Revised Final Deficiency Rept Re Defective Bettis Model T3 Series Actuation Yokes on Henry Pratt Co Valves.Due to Delay in Receipt of Replacement Parts & Const Scheduling,Required Mods Not Yet Completed
ML20070E395
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 12/10/1982
From: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, RDC-58(82), NUDOCS 8212170241
Download: ML20070E395 (1)


Text

sg

c. ; . L . [, st MIv  ; ;t; , r! y yi: p; pg->q33y 2

'I 'f l p

(' l r t( F j u t. n '

' t r;

1. i. a. it b ._

~. 7. m = p (_s g ; ;; so:i =,4 ,i! '

P.O DOX 5000 - CLEVELAND. OHlo 44101 - TELEPHONE (216) 622-9800 - ILLUMINATING BLDG - 55 PUBLICSOUARE Serving The Best Location in the Nation MURRAY R. EDELMAN December 10, 1982 VICE PRESIDENT NUCUAR Mr. James G. Keppler Regional Administrator, Region III Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission 799 Roosevelt Road ~

Glen Ellyn, Illinois 60137 RE: Perry Nuclear Power Plant Docket Nos. 50-440; 50-441 Bettis Model T3 Series Actuator Yokes [RDC 58(82)]

Dear Mr. Keppler:

As discussed with Mr. R. C. Knop of your office on December 2, 1982, the replacement of Bettis Model T3 Series Actuator Yokes on the eight Henry Pratt Co. valves supplied to PNPP is now scheduled to be completed by June 30, 1983.

In our final report pursuant to 10CFR50.55(e) on this subject dated August 5, 1982, we had stated that this work would be completed by November 29, 1982.

Due to a delay in receipt of replacement parts and construction scheduling, we have not yet been able to complete the required modifications.

Please call if there are any additional questions.

Sincerely, L

Murray R. .delman Vice President Nuclear Group MRE:pab l cc: Mr. M. L. Gildner NRC Site Of fice Director Of fice of Inspection and Enfor cement U.S. Nuclear Regula tory Commission Washington, D.C. 20555 U.S. Nuclear Regulatory Commission c/o Document Management Branch Washington, D.C. 20555 Mr. J. E. Konklin, Chief Projects Branch Section IA Division of Project and Resident Programs 8212170241 921210 PDR ADOCK 05000440 g/Eg S PDR DEC 13 E62