1 OPERATING DATA REPORT DOCKET NO. 50-369 DATE 3-15-83 C051PLETED BY J. A. Reavis TELEP110NE 704-373-7567 OPERATING STATUS Notes
- NOTE: Nameplate Rating McGuire Unit 1
!. Unit Name:
(Gross MWe) calculated as
- 2. Reporting Period: February 1,1983-February 28, 1983 3411 1450.000 MVA x.90 power
- 3. L.uensed Thennal Power (Mjvt):
factor per Page iii, 1305*
- 4. Nameplate Rating (Grow 3DVel:
NUPEG-0020.
1180
- 5. Design Electrical Ratin;(Net SIWei:
- 6..\\taximum Dependable Capacity (Grow 51Wel:
U 80
- 7. Maximum Dependable Capacity (Net.\\l Vel:
S. If Changes Occur in Capacity Rating (licms Nuraber 3 Throu;h 7) Since Last Report Give Reasons:
None E "*
- 9. Power Level To Which Restricted,if Any (Net MWe):
- 10. Reasons Far Restrictions. If Any:
Tnis Mouh Yr..to.Dat e Cumulative 10 920.0 672.0 1 416.0 II. Hours h Reporting Period
- 12. Number Of Hours Reactor Was Critical 0.0 494.9 7 633.0
- 13. Reactor Reserve Shutdown flours 0.0 494.9 7 587.1
- 14. Ilours Generator on.Line
- 15. Unit Reserse Shutdown flours
- 16. Gross Thermal Energy Generated (>lWil) 0 857 172 14 359 590 11 293 837 4 920 428 1". Gross Electrical Energy Generated (SIWil)
IS. Net Electrical Energy Generated (MWil)
-4 125 268 287 4 589 610
- 19. Unit Service Factor 0.0 35.0 69.5 0.0 35.0 69.5
-20. Unit Availability Factor
- 21. Unit Capacity Factor (Using MDC Neti 0.0 16.1 35.6 0.0 16.1 35.6
- 22. Unit Capacity Factor (Using DER Net)
- 23. Unit Forced Outa;c Rate 0.0 0.R 71
't
- 24. Shutdowns Scheduled Oser Nest 6 Months (Type. Date.and Duration of Each1:
Current 1v doinst Steam Generator Modification April 19, 1983
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
2b. Units in Test Status (Prior io Commercial Operation):
Forecast Achiesed INITI \\ L CRITICA L1TY INITI.\\ L ELEC 1 RICI f Y COslNIERCI A L Ort.R A flON 8303180376 830315 gop;i PDR ADOCK 05000369 R
PDR l
i
DOCKET NO. 50-369 UNIT McGuire 1 3-U-83 DATE AVERAGE DAILY UNIT POWER LEVEL MONTH February, 1983 AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL DAY (MWe-net)
DAY (MWe-net) 17 1,
2 18 3
10
~-
20 4
4 5
21 6
22 23
'7 8
24 g
25 10 26 11 27 12 28 13 29 14 30 15 31 1S DAILY UNIT POWER LEVEL FOR\\1 INSTRlWTIONS On this fonn, hst the averare daily unit power level in MWe net for each day in the reporting n.onth.
Compute to the nearest whole megawatt.
These figures will I e used to plot a graph for caeh reporting month. Note that by usini! maximum dependable capacity for the net electrical ratin of the unit. there may be ineasions when the daily average power levet euceds the 1001 hne f or tiie restricted power lesel hne). In such c.ist, the average daily unit power output sheet should be footnoted to t splam the app.uent anomaly.
.g.
.~.
50-369 DOCKET NO.
~
UNITSifUTDOWNS AND POWER I:iiDUCT!ONS UNIT NAME McGuire 1 a
DATE 3-15-83 J. A. Reavis RI. PORT MONTI! February, 1983 COMPLETED HY TELEPflONE 704-373-7567 i
c i
i.
t a.
)
.!E 3*
.E Licens::s 3 r, fvt Cause & Coerective No.
Date i
5g 2 s E-Event 3,7 eT Action to H
$E js @ g Report a mO EO Pievent Itceurtence o
b 4
1A 83-02-01 S
672,00 H
CB HTEXCH Dutage continues for modification of steam generators. Turbine. work, main' generator work, ice condenser work, ther-mal sleeve work, and moisture separator, j
and reheater repairs are also in progress i
4 4
4 i
l 1
I 2
3 4
i F: Forced Reamn:
Methoti:
Exhibit G. Instructions S: Scheduled A Eiguipment Failure (Explain) 1 Matiu:'t for Preparation of Data H-Maintenance of Test'
~
2 Manual Scram.
Entry Sheets for I.ieensee 3
1 Automatie Scram.
Event Report (1.ElO File INtlREG.
C Refueling D Regulatory Restriction
-4 Other (lixplain) 0161) 1 E-Ope;ator Training & License Examination F Administrative 5
G Opeiational lirror (Explain) '
Exhibit i.Same Source 19/77)
!! Other (lixplaio) 1 h
DOCKET NO:
50-369 UNIT:
McGuire 1
~
DATE:
3-15-83
~
NARRATIVE SU) DIARY Month:
February, 1983 McGuire Unit 1 continues with the steam generator :nodification outage.
Work on the main tarbine, main generator, ice condenser, the mal sleeves, and maisture separator and reheaters is continuing also. The unit is expected to returr; to service at full load in April,1983.
e
.e.
.o.
' MONTHLY REFUELING INFORMATION REQUEST McGuire Unit 1 1.
Facility name:
2.
Scheduled next refueling shutdown:
January, 1984 3.
Scheduled restart following refueling:
4.
Will refueling or resumption of operation thereaf ter require a technical specification change.or other license amendment?
N/A If yes, what will these be?
If no2 has reload design and core configuration besc. reviewed by Safety Review Committee regarding unreviewed safety questions?
N/A 5.
Scheduled date(s) for submitting proposed licensing action and auppcrting informatica: N/A i
6.
Important licensing considerations (new or different design or supplier, unreviewed design cr performance analysis methods, significant changes in
]
design or new operating procedures).
N/A l.
Number of fuel assemblies (a) in the core:
0 220 (b) in the spent fuel pool:
500 8.
Present licensed fuel pool capacity:
Size of requested or planned increase:
9.
Projected date of last refueling which can be accommodated by present licensed capacity:
March 15, 1983 DUKE POWER COMPANY Date: