Interim Deficiency Rept DER 82-53 Re Failure of Joy Fan Blade Causing 2-inch Penetration of Containment Liner Plate. Initially Reported on 820924.Final Rept Will Be Submitted by 830422
ML20073F803
Person / Time
Site: Palo Verde  
Issue date: 03/22/1983
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Sternberg D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
10CFR-050.55E, 10CFR-50.55E, 83-019-026, 83-19-26, ANPP-23329-RQT, DER-82-53, NUDOCS 8304150543
Download: ML20073F803 (2)


Text

.

  • o-o Docket Nos. 50-528/529/530

~

"q gyED

. g 50.55(e) Report i

g @ -6 g p" 3

  • Arizona Public Service Company PHOENIX, ARI2oNA 85036 re oox 21666.

March 22, 1983 ANPP-23329-RQT/BSK gGS '

U. S. Nuclear Regulatory Commission

~

Region V Creekside Oaks Office Park l

1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 i

Attention:

Mr. D. M. Sternberg, Chief i

j Reactor Projects Branch 1

)

Subject:

Time Extension For Report - DER 82-53 A 50.55(e) Potentially Reportable Deficiency Relating to 1

Failure Of Joy Fan Blade Caused 2-Inch Penetration Of Unit 1 Containment Liner Plate File: 83-019-026 D.4.33.2 I

i

Reference:

(A) Telephone Conversation between J. Eckhardt and I

G. Duckworth on September 24, 1982 (B) ANPP-22092, dated October 25, 1982 (Interim Report)

(C) ANPP-22585, dated December 22, 1982 (Time Extension)

(D) Letter to APS From G. W. Knighton, USNRC-Washington, D.C.

dated February 4, 1983.

..(E)

ANPP-23069, dated February 23, 1983 (Interim Report -

Revision 1) i

Dear Sir:

J 4

The NRC was notified of a potentially reportable deficiency in Reference (A), an Interim Report was transmitted by Reference (B), a Time J

Extension was requested by Reference (C) and an Interim Report was i

transmitted by Reference (E) in response to the NRC's request in i

Reference (D) for additional information. At that time, it was estimated l

that a Final Report would be available by March 31, 1983.

i Due to the extensive investigation and evaluation required, it is now expected that this information will be finalize'd by April 22, 1983, at j

which time a complete report will be submitted.

I i

Very truly yours,

(

i CU4_

nLR I

E. E. Van Brunt, Jr.

APS Vice President Nuclear Projects Management ANPP Project Director EEVRJr/RQT:db

, " _ ]

cc: See Attached Page 2 i

8304150543 830322 PDR ADOCK 05000528 S

PDR

eo-e U. S. Nuclear Regulatory Commission March 22, 1983 Attention:

Mr. D. M. Sternberg, Chief ANPP-23329-RQT/BSK Page 2 cc: Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 George W. Knighton, Chief Licensing Branch No. 3 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Emanuel Licitra, Manager Licensing Project U. S. Nuclear Regulatory Commission Washington, D. C. 20535 T. G. Woods, Jr.

J. A. Roedel D. B. Fasnacht G. C. Andognini i

J. R. Bynum A. C. Rogers B. S. Kaplan W. E. Ide J. Vorces P. P. Klute/D. D. Green A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher R. M. Grant D. R. llawkinson L. E. Vorderbrueggen G. A. Fiorelli