Malling Address Alabama Power Company 600 North 18th Street P;st Offica Box 2641 Birmingham, Alabama 35291 Telephone 205 783-6081 F. L Clayton, Jr.
%2's'* 027"'
AlabamaPower d
the Southern dectrC System June 10, 1983 Docket Nos. 50-348 50-364 Director, Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washi ngton, D. C.
20555 Attention: Mr. S. A. Varga Joseph M. Farley Nuclear Plant - Units 1 and 2 Licensing items Requesting NRC Approval Gentlemen:
Attached for your information is a status of all licensing items identified in Alabama Power Company's letter dated January 13, 1983.
This status is provided on a monthly basis and updated to include any additional submittals requesting NRC approval.
If you have any questions, please advise.
Yours very t uly, b
F. L. Clayton, Jr.
FLCJr/GGY:lsh-D39 Attachment cc: Mr. R. A. Thomas Mr. G. F. Trowbridge Mr. J. P. O'Reilly Mr. E. A. Reeves Mr. W. H. Bradford Dr. I. L. Myers 8306160278 830610 FDR ADOCK 05000348 P
PDR I
(
ATTAOSIENT Page 1 STATUS OF LIE NSING ITEMS REQUIRING Inc APPROVAL Ji3IE 10, 1983 PROPOSED ACTUAL REQESTED APCo AR:o 16tC SIAINITTAL SWINITTAL APPROVAL ACTUAL 16tC TAC ITEM DATE DATE DATE APPROVAL DATE ND.
1 Movable Control Rod Assemblies for 02-22-83 03-04-83 07-15-83 3 49951 FNP 1 and 2 (T.S. 3/4.1.3) 49952 2
Charcoal Filters for FNP 1 and 2 03-01-83 03-04-83 09-01-83 49953 (T.S. 4.7.7, 4.7.8 and 4.9.14) 49954 2
3 River Water System for FNP 1 and 2 N/A 12-30-82 07-01-83 49374 (T.S. 3/4.7.5) 49375 4
Diesel Generator Overload Test for N/A 08-03-82 10-01-83 I 49374 FNP 1 and 2 (T.S. 4.8.1.1.2.c.5) 12-30-82 49375 5 BIT Reduction for FNP 1 and 2 N/A 12-30-82 03-31-83 03-15-83 N/A (T.S. 3/4.5.4) 03-04-83 03-18-83 6
Turbine Valve Surveillance for FNP 2 N/A 10-08-82 12-01-82 NRC letter 49973 (T.S. 3/4.3.4) 12-10-82 of 04-29-83 01-18-83 stated NRC pos it lon.
APCo submltied appeal on 05-31-83 2
7 RCS Pressure Isolation Valves N/A 08-10-82 07-01-83 48714 for FNP 1 and 2 (T.S. 3/4.4.7.2 12-23-82 48715 and 3/4.4.7.3) 8 Mechanical Snubber Functional Test N/A 11-05-82 12-01-82 01-31-83 N/A Exemption for FNP 1 (T.S.4.7.9.e) 9 Waste Gas Hydrogen /0xygen Analyzer 12-01-83 3 06-01-84 3 for FNP 1 and 2 (T.S. Table 4.5-9) 1 Revised by APCo letter dated 06-03-83 2 Delay of approval will adversely af fect the FNP 2 Ref ueling Outage in September 1983 or precipitate a special outage.
3, Revised due to reevaluation.
4 APCo currently evaluating NRC SER.
5 FNP 2 Hydraulic Snubber List will be submitted 60 days af ter startup following the Unit 2, 2nd Ref ueling Outage scheduled to commence September,1983 O.
New request per this status which, if not approved, would precipitate a special outage.
ATTACHIENT Page 2 STATUS OF LICENSIps ITEMS REQUIRING 154C APPROVAL Jt2E 10,1983 PROPOSED ACTUAL REQUESTED APCo APCo MC SusselTTAL SLEINITTAL APPROVAL ACTUAL petC TAC ITEM DATE DATE DATE APPROVAL DATE 10 10 ISl/IST Licensing Program a.
Unit 1 Inservice Inspection (ISI)
Program for ASME Code Class 1, 2 and 3 Components
- 1) Rollef Requests on vessel N/A 04-17-81 09-01-83 48559 cladding examinations 01-10-83
- 2) Rollef Requests on hydro-01-18-83 01-28-83 09-01-83 49547 static test requirements b.
Unit 2 Inservice inspection (ISI) Program for ASME Code Class 1, 2 and 3 Components 2
- 1) Revision 0 Rollef Requests N/A 07-25-80 09-01-83 2
- 2) Rollef Requests on vessel N/A 01-10-83 09-01-83 49373 cladding examinations 2
- 3) Rollef Request on hydrostatic 01-18-83 01-28-83 09-01-83 test requirements c.
Unit 1 Inservice Testing (IST)
Program for AMSE Code Class 1, 2 and 3 Components 4
- 1) Revision 2 Relief Requests N/A 04-21-80 03-15-83 05-02-83 N/A 4
- 2) Revision 3 Rollef Requests N/A 07-16-81 03-15-83 05-02-83 N/A 4
- 3) Revision 4 Rollef Requests N/A 10-25-82 03-15-83 05-02-83 N/A 1
Revised by APCo letter dated 06-03-83 2 Delay of approval will adversely af fect the FNP 2 Refueling Outage In September 1983 or precipitate a special outage.
3 Revised due to reevaluation.
4 APCo currently evaluating P51C SER.
5, FNP 2 Hydraulle Snubber List will be submitted 60 days af ter startup following the Unit 2, 2nd Ref ueling Outage scheduled to commence September,1983 O.
New request per this status which, if not approved, would precipitate a special outage.
r w
w
ATTACHENT Page 3 STATUS OF LICENSIIS ITEMS REQUIRiis IRC APPRDVAL JimE 10, 1983 PROPOSED ACTUAL REQUESTED APCo AR:o mc SUBMITTAL SUBMITTAL APPROVAL ACTUAL MtC TAC ITEM DATE DATE DATE _
APPROVAL DATE 80 d.
Unit 2 Inservice Testing (IST)
Program for ASME Code Class 1, 2 and 3 Components 4
- 1) Revision 0 Relief Requests N/A 03-12-80 02-15-83 04-08-83 N/A 4
- 2) Revision 1 Relief Requests N/A 03-17-82 02-15-83 04-08-83 N/A 4
- 3) Revision 2 Relief Requests N/A 08-06-82 02-15-83 04-08-83 N/A 11 Spent Fuel Pool Storage Additions N/A 03-19-82 11-01-82 04-15-03 N/A for FNP 1 05-01-83 (revised need date) 12 Change 18 Month Interval to RefueIIng 04-01-83 04-05-83 10-01-83 13 Meteorological Tower Surveillance for 02-01-83 01-24-83 08-01-83 FNP 1 and 2 (T.S. 3/4.3.3.4) 14 in-Core Thimbles for FNP 1 and 2 N/A N/A N/A N/A N/A (T.S. 3.3.3.2) 15 Safety Evaluations for Next Fuel Reloads:
a.
Unit 1 Upflow Modification N/A 08-16-82 N/A N/A N/A b.
Unit 1 Cycle 5 03-14-83 03-17-83 N/A N/A N/A c.
Unit 2 Cycle 318 Month Fuel 09-01-83 N/A N/A N/A Cycle 16 FAH and Positive Moderator Temper-09-15-83 3 02-01-84 ature Coef fIciont 17 Containment Spray N/A N/A N/A N/A N/A l
1 Revised by APCo letter dated 06-03-83 2 Delay of approval will adversely af fect the FNP 2 Ref ueling Outage in September 1983 or precipitate a speclei outage.
3 Revised due to reevaluation.
4 APCo currently evaluating EC SER.
5 FNP 2 Hydraulle Snubber List will be submitted 60 days af ter startup following the Unit 2, 2nd Ref ueling Outage scheduled to commence September,1983 O.
New request per this status which, if not approved, would precipitate a special outage.
ATTA00ENT Page 4 STATUS OF LICENSilS ITEMS REQUIRilS NRC APPROVAL JtME 10,1983 190 POSED ACTUAL REQtESTED APCo APCo MtC SUBIITTAL SIENITTAL APPROVAL ACTUAL IGtC TAC ITEM DATE DATE DATE APPROVAL DATE 80 18 Technical Specification Optimization N/A N/A N/A N/A N/A Westinghouse Owners Group 19 Safety Related Battery Changes 04-15-83 05-03-83 11-03-83 20 Rod Swap Test During Low Power 03-01-83 03-01-83 N/A N/A N/A Physics Testing 21 Rod Drop Timing During Low Power N/A N/A N/A N/A N/A Physics Testing 22 Auto Rod Control Above 90% Power N/A 01-11-83 04-01-83 03-24-83 N/A for Unit 2, Cycle 2 and Unit 1, 09-14-82 12-01-82 Cycle 5 23 Unit 2 Licensing Deletion Amendment 01-12-83 01-07-83 N/A N/A N/A Clarification Letter 24 FSAR Update 07-01-83 N/A N/A N/A 25 Administrative Changes a.
Accumulator and ECCS Subsystem 02-01-83 02-01-83 09-01-83 49184 for FNP 1 and 2 (T.S. 4.5.1.1 49185 (c) and 4.5.2.(a))
b.
Generic Letter 82-17 on Audit of N/A 10-25-82 09-01-83 49068 Emergency Plan for FNP 1 and 2 49069 (T.S. 6.5.2.8.e) c.
Machanical and Hydraulle Snubber 06-01-83 05-27-83 09-01-83 Lists for FNP 1 (T.S. Table 5
3.7-4A and 3.7-4b) e 1
Revised by APCo letter dated 06-03-83, 2 Delay of approval will adversely af fect the FNP 2 Ref ueling Outage in September 1983 or precipitate a special outage.
3 Revised due to reevaluation.
4 APCo currently evaluating MIC SER.
5 FNP 2 Hydraulic Snubber List will be submitted 60 days af ter startup following the Unit 2, 2nd Refueling Outage scheduled to commence September,1983.
C.
New request per this status which, if not approved, would precipitate a special outage.
ATTACMENT Page 5 STATUS OF LICENS10E ITEMS REQU".ING J
ISIC APPROVAL JtBE 10,1983 PROR)$ED ACTUAL REQLESTED APCo AFCo IGtC SLEBelTTAL SWIMITTAL APPROVAL ACTUAL IGtC TAC ITEM DATE Dn?I DATE APPROVAL DATE BE).
d.
Administrative Changes for FNP 03-01-83 02-01-83 09-01-83 49184 1 and 2:
49185
- 1) Fire Detectors Table 3.5-12
- 2) RHR isolation 4.5.2.d.1
- 3) River Water Sury 3/4.7.5
- 4) Yard Fire Hydrant Table 3.7-7
- 5) Service Water Battery 4.8.2.5.2(d) 2
- 6) Organization Chart Figure 6.2-2 e.
Unit 2 Pressurizer Sensor Table 03-01-83 02-01-83 09-01-83 49185 (T.S. 3.3.3.7) f.
Unit 1 Refueling Outage Change:
03-01-83 02-01-83 09-01-83 49184 Containment Vent g.
Turbine Building Hydraulic N/A 12-10-82 09-01-83 49287 Snubbers for FNP 2 h.
Incorporation of Licensing N/A 11-24-82 09-01-83 Requirements for FNP 2
- 1) FNP 2 License Condition 49479 2.C.(17) - Containment Vent Line
- 3) FNP 2 License Condition 48687 2.C.(19)(b) - Containment Overcurrent Protection I.
Organization Change to Of fsite N/A 11-16-82 09-01-83 49184 Management for FNP 1 and 2 49185 1
Revised by APCo letter dated 06-03-83 2 Delay of approval will adversely af fect the FNP 2 Ref ueling Outage in September 1983 or precipitate a special outage.
3, Revised due to reevaluation.
4 APCo currently evaluating E C SER.
5, FNP 2 Hydraulic Snubber List will be submitted 60 days af ter startup following the Unit 2, 2nd Ref ueling Outage scheduled to commence September,1983 6,
New request per this status which, If not approved, would precipitate a special outage.
(
ATTACHIENT Page 6 LICDISIIS ITEFS REQUESTED SIBSEQUENT TO APCo's JANUARY 13, 1983 LETTER JIME 10,1985 PROPOSED ACTUAL REQUESTED APCo APCo istC SUBMITTAL SIEMITTAL APPROVAL ACTUAL lstC TAC ITEM DATE DATE DATE APPROVAL DATE NO.
1 Administrative Changes N/A 02-01-83 09-01-83 49184 a.
Engineered Safety Actuation System Instrumentation ACTION Statement 20 Error b.
Security Plan Audit Frequency c.
Environmental Qualification (FNP 1) d.
Augmented Low Power Test Program (FNP 2) 2 Turbine Valve Surveillance N/A 05-27-83 07-29-83 One-Time Change (T.S. 3/4.3.4) 3.
Snubber Visual Inspection 06-17-83 10-01-83 0 One-Time Change (T.S. 3/4.7.9) 1 Revised by APCo letter dated 06-03-83.
2 Delay of approval will adversely af fect the FNP 2 Ref ueling Outage in September 1983 or precipitate a special outage.
3, Revised due to reevaluation.
4 APCo currently evaluating NRC SER.
5, FNP 2 Hydraulic Snubber List will be submitted 60 days af ter startup following the Unit 2, 2nd Ref ueling Outage scheduled to commence September,1983 6,
New request per this status which, if not approved, would precipitate a special outage.