Interim Deficiency Rept Re Welding Techniques Not Covered by Brown-Boveri Electric QA Program Used in Fabrication of safety-related Switchgear.Initially Reported on 820525.Next Rept Will Be Submitted by 830715
ML20069E365
Person / Time
Site: Marble Hill
Issue date: 03/14/1983
From: Shields S
PSI ENERGY, INC. A/K/A PUBLIC SERVICE CO. OF INDIANA
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, S82-12, SVP-0014-83, NUDOCS 8303220020
Download: ML20069E365 (2)


Text

f PUBLIC SERVICE INDIANA S. W. Shields March 14, 1983

! senior vice President . S82-12 Nuclear Division SVP-0014-83 Mr. James G. Keppler, Docket Nos.: STN 50-546 Regional Administrator STN 50-547 U. S. Nuclear Regulatory Commission Construction Permit Nos.:

Region III CPPR - 170 799 Roosevelt Road CPPR - 171 Glen Ellyn, Illinois 60137 Marble Hill Nuclear Generating Station - Units 1 and 2

Dear Mr. Keppler:

On May 25, 1982, Mr. S. J. Brewer of Public Service Company of Indiana, Inc. (PSI) notified your office of a potentially reportable item as required by 10 CFR 50.55(e). During an audit at Brown-Boveri Electric, Inc. (BBC) facilities PSI quality assurance personnel discovered that welding techniques not covered by BBC's quality assurance program were being used in the fabrication of safety-related switchgear. Such activ-ities are special processes and should have been controlled by procedure as required by 10 CFR 50, Appendix B, Criterion IX. It was also discovered that no controls were placed on the terminal lug crimping process and certification of circuit breaker wiring was unavailable. With these deficiencies it is possible that installed equipment could differ from j that used for IEEE 323/344 qualification.

BBC has rewritten part of their Quality Assurance Manual to address special processes and bring such activities into compliance with 10 CFR 50, Appendix B. BBC has revised its procedures to include

(

controls on welding and crimping activities and has provided certifi-l cation on circuit breaker wiring. Equipment fabricated prior to the audit and affected by the aforementioned activities has been identified on nonconformance reports. Work by PSI and BBC is continuing in an effort to close out the nonconformance reports.

This letter is intended to fulfill the requirements of an interim report as required by 10 CFR 50.55(e). A further report on this item will be filed on or before July 15, 1983.

i j 8303220020 830314 gDRADOCK05000Q ggg i g 23 P. O. Box 190, New Washington, Indiana 47162 812. 289.3000 gg

- ~ _ _ - - -

PUBUC.

SERVICE INDIANA Letter: J. G. Keppler_ March 14, 1983 i S82-12 SVP-0014-83 I If you have any questions regarding this matter, please contact me at your convenience.

~

S cerel ,

l i S. W. Shields SWS/LGY/bak 1 cc: Director of Inspection & Enforcement

U. S. Nuclear Regulatory Commission Washington, D. C. 20555

~