Forwards Rev to Tech Spec Change Request 84,in Response to Generic Ltr 82-16.Rev Required to Reassign Section Numbers to Conform W/Format Changes Incorporated in Tech Spec Amend 66
ML20073S400
Person / Time
Site: Beaver Valley
Issue date: 04/28/1983
From: Carey J
DUQUESNE LIGHT CO.
To: Varga S
Office of Nuclear Reactor Regulation
Shared Package
ML20073S402 List:
References
GL-82-16, TAC-49724, TAC-51512, NUDOCS 8305060604
Download: ML20073S400 (2)


Text

e e

'Af Telephone (412) 393-6000 Nuclear Division P.O. Box 4 Shippingport, PA 15077-0004 April 28, 1983 Director of Nuclear Reactor Regulation United States Nuclear Regulatory Commission A t tn:

Mr. Steven A. Varga, Chief Operating Reactors Branch No.1 Division of Licensing Washington, DC 20555

Reference:

Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 Revise Proposed Change Request No. 84 to Operating License Centlemen:

Enclosed are:

1.

Three (3) originals and thirty-seven (37) copies of a rev-ision to Technical Specification Change Request No. 84, dated February 7,1983, concerning Technical Specification change in response to Generic Letter 82-16.

2.

Forty (40) copies of the revised Technical Specification change pages.

This revision is required to re-assign section numbers to conform with the change in format incorporated into the Technical Specifications by Amendment No. 66.

The following changes are addressed:

Page Change 6-14, 6-16 revise the format 6-22 incorporate Section 6.9.1.14, this was previously Section 6.9.1.10 that was omitted by Amendment No. 66 3/4 2-6a, B3/4 2-5 re-number the reference to specification 6.9.1.10 to 6.9.1.14 ho l

o 8305060604 830428 PDR ADOCK 05000334 P

pop

- Braver Valley Powar Station, Unit No.1 Docket.No. 50-334, License No. DPR-66 Revise Proposed Change _ Request No. 84 to Operating License Page 2 Therefore, please delete pages 6-14 and 6-16 from our original sub-mittal and include the above revised pages..

Since this is an administrative change to section numbers, we have determined that no safety evaluation is required.

Very r y yours, d

J.

Carey Vice President, Nuclear cc:

Mr. Pete Tam, Project Manager United States Nuclear Regulatory Commission Phillips Building Washington, DC 20555

- Mail Stop 438 -

Mr. W. M. Troskoski, Resident Inspector U. S. Nuclear Regulatory Commission Beaver Valley Power Station Shippingport, PA 15077 U. S. Nuclear Regulatory Commission c/o Document Managment Branch Washington, DC 20555