ML20076K769

From kanterella
Jump to navigation Jump to search
Part 21 Rept Clarifying Position Re Equipment Failures During C-E Qualification Testing of Target Rock Solenoid Activated Valves Per T Lee 830620 Request.Valve Design Conforms to NUREG-0588.Retrofit Program Supported
ML20076K769
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 07/11/1983
From: Pattarini D
TARGET ROCK CORP.
To: Deyoung R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
References
REF-PT21-83-928-000, RTR-NUREG-0588 E-16673, PT21-83-928-000, NUDOCS 8307180081
Download: ML20076K769 (1)


Text

I.

twx m m sno Target Rock Corporation, P.O. Box V,1966E Broadhollow Rd., East Farmingdale, N.Y.11735 / Phone:(516) 293 3800 SUBSDAffr CURTGS VUMM CORMW DN Refer to: E-16673 July 11, 1983 W5 50- W)

Mr. Richard C. DeYoung, Director C-$ h 0 Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Subject:

10 CFH 21 Report by Combustion Engineering on Target Rock Solenoid Activated Valves Models 77L-001 and 77L-003 dated November 8, 1982, Number LD-82-087

Reference:

a) Telephone Conversation T. Lee /T. Crowley June 20, 1983 b) Target Rock Corporation Letter E-16612 dated June 7, 1983

Dear Mr. DeYoung:

In response to AY. Lee's telephone request, Reference al, we are includ-Ing further clarification of our position regarding reported equipment failures during qualification testing performed by Combustion Engineer-ing.

The testing performed by C. E. was conducted to a C. E. interpretation of the requirements of NUREG 0588 and was designed to be plant specific for the Palo Verde plant. Other utilities using simifar Target Rock de-signs have reviewed their qualification status and determined that there is no conflict with NUREG 0588. Further, Arizona Public Service has determined that the results of the test program are not applicable to the balance of plant valves. However, in conjunction with the valves supplied to Palo Verde through C.E., Target Rock is supporting a retro-fit program incorporating C.E.'s requirements consistent with C.E.'s in-terpretation of the results of the qualification test conducted for use in the NSSS system.

We would be pleased to discuss this further with you at your convenience.

Very truly yours, TARGET ROCK CORPORATION

~

D. M. Pattarini Vice President, Engineering DMP/jm 8307180081 830711 PDR ADOCK 05000528 u PDR

[h~b $ 1 j