Application to Amend License DPR-35 Changing Tech Specs Re Core & Containment Cooling Sys & Fire Protection.Submittal Is Initial Segment of Total of Seven Submittals Re Fire Protection
ML20072M698
Person / Time
Site: Pilgrim
Issue date: 07/11/1983
From: Harrington W
BOSTON EDISON CO.
To: Vassallo D
Office of Nuclear Reactor Regulation
Shared Package
ML20072M702 List:
References
83-180, NUDOCS 8307150068
Download: ML20072M698 (5)


Text

. . _

  • e '

BOSTON EntBON COMPANY 800 BovLsTON STRetr 80sTON, MAssACHustTTs 02199 WILLIAM D. HARRIN GTON sinies vies passiosur StWeLEAe July 11, 1983 BECo Letter No.83-180 Proposed Change No. 83-7 Mr. Domenic B. Vassallo, Chief Operating Reactors Branch #2 Division of Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 License No. DPR-35 Docket No. 50-293 Proposed Change to Technical Specifications

Reference:

(A) Boston Edison Company Letter (W.D. Harrington) to NRC (D.B.

Vassallo), dated May 13,1983(2.83.122)

Dear Sir:

Pursuant to 10CFR part 50.90, Boston Edison Company hereby proposes the following modification to Facility Operating License No. OPR-35, Appendix A. The proposed modification is described in the Attachment to this letter.

This proposed modification should be treated as the initial segment of a total of seven submittals addressing the fire protection issue. In accordance with our request in Reference A, we are requesting that a single amendment be issued upon satisfactory review of all our submittals. To facilitate your review, our final submittal will include all of the previous submittals on this issue, in effect, submitting completely revised Technical Specification Section 3/4.12 LC0's and Surveillances.

\

8307150068 830711 DRADOCK05000g

l f ,

[O DTON EDGON COMPANY Mr. Domenic B. Vassallo, Chief Page 2 Should you have any questions concerning this submittal, please do not hesitate to contact us.

Very truly yours, TFF/ mat Attachment 3 signed originals and 37 copies Commonwealth of Massachusetts)

County of Suffolk )

Then personally appeared before me W.D. Harrington, who, being duly sworn, did state that he is Senior Vice President - Nuclear of Boston Edison Company, the applicant herein, and that he is duly authorized to execute and file the submittal contained herein in the name and on behalf of Boston Edison Company and that the statements in said submittal are true to the best of his knowle ge and belief.

My Commission expires: 04a4 pyg ) -/h, Notary {ublic L l

Attachment Proposed Technical Specification Change Proposed Change Reference is made to Pilgrim Nuclear Power Station, Unit #1 Technical Specifica-tions, Appendix A, Section 3.5, " Core and Containment Cooling Systems," Section 3.9, " Auxiliary Electrical Systems," and Section 3.12, " Fire Protection."

1. Item 4.5.A.1.c Change "Once/ month and Once/ cycle from to "Once/ month" the Alternate Shutdown Panel"
2. Item 4.5.A.3.c Change "Once/ month and Once/ cycle from to "Once/ month" the Alternate Shutdown Panel"
3. Item 4.5.B.1.a Change "Once/3 months and Once/ cycle to "Once/3 months" from the Alternate Shutdown Station"
4. Item 4.5.C.1.b Change "Once/ month and to "Once/ month" Once/ cycle from the Alternate Shutdown Station"
5. Item 4.5.C.1.c Change "Once/ month and to "Once/ month" Once/ cycle from the Alternate Shutdown Station" l

1 l

L- .

6. Item 4.5.0.1.b Change "Once/ month and Once/ cycle from to "Once/ month" the Alternate Shutdown Station"
7. Item 4.5.D.1.c Change "Once/ month and Once/ cycle from to "Once/ month" the Alternate Shutdown Station"
8. Item 4.5.E.1.c Delete Item 4.5.E.1.c entirely.
9. Item 4.9.A.1.a Delete "Once per operating ... started and loaded."
10. The changes shown in Numbers 1-9 above are addressed in new Section 3.12.G,

" Alternate Shutdown Panels", which is part of this Attachment. Refer to new Section 3.12.G for specific additions to the Technical Specifications. Please note that Section 3.12, " Fire Protection," will be entirely rewritten. The attached Section 3.12.G is submitted as the initial segment of seven segments scheduled for review.

11. The new bases for proposed Section 3.12.G, " Alternate Shutdown Panels" are enclosed as part of this Attachment. The BASES for Section 3.12, " Fire Protection", will be completely rewritten. The attached BASES are submitted as the initial segment of seven segments scheduled for review.

Reason for Change These changes are proposed to incorporate the requirements for the Alternate Shutdown Panels into a separate section of the Technical Specifications. Con-solidation of these requirements will clarify the Limiting Conditions for Opera-tion and the Surveillance Requirements.

Safety Considerations These changes do not present an unreviewed safety question as defined in 10CFR 50.59. It has been reviewed and approved by the Operations Review Committee and reviewed by the Nuclear Safety Review and Audit Conmittee.

Significant Hazards Considerations These changes do not present a significant hazard as defined in 10CFR50.92(c), in that these changes do not involve a significant increase in the probability or I

i

consequence of an accident previously evaluated, do not create the possibility of an accident different from those previously evaluated, nor do these changes involve a significant reduction in a safety margin.

Schedule of Change As stated in our letter of May 13, 1983, we expect the NRC to issue the seven submittals as a single amendment. This amendment will be effective upon our receipt of its approval by NRC.

Fee Determination Pursuant to 10CFR170.12, Boston Edison Company proposes this as one segment of the Fire Protection submittal, which, when taken as a whole will be classified as a Class III amendment. Accordingly, a check for $4000 will be transmitted with the final segment of this amendment request.