Clarifies Status of TMI Items II.K.3.27, Common Ref Level, II.D.1.2, Relief Valve & Safety Valve Test Program & III.D.3.4, Control Room Habitability. Only Mod for Control Room Scheduled for Completion During Cycle 11 Refueling
ML20073B418
Person / Time
Site: Oyster Creek
Issue date: 04/08/1983
From: Fiedler P
GENERAL PUBLIC UTILITIES CORP.
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.D.1, TASK-2.K.3.27, TASK-3.D.3.4, TASK-TM GL-82-05, GL-82-10, GL-82-5, NUDOCS 8304120410
Download: ML20073B418 (2)


Text

50->!1 j

l 4

GPU Nuclear Q

g7 P.O. Box 388 Forked River, New Jersey 08731 609-693-6000 Writer's Direct Dial Number April 8, 1983 Mr. Dennis M. Crutchfield Ope: rating Reactors Branch #5 U.S. Nuclear Regulatory Commission Wa shing ton, D.C.

20555

Dear Mr. Crutchfield:

Subject:

Order Confirming Licensee Commitments on Post TMI Related Issues (Generic Letters 82-05 and 82-10)

The purpose of this correspondence is to clarf fy the status of three NUREG 0737 items included in your Order Confirming Licensee Commitments on Post-TMI t

l Related Issues dated March 14,1983. Our status on these three items is as I

follows:

II.K.3.27 Common Reference Level As stated in our correspondence of May 7,1982, our final phase of implementation for this modification will involve the deletion of all references to old scales, procedure revisions and conducting the necessary training. This will be completed during our current refueling outage.

II.D.l.2 Relief Valve and Safety Valve Test Programs.

Submittal of our plant specific report will be forwarded to you by April 29,1983.

III.D.34 Control Room Habitability As stated in our correspondence of October 8,1982, only our interim modifications for Control Room Habitability are scheduled for completion during our cycle 11 refueling outage. As discussed in a conference call with Mr. J. Lombardo and J. Feed of your staff on March 22, 1983, the final modifications are scheduled for a later date.

Should you bave any questions concerning these items please contact Mr. James Knubel, Manager BWR Licensing at (201) 299-2264.

Very truly yours, O

8304120410 830408 Vice President and Director h

Peter B. Fiedler PDR ADDCK 05000219 P

PDR Oyster Creek l

PBF:jal Enclosure GPU Nuclear is a part of the General Public Utilities System j