Final Deficiency Rept Re Main Steam Isolation Bypass Control Valves Mfg by Masoneilan.Initially Reported on 830211.Valves Will Be Reworked & Corrected Prior to Fuel Load
ML20069D096
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 03/11/1983
From: Koester G
KANSAS GAS & ELECTRIC CO.
To: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, KMLNRC-83-025, KMLNRC-83-25, NUDOCS 8303180249
Download: ML20069D096 (1)


Text

-

KANSAS GAS AND ELECTRIC COMPANY THE ELECTAC COMPANY GLENN L dOESTEft un m,w.v. ucu..

March 11, 1983 y (.% ; : l!

j WA'd.1

~7(

Mr. W.C. Seidle, Chief Reactor Projects Branch 2

,jj,

,j U.S. Nuclear Regulatory Commission l\\

gl Region IV

{

l lj 611 Ryan Plaza Drive, Suite 1000 L

Arlington, Texas 76011 1

KMLNRC 83-025 Re:

Docket No. STN 50-482 Subj: Final 10CFR50.55(e) Report - Masoneilan Valves

Dear Mr. Seidle :

This letter is submitted as the Final 10CFR50.55(e) Report concerning main steam isolation bypass control valves manufactured by Masoneilan.

This subject was initially reported by Mr. Gene Rathbun of Kansas Gas and Electric Company (KG&E) to Mr. William Johnson of the Nuclear Regulatory Commission, Region IV, on February ll,1983.

KG&E recently had the four Main Steam Isolation bypass control valves disassembled and inspected by the Vendor's representative. The inspection was performed because of deficiencies discovered in valves of the same type at Union Electric's Callaway Plant. KG&E's inspection revealed that three of the four valves in question had deficiencies. Machining on the main plug of two valves exceeded the manufacturer's requirements and the third valve had an incorrect cage installed. Nonconformance Report ISN8608P has been initiated to document the deficiencies and provide appropriate control measures.

In lieu of performing an analysis of the safety implications of these deficiencies, KG&E made the conservative assumption that the deficiencies could have adversely affected the safety of operations. Therefore, KG&E will have the valves reworked to bring them into compliance with design requirements. It is anticipated that the rework will be completed prior to the end of this year; but, in any event, the corrective action will be completed prior to fuel load.

If you have any questions concerning this subject, please direct them to me or to Mr. Otto Maynard of my staff.

Yours very truly, GLK:bb pf tj /)

cc: RCDeYoung O

HRoberds/SSchum

[k 97 8303180249 830311 PDR ADOCK 05000482 S