10-19-82 re: NRC Dockets 50-h00 and 50-h01 0.L.
00 H T,ED Shearon Harris Nucicar Power Plant Carolina Power & Light Co, et al, Annlicant s W OCT 22 All:0 gpgEvlbE' jU R ^
Dear Judges Kelley,
Carnenter and Bright:
When visiting the LPDR for Shearon Harris on 10-19-82 ( today ) tMANCH among docunents received 10-18-82 there (according to L*D" lib *arian Linda Hicknan), was a sheet showing CP&L files h0 conies of' its answers to NUC staff questions.
That is, CP&L sends N"C h0 conies, and then is connlaining it can 't find more than 2 more t o serve intervenors.
This is ridiculous.
(Accession #8209090023)
There is also a letter dated Sentenber 9,1982, accessicn
- 82091h0280, attached to an affidavit showing 1h ron-CP&L recinients (none of when anpear to be NRC either) for FSAR anendment #h.
These are folks CP&L has s ent co nie s to, a c c ond5 ng to the affidavit of S.R. 2nnerman, Manager, Licensing and Fernite, for CP&L.
I also spent about 1 and 3/h hours making 207 conies at 10 cents each while at the LPDR today.
Near ny hone in Durhan is a 3// cony self-se"vice niace, and a hd/co,y s elf-servica niace.
Within h blocks o' = $ s a niace that will do conying for ne for 5d/page.
I think ny time would be far nore nroductively used in reviewing CP&L's subnissions, though I try to nake a f ew notes while co ying on the LPDR's slow nachine.
At least this time it did not break down, and there were only har 5 others who needed or to use it, uhon I had to nake way for.
All this for an incomlete O'O Q Eo' cony of a docunent CP&L mailed off mnths ago (8/31/82) but which 58 IDQ the LPDR had not received at ny last visit.
I nade co nies there 6
9.27/82 and stopned by once (or more?) between then & now, but OO g<
nothing new had arrived. I ask you to take this info nto a ccount.
g I certify all parties have been served, Wells Eddle man
~
aso3
UNITED STATES OF AME9ICA NUCIJAR REGULATOFY COMMISSION In the matter of CAROLINA PO' DER & LIGHT CO. Et al. )
Dockets 50-h00 n.
Shearon Harris Nuclear Power Plant, Units 1 and 2
)
and 501.h01 0.L.
p CERTIFICATE 0F SERVICE I hereby certify that copies of
[b b [4L 6 7 b nl 2
[C 6&)TI CE Dk (fD CALMb HAVE been served this M day of hCMM 1981,bydeposit$n the US Mail, first-class posth6e prepaid, upon all parties whose names are listed below, except those whose names are rarked with i
an asterisk, for whom service was accormlished by Judges Ja :es Eelley, Glenn B=ight and James Caynter (1 cony each)
Atonic Safety and Licensirt Board US Nuclear Regulatory Connission Washington DC 20555 GeorEe F. Trowbridge (attorney for Anplicants)
Shaw, Pittnan, Potts & Trowbrid e E
1600 M St. NW Washington, DC 20036 Office of the Executive Legal Director Phyllis Lotchin, Ph.D.
Attn Dockets 50-1400/kO1 0?L.
10D 3ridle Run USNRC Chanel Hill Washington DC 20555
~
NC 2751h Dan Read Docketing and Service Section CEANGF/ELP Attn Docke ts 50-k00/h010.L.