1

Subject:

NRC Inspection Report of March 1 - April 30, 1983 File: 83-019-026, D.4.33.2

Dear Sir:

This letter refers to the Inspection conducted by Mr. L. E. Vorderbrueggen during March 1 - April 30, 1983, as documented in your letter of May 25, 1983, of activities authorized by the Nuclear Regulatory Commission (NRC)

Construction Permit No. CPPR-141, 142, and 143.

Due to the extensive investigation and evaluation required.for the item of noncompliance, it is now expected that our response will be finalized by.

July 25, 1983, at which time a complete report will be submitted.

The above confirms a telephone conversation between yourself and Bruce Kaplan.

Very truly ours.

(

W l'\\ LLL E. E. Van Brunt, Jr.

APS Vice President Nuclear Projects ANPP Project Director EEVBj r/BSK:ru cc: