s Arizona Public Service Company P.O Box 21666
- PHOENIX, ARIZONA 85036
~..
April 21, 1983
~
/;
~
~
ANPP-23560-RQT/BSK CORRECTED COPY
- U. S. Nuclear Regulatory Commission 9
7 Region V 3
Creekside Oaks Office Park l
1450 Maria Lane - Suite 210 J
/
@ -)\\
\\
Walnut Creek, California 94596-5368 Attention: Mr. D. M. Sternberg, Chief Reactor Projects Branch 1
Subject:
Interim Report - DER 83-17 A 50.55(e) Fotentially Reportable Deficiency Relating to Fire Protection Switches By ITE Gould Failed To Meet The Requirements Of TMI Task 18A File: 83-019-026; D.4.33.2
Reference:
Telephone Conversation between P. Narbut and R. Tucker on March 4, 1983
Dear Sir:
The NRC was notified of a potentially reportable deficiency in the referenced telephone conversation. At that time, it was estimated that a determination of reportability would be made within thirty (30) days.
Due to the extensive investigation and evaluation required, an Interim Report is attached. It is now expected that this information will be finalized by May 19, 1983, at which time a complete report will be submitted.
Very truly ours
{
q.
L CLUL_
%L E. E. Van Brunt, Jr.
APS Vice President Nuclear Projects Management I
ANPP Project Director l
l EEVB/RQT:db Attachment cc: See Attached Page 2
- Paragraph 2, finalized date should read July 19, 1983.