Submits Clarification of IPEEE & USI A-46 Completion Schedule.Util Expects to Have IPEEE Evaluation Completed & Forwarded to NRC No Later than Dec 1995 & USI A-46 Evaluation No Later than Sept 1995
ML20070Q852
Person / Time
Site: Cooper Entergy icon.png
Issue date: 05/13/1994
From: Horn G
NEBRASKA PUBLIC POWER DISTRICT
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
REF-GTECI-A-46, REF-GTECI-SC, TASK-A-46, TASK-OR GL-88-20, NSD940487, NUDOCS 9405190172
Download: ML20070Q852 (2)


Text

C et o

a d

COOPER NUCLE AR ST ATION

-G - Y f"' Ny P 0. 00X 98. BROWNVILLE, NEBRASKA Ga321 F W. y Nebraska Public Power District "P2% =3?"

w.a m

mmmmm=

mmmmm m====m

== ===m NSD940487 May 13,1994 U.S. Nuclear Regulatory Conunission Attention: Document Control Desk Washington, DC 20555

Subject:

Clarification of the IPEEE and USl A-46 Completion Schedule Cooper Nuclear Station Docket No. 50-298, DPR-46

Reference:

1) IPEEE for Severe Accident Vulnerabilities - 10CFR50.54(f), Generic Letter 88-20, Supplement No. 4, dated June 28,1991, " Individual Plant Examination of External Events -10CFR50.54(f)"
2) Letter from G. R. llorn (NPPD) to U.S. NRC Document Control Desk dated December 19,1991, " Response to Generic Letter 88-20, Supplement No. 4
3) Letter from G. R. Ilorn (NPPD) to U.S. NRC Document Control Desk dated September 21,1992. " Response to Supplement I to Generic Letter 87-02"
4) Letter from Roby B. Bevan (USNRC) to G. R. Ilorn (NPPD) dated July 1,1992,

" Review of Response to Generic Letter 88-20, Supplement No. 4"

5) Letter from G. R. llorn (NPPD) to U.S. NRC Document Control Desk dated February 24,1993, " Clarification of the Generic Letter 87-02, Supplement 1"
6) Letter from Kevin A. Connaughton (USNRC) to G. R. Horn (NPPD) dated July 26,1993, " Evaluation of Licensee's Supplemental Response to Supplement No.

I to Generic Letter 87-02 for Cooper Nuclear Station" Gentlemen:

The Nuclear Regulatory Commission (NRC) ret uested in Reference 1, pursuant to 10 CFR 50.54(f), that each licensee perform an Indivicual Plant Examination of External Events (IPEEE). In this reference, the NRC recommended that the examination of other external event programs be coordinated with the IPEEE to minimize duplication of examination and review efforts. In response to Reference 1, the Nebraska Public Power District (District) informed the NRC, per Reference 2, that it intends to integrate and coordinate the resolution of Unresolved Safety Issue (USI) A-46 and the seismic portion of the IPEEE, for Cooper Nuclear Station (CNS) to the maximum extent possible. In this reference, the District committed to an IPEEE completion date of June 28, 1994. This completion date was based on an NRC request for licensees to submit the IPEEE results within three years from the issuance of Generic Letter (GL) 88-20, Supplement 4. This completion date was also contingent on the issuance of the final NRC Supplemental Safety Evaluation Report (SSER) on the Seismic Qualification Utility Group (SQUG) Generic Implementation Procedure (GIP) and the completion of the joint A-46/IPEEE walkdown to be accomplished during the first refueling outage following, by at least 6 months, the resolution of all GIP issues. In order for the joint A-46 and IPEEE walkdowns to have been accomplished during the 1993 refueling outage, resolution of all GIP issues would had to occur by August 1992. The NRC accepted this position in Reference 4.

9405190172 940513 PDR ADOCK 05 w w m E memy w w w ]000298

&&.,,pyy,,

DR w = m a m a a h B "Y10TI M lIG % WRl3 M 7,gn muuwa.aawun l

-. ~

- - ~..

/

U.S. Nuclear Regulatory Commission

' May 13,1994 Page 2,of 2 The District received final resolution of the GIP issues that were_ specific to CNS, including NRC acceptance of the seismic spectrum for CNS as " conservative design spectra", was on July 26,1993 (Reference 6). Given the District's commitment to integrate the IPEEE and the A-46 effort to the maximum extent possible, the need to perform the joint walkdowns during a refueling outage, and the scheduling of the next refueling outage, the District's next opportunity to perform the joint walkdowns will not occur until the 1995 refueling outage (currently scheduled for February 1995).13ased on the refueling outage schedule, the District expects to have the IPEEE evaluation completed and forwarded to the NRC no later than December 1995. This completion date allows for approximately the same amount of time to put together the final IPEEE report as what was anticipated subsequent to the 1993 refueling outage (Reference 2).

In addition, the District expects to complete and submit the A-46 evaluation no later than September 1995. Similar to the IPEEE completion date given above, this completion date also allows for approximately the same amount of time to put together the A-46 Seismic Evaluation Report (180 days following the refueling outage) as was previously anticipated in References 3 and 5. At the present time, the District is not aware of any major open items which would prohibit the joint A-46/IPEEE walkdowns during this outage. If any major open item develops -

or is discovered, that may impact the IPEEE or A-46 schedules, the District will inform the NRC on these matters as soon as practical.

Please contact me if you need any more information.

Sinc' rely,

/~

O llorn Vile President - Nuclear GRII/GRS/dnm ec:

Regional Administrator USNRC - Region IV Arlington, Texas NRC Resident inspector Cooper Nuclear Station l