Cp&L Carolina Power & Light Company December 29, 1982 Office of Nuclear Reactor Regulation ATTN:
Mr. D. B. Vassallo, Chief Operating Reactors Branch No. 2 United States Nuclear Regulatory Commission Washington, D.C.
20555 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS.1 AND 2 DOCKET NOS. 50-325 AND 50-324 LICENSE NOS. DPR-71 AND DPR-62 REQUEST FOR LICENSE AMENDMENT REACTIVITY ANOMALIES
Dear Mr. Vassallo:
SUMMARY
In accordance with the Code of Federal Regulations, Title 10, Part 50.90 and Part 2.101, Carolina Power & Light Company (CP&L) hereby requests revisions to the Technical Specifications (TS) for the Brunswick Steam Electric Plant (BSEP), Unit Nos. 1 and 2.
The purpose of these revisions is to clarify exactly when the reactivity anomaly surveillance is to be performed.
DISCUSSION Technical Specification 4.1.2.a states that the core reactivity is l
to be checked "During the first startup following CORE ALTERATIONS". The intent of this surveillance requirement is to insure that the anomaly check is j
done before the new core accumulates an entire effective full power month of exposure.
In the past, "During the first startup" has been interpreted as the entire time between initial rod pulls and the attainment of an equilibrium one hundred (100) percent power level.
I Since the anomaly check cannot be performed with a satisfactory l
degree of validity until a high, steady-state power level is achieved, the l
surveillance requirement should be changed to reflect this criterion.
'Ihe statement "During the first startup" is not sufficiently specific to indicate I
exactly when the check should be performed.
Revision of TS 4.1.2.a as attached, will eliminate any confusion arising from the surveillance requirements as currently written.
1 Enclosed are revised TS pages for Unit Nos. I and 2.
'Ihese changes will not require the initial reactivity anomaly check to be performed until an equilibrium power of at least 90 percent is achieved. Waiting until this power level to perform the anomaly check will not have a detrimental effect on plant safe';y since other tests performed at the initial criticality of a new cycle, specifically the shutdown margin test, indirectly test for reactivity l
anomalies. The results of the shutdown margin tests are used to verify that 20 !
0 FG01030001 821229 PDR ADOCK 05000324 f
PDR P
411 Fayetteville Street
- P. O. Box 1551
- Raleigh, N_ C. 27602 l
O*OO
- =
Mr. D. B. Vassallo. December 29, 1982 the actual core reactivity agrees with that expected.
This will provide an early indication of any core reactivity concerns prior to reaching the power level where actual reactivity anomaly testing is performed.
ADMINISTRATIVE INFORMATION You will find enclosed the revised TS pages with the changes indicated by vertical lines in the right-hand margins. We have evaluated this request in accordance with the criteria in 10CFR170.22 and have determined that this request involves an administrative issue; therefore, a single Class I and Class II license amendment fee is required for Units 1 and 2.
Our check for one thousand six hundred dollars ($1,600.00) is enclosed in payment of this fee.
Should you have any questions concerning this matter, please contact us.
Yours very truly, A
L. W. Eury Senior Vice Pr ident Power Sepply AWS/kj r (5813C2T4)
Attachment l
cc:
Mr. D. O. Myers (NRC-BSEP) l Mr. J. P. O'Reilly (NRC-RII)
\\
Mr. J. A. Van Vliet (NRC)
L. W. Eury, having been first duly sworn, did depose and say that the information contained herein is true and correct to his own personal knowledge or based upon information and belief.
_{oa $
/ OA (L
j Notary (Seal) l My commission expires:-
, ~
mmisskn txhres May gg, ggy l
l
..