Washington Public Power Supply System Box 1223 Elma, Washington 98541 (206)482-4428
(
Docket No. 50-508 February 11, 1983 G03-83-128 U. S. Nuclear Regulatory Commission, Region V Office of Inspection and Enforcement 1450 Maria Lane, Suite 260 Walnut Creek, California 94596-5368 Attention:
Mr. D. M. Sternberg, Chief Reactor Projects Branch No. 1
Subject:
ITEM 0F NONCOMPLIANCE (50-508/80-09/05)
FAILURE TO FABRICATE WASTE GAS DECAY TANKS IN ACCORDANCE WITH DRAWING REQUIREMENTS
Reference:
Letter, D. M. Sternberg to R. S. Leddick, dated January 17, 1983.
This letter is intended to supplement the information given to D. P.
Haist, Reactor Inspector, during the inspection performed December 13-17, 1982 regarding the subject matter (see Reference).
Discussions between the Supply System, Ebasco, Combusticn Engineering (C-E), Richmond Engineering Company (RECO) and the Supply System'e Authorized Nuclear Inspector (ANI) have been in progress since March, 1982 to establish an acceptable means for correcting the nonconforming condition.
As a result of a meeting held January 11, 1983, the following was decided:
- 1) CE will provide an ASME Section XI repair plan identifying the grinding and welding performed by RECO.
- 2) Documentation of the grinding work will be provided with the Section XI repair plan.
- 3) The Supply System will verify acceptability of the grinding work.
- 4) Rapair welding performed by REC 0 will be removed and rewelded in accordance with the requirements of the approved Section XI repair plan.
This work is expected to be completed by July, 1983.
r303110379 83o307 PDR ADOCK 03000508 C
. P.D R.
9
Mr. D. M. Sternberg February 11, 1983 Page 2 G03-83-128 Should you have any questions or desire further information, please feel free to contact me directly.
?
^
R. S. Leddick (760)
Program Director, WNP-3 JAV:nj cc:
J. Adams - NESCO D. Smithpeter - BPA A. Tuzes - CE, Windsor Ebasco - New York WNP-3 Files - Richland
-