GENER AL $ ELECTRIC NUCLEAR POWER SYSTEMS DIVISION GENERAL ELECTRIC COMPANY,175 CURTNER AVE., SAN JOSE, CALIFORNIA 95125 MFN 054-83 MC 682 (408) 925-5040 JNF 016-83 March 16, 1983 U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Washington, DC 20555 Attention:
Mr. D.G. Eisenhut, Director Division of Licensing Gentlemen:
SUBJECT:
IN THE MATTER OF 238 NUCLEAR ISLAND GENERAL ELECTRIC STANDARD SAFETY ANALYSIS REPORT (GESSAR II)
DOCKET NO. STN 50-447 REVISED DRAFT RESPONSES AND RESPONSES TO DISCUSSION ITEMS Attached please find revised final draft responses to selected Auxiliary Systems Branch questions of the Commission's August 25, 1982 information request.
Only modifications (new or revised) to the responses of the referenced letter are provided.
Also attached are draft responses to Equipment Qualification Branch discussion items.
Responses are provided in the attachments as indicated below:
Attachment Number 1
Draft Responses to Auxiliary Systems Branch Questions 2
Draft Responses to Equipment Qualification Branch Discussion Items Sincere
/
[d $
d
% lenn G rwood, Manager Nuclear Safety & Licensing Operation Attachments cc:
F.J. Miraglia (w/o attachments)
C.0. Thomas (w/o attachments)
D.C. Scaletti L.S. Gifford (w/o attachments) 8303180017 830316 PDR ADOCK 05000447 A
g e
g e
ATTACHMENT N0e 1 DRAFT RESPONSES TO AUXILIARY SYSTEMS BRANCH QUESTIONS e
e
410.24 Verify that the information provided in Section 9.1.3 of your (9.1.3)
FSAR is based on the new high density spent fuel pool storage capacity. Provide additional information regarding the spent i
fuel decay heat load for the maximum, normal and abnormal heat loads as discussed in Items 1.d and 1.h of the review procedures in Section 9.1.3 of the SRP.
410.24 Response j
Paragraph 9.1.3.1.2(4) for the Power Generation Design Basis i
states that the heat load is the sum of 1) the 37% core batch i _
just removed at the last 18-month equilibrium fuel cycle, with four year exposure, and 2) the 37% core batch from the previous refueling outage.
The heat load, therefore, is a function of two 37% batches which means that the entire heat capacity of the fuel storage pool does not enter the design.
The fresh core supplies about 90% of the heat load and the aged core fraction supplies the other 10% of the design load.
The density of the fuel racks would change the heat load calculation only if all of the potential batches stored within the pool are used toward the total design value.
Even under these conditions, the design value would be only slightly affected.
Paragraph 9.1.3.2 describes that the above design core load for heat capacity is based upon maintaining 1250F in the pool. This is the system design maximum load and temperature combination.
However, if conditions exist as described in paragraph 9.1.3.3, wherein up to a full reactor core is plaged into the pool, instead of the 37% batch, the pool may go to 150 F.
But adding the RHR cooling capacity will keep the temperature at a maximum of 1250F.
Item 1.h(ii) states that the normal maximum spent fuel heat load is set as one refueling load at equilibrium conditions after 150 hours0.00174 days <br />0.0417 hours <br />2.480159e-4 weeks <br />5.7075e-5 months <br /> decay, with one refueling load after 1 year decay, and 140 7 0
pool temperature. The GESSAR II design basis is more conservative in that the refueling load is assumed at 112 hours0.0013 days <br />0.0311 hours <br />1.851852e-4 weeks <br />4.2616e-5 months <br /> decay and the maximum pool temperature is set at 1250F.
The shorter fresh batch decay time adds to the total heat load sum of the two batches.
Item 1.h(iii) states that the spent fuel pool cooling system shall 1
have capacity for a full core at equilibrium and one refueling load, at 36 days, for a total of 1-1/3 core fraction.
Item 1.h(iv) further adds 1/3 core for pool capacity over 1-1/3 batches.
If RHR cooling capacity is included in the spent fuel pool cooling system, then the cooling capacity is more than adequate to meet these criteria.
The two fuel pool heat exchangers cover only the normal maximum reflecting item 1.h(ii) and the RHR covers any additional load while the reactor is open.
i ll 4
l
410.37 In Section 9.3.1.2 of your FSAR, you state that the instrument (6.8) air supplied to the main steam safety relief valves and isolation (9.3.1) valves is filtered to remove all particles larger than 50 microns.
To be consistent with Section 9.3.1 of the SRP and ANSI MC11.1-1976, this air should be filtered to 3 microns or less.
Revise your design to meet this criterion. Address, as an interface requirement if necessary, the maximum total oil content of the air supply to these valves and their accumulators in accordance with Section 9.3.1 of the SRP. These same requirements should also be addressed for the pneumatic supply system.
Response
The text has been changed to reflect the 3 micron filtering.
This will require the line upstream of the filter to be changed from carbon steel to galvanized.
The P&ID's will be changed accordingly.
With respect to air quality see response to question 410.33.
22A7007 GESSAR II Rsv. 0 238 NUCLEAR ISLAND
)
9.3.1.2 System Description (Continued)
Instrument air to the Main Steam SRVs and isolation valves is 410.37 Corrosion-resistant materials filtered to less than 3 microns.
w N e W of the filter.
cr used All accumulators are constructed of corrosion-resiatant material Accumulator mounting orientation is cnd include low point drains.
Accumulators are with the major axis in a vertical direction.
located in a manner which prevents their failure from generating missiles or impairing the function of any surrounding safety-related equipment.
The accumulator support structure is designed to sustain the maximum thrust loads developed during a failure of the largest A flexible section of austen-line connected to the accumulator.
itic stainless steel pipe is installed in the piping from the accumulators of the Main Steam SRVs and MSIVs to the associated This pipe section accommodates the relative motion of actuators.
the steamline with respect to the accumulator.
I Air supply lines to the accumulators include a checkvalve to pre-The check-vent backleakage upon loss of supply line pressure.
valve is constructed of corrosion-resistant material and is spring shutoff.
Pipe loaded with a resilient seal for "bubblatight" between the MSIV air control valves and accumulators is 1 1/4 in.
diameter minimum and 10 ft maximum' equivalent length, to maintain valve response.
9.3.1.3 Safety Evaluation The operation of the Instrument and Service Air Systems is not*
required to assure of any of the following:
coolant pressure boundary; (1) integrity of the reactor 9.3-4 e
-wwg-v g,-
-- +
w---
gw weww y
w w-m-ee te -w n - -, -ee-w
w
--2
~
/
GESSAR II 22A7007 238 NUCLEAR ISLAND Rsv. 0 6.8.2
System Description
The Pneumatic Supply System provides dry, oil-free, compressed the steam-condensing control air for the actuators of the ADS SRV, volves'of the RHR System, the specified valves of the SGTS, Hydrogen Mixing and Drywell and Containment Vacuum Relief Systems (cee Figure 6.8-1 for details).
I The Pneumatic Supply System is separated into two independent Division 1 supplies air to the ADS valves and divisions.
cccumulators on steamlines A and C and to specified valves of the SGTS, Hydrogen Mixing and Drywell and Containment RHR System, Division 2 supplies air to the ADS valves Vacuum Relief Systems.
cnd accumulators on steamlines B and D and to specified valves of the RHR Systeht, SdTS, Hydrogen Mixing and Drywell and Containment Operation of one division is sufficient to Vacuum Relief Systems.
meet the requirements of the systems serviced.
To ensure adequate air supply under both normal and accident conditions, each division is separated by nonsafety and assured cafety.
- The nonsafety portion of each division contains an air compressor and associated air intake filter and after cooler to l'
This air is dried provide a continuous source of compressed air.
in a parallel flow air dryer, with its associated prefilters and M
Supply after filters, and is then directed to the air receiver.
AS Sh o" E
rom the receiver service the air valves.E Q t { N o
headers ou i s R 4t r.L w s4L g a
wc v
+
bI
"'#p
,G G.S-b hle. d y 4 1. All Pi p q u f 5 ow 4 e.-s LOPP and/or system low pressure, the compressor supply During LOCA, I
to the receiver is automatically cut off, and the assured safety air supply valve is opened.
The safety air supply consists of a bank of high pressure air bottles, with a pressure-reducing valve, The bottled supply is adequate piped directly to the air receiver.
to meet emergency air requirements for a period of seven days.
i The operator must replace some of the bottles after this period N b *"
a j yoga.d hd f f 9 C
s% se m> sM '
/
y 6.8-2 f
410.38 Identify the testing requirements and frequency of tests for;the (6.8) safety-related accumulators and check valves provided in the (9.3.1) compressed air system and pneumatic supply system.
To assure continuous reliable functioning of the instrument air system and the pneumatic supply system, provide a procedure or an interface requirement for a procedure which requires periodic testing of the air quality for both the instrument air system and the pneumatic supply system.
Response
Response to this question is provided in revised Subsections 9.3.1.4 and 6.8.4.
m 9
-~
~ -'
44atuut GESSAR II Rsv. O 238 NUCLEAR ISLAND N
9.3.1.3 Safety Evaluation (Continued) energy in the building environment generates missiles nor r
impairs the functioning of safety-related equipment.
Containment isolation valves and associated accumulators
~
are located a minimum' distance from the coiitainment wall.
All of the accumulators, piping connecting the accumula-(6) t structures
, tors and the actuator supply line and suppor installed and j
for the accumulators are designed, built, tested to ASME Code,Section III, Safety Class 3 and Seismic Category I.
Support structures are designed to absorb the thrust (7) loads that would be developed assuming a failure of the largest pipe connected to the accumulator.
'(
9.3.1.4 Inspection e.nd Testing Requirements The Instrument Air System and Service Air System are proved Portions of am operable by their use during normal plant operation.
99 both systems normally closed to airflow can be tested to ensure 5 ww ut operability and integrity of each system. 4 + dro Av w N Anua.g &Www4ct WivM ANS( Me l {.t -IT7/..
r u ss u.9 tegaoygcA M ro The air supply system to the MSIV and main steam SRV shall be sub-A1=Ma. ' =
- /
jected to preoperational tests in accordance with Chapter 14 3
wHw.44 PEc+.noce. TESTS se TWC-CBEcV- %%AJE.S Ado 4c.cA;r,y47,pg, }
W a v wo % e c o @ w c rt;.9 Te Anuo.E var Vet c@CPAEnbWT*
Y
, (.
The motor-operated isolation valves are capable of being tested to l
l assure their o'perational integrity by manual actuation of a switch located in the control room and by observation of associated posi'-
Test and vent connections are provided at tion indication lights.
l the isolation valve penetrations in order to verify their leaktightness.
',d J
i 9.3-7 I
-. - - - - -. -. ~ -. -
-v--
--.-----y w.-
GESSAR II 22A7007
+
238 NUCLEAR ISLAND Rev. 0 6.8.3 System. Evaluation (Continued) 5 which are designed to Seismic category I, ASME Code III, Class 2, Quality Group B and Quality Assurance B requirements.
The pneumatic supply is separated into two independent divisions, with each division capable of supplying 100% of the requirements of the division being serviced.
Each division is mechanically and electrically separated from the other.
The system satisfies the components' air demands during all plant operation conditions (normal through faulted).
Safety grade portions of the Pneumatic Supply System are capable of being isolated from the nonsafety parts and retaining their function during LOCA and/or seismic events under which any nonsafety parts may be damaged.
Pipe routing of Division 1 and Division 2 pneumatic air is kept
(
separated by enough space so that a single fire, equipment dropping accident, strike from a single high energy whipping pipe, jet force from a single broken pipe, internally generated missile i
or wetting equipment with spraying water cannot prevent the other division from accomplishing its safety function.
Separation is accomplished by spatial separation or by a reinforced concrete barrier, to ensure separation of each pneumatic air division from any systems and components which belong to the other pneumatic air division.
6.8.4 Inspection and Testing Requirements Periodic in-service inspection of components, in accordance with
~*
to ensure the capability and integrity of the ASME Section XI, bkI b d'NN Po
^
system is mandatory. Aw pa b ca.
udL A MSI Mc t 1.1 - t 9 7 6.
.h ass a cwp e
6.8-5
GESSAR II 22A7007
~
238 NUCLEAR ISLAND Rev. 0 6.8.4 Inspection and Testing Requirements (Continued)
The air-operated isolation valves are capable of being tested to assure their operational integrity by manual actuation of a switch located in the control room and by observation of associated position indication lights.
Test and vent connections are provided at the containment isolation valves in order to verify their leaktightness.
Operation of valves and associated equipment used to switch from the nonsafety to safety air supply can be tested to assure operational integrity by manual actuation of a switch 03 located in the control room and by observation of associated position indication ights. Pe e g o ch c ke b of-%-
Ck V a k v4 c-urs shall b-c c.c w ck w c*F M M e CA S Ju g j 3 Acc e&w\\Is va v4 oper ya y
6.8.5 Instrumentatio% Requirements Supply-air-header-pressure and moisture-content sensors are located at the supply header of each division and monitored in the control room.
A pressure sensor is provided for the safety air supply, and an alarm signals low air pressure.
Automatic isolation valves are provided for the safety and non-safety air supply.
Upon a LOCA and/or detection of nonsafety air low pressure, the system automatically isolates the nonsafety air supply and opens the isolation valve to the safety air supply.
A remote manual switch and open/ closed position lights are pro-vided in the control room for verification of proper valve operation.
The compressor is shut down by a high backpressure signal or by manual override.
Air-operated isolation valves in series are provided for the pneumatic air pipe penetrations through the containment and drywell.
These valves are not automatically closed by a LOCA isolation signal.
Air supply for the isolation valve air operators is from the Pneumatic Supply System itself.
The 6.8-6
4 w
ATTACHMENT NO. 2 DRAFT RESPONSES TO EQUIPMENT QUALIFICATION BRANCH DISCUSSION ITEMS
Item 1 Applicability of NEDE-24326-1-P Section 4.4 qualification methodology to mechanical equipment.
Response
i A reference will be added to Section 3.9.3.2 as shown on page 3.9-76.
Item 2 Preference of tests and analyses of assemblies over separate components.
Response
A statement will be added to Subsection 3.10.1.1 as shown on page 3.10-2 showing tests or analyses of assemblies is prefered to tests or analyses on separate components.
Item 3 Applicability of R.G.1.148.
Response
A reference to R.G.1.148 will be added to Subsection 3.10.1.3 as shown on page 3.10-3.
Note the addition of Subsection 1.8.148.
Item 4 Justification of less than 5 OBE's.
Response
As described in revised response 271.04a of Attachment No. 6 to the letter from Glenn G. Sherwood to D.G. Eisenhut dated February 17, 1983 (MFN 035-83),
5 OBEs combined with the appropriate hydrodynamic loads are utilized for equipment qualification.
Item 5 Usage of NUREG-0484 for combining dynamic loads.
Response
As described in revised response 271.02a of Attachment No. 6 to the letter from Glenn G. Sherwood dated February 17,1983 (MFN 035-83), hydrodynamic and seismic loads are combined using the methodology of NUREG-0484.
1 Item 6 Documentation of justification for using single axis or single frequency tests.
Response
A statement will be added to Subsection 3.10.2.1.4 as shown on page 3.10-9 to require the final test report justify using single axis or single frequency tests for all items that are tested in this manner.
Item 7 Confirmation that all safety-related does not have any natural freq'ency below u
4 Hz.
Response
This is part of the confirmatory response to Structural and Geotechnical Engineering Branch questions 220.09 and 220.44 scheduled for completion in April 1983.
I 1.
1
~
GESSAR II 22A7007 238 NUCLEAR ISLAND Rav. )h 4 i
m 3.9.3.1.20 Non-NSSS Piping k 4.3 pmst h o Th% )
basis in accordance with Appendix F of the code.
For Class 2 and 3 piping, stresses are calculated on an elastic basis in accord-ance with Appendix F of the code.
For Class 2 and 3 piping, stresses are calculated on an elastic basis in accordance with NC/ND-3600 of the code.
3.9.3.2 Pump and Valve Operability Assurance Table 3.9-14 lists the active pumps and valves in the NSSS. Tables 3.9-15 and 3.9-16 list the active non-NSSS pumps and valves, respectively.
Active mechanical equipment are classified as Seismic Category I and each is designed to perform a mechanical motion for its safety funtion during the life of the plant under postulated plant condi-tions.
Equipment with faulted condition functional requirements include active pumps and valves in fluid systems such as the Resid-ual Heat Removal System,. Core Spray System, and > bin Steam System.
Safety-related valve's and pumps are qualified by testing and analysis and by satisfying the stress and deformation criteria at the critical locations.
Operability is assured by meeting the requirements of the programs defined in Subsection 3.9.2.2, Section 3.10, Section 3.11 and the following subsections.
)
IN SERTj
~
3.9*3.2.1 ECCS Pump / Motors All actire pumps are qualified for Operability by first being subjected t0 rigid tests both prior to installa:icn in the plant and after installation in the plant.
The in-shcp tests include:
(1) ~ hydrostati: tests of pressure-retaining parts of 1255 of the design pressure;.' 2 ) seal leakage tests; and (3) perf:rmanca tests while the pump is operated with flow to determine total developed nead, minimum and maximum head and ne: pcsitive suction head (NPSE) requirements.
Also monitored during these operating tests are 3.9-76
19SELT Fok PAGE 3.9 ~l 6 m
SeMson 4.4
.o T W s D E
'24'3 2 6 I - P app tco l
3o b'b _sda etruw
- 4 k s e t s m s c.
- o. r c,
~
p.J LL %4Ldc3 3 p~~rd g\\xm 1 4.
am we os -usu-i- e s s ce h okAAcd aa M aJ e \\ cd vs ta k d.
.m,p p.
+
9 O
e,-
.M.
-nm e-
-=en.
e.-n.
O-(
N. C. Sh sMe.,'GNd Elech g
t Eww ren%4 Qulcri P
'j Jueg tses (Pne wh of robva-
~g
eueduurun
@.-f 238 NUCLEAR ISLAND Rav.fl/p 3.10.1 Seismic Qualification Criteria (Including Hydrodynamic I
Loads) b od D
3.10.1.1 Selection of Qualification Method 14 % L Qualification of Seismic Category I instrumentation and electrical equipment is accomplished by test, analysis, or a combination of the two methods.
In general, analysis is used to supplement test data although simple components may lend themselves to dynamic analysis in lieu of full-scale testing.
The deciding factors for choosing between tests or analysis include:
(1) magnitude and frequency of the seismic and hydrodynamic loadings; (2) environmental conditions (Subsection 3.11.1) associated with the dynamic loadings; (3) nature of the safety function (s);
(4) size and complexity of the equipment; and (5) dynamic characteristics of expected failure modes (structural or functional).
N (T W Slii,n T) 3.10.1.2 Input Motion The input motion for the qualification of equipment and supports is defined by response spectra.
The response spectra (Figures 3.10-1 through 3.10-84) are generated from the building dynamic analysis.
They are grouped by buildings and by elevations.
This RRS definition incorporates the contribution of hydrodynamic loads 3.10-2
-nam
Tpsw&T F Ott-P A GE 3. \\ 0 - b
__.CT{ _ 7 k.
M a-c b o m. OE
%k bbn. %+
b
~
6 V G l
e^ (
^^im K 2 s
a,y3
(
ligs-sqjdfMb;k e,
M A, ac aal y.FunGL
~
.en%%4AJs aJ~~
oc 9
.seg _ A u m 7 4 te.3., m m e.J
^
i d
,1 ~ o d Ya e ~7L e
e a.~A 4k 2., Q %% ~
s so U
~4J e-u
~~u
).
pu%
3 e
w 0
4
---,y 7-
--,y
~
~
GESSAR II 22A7007 238 NUCLEAR ISLAND Rev./fl4 3.10.1.2 Input Motion (Continued) in the following combination which incorporates all possible combinations:
h5 f* A SSE + AP + LOCA + SRV 9
where Mm AP = annulus pressurization LOCA = loss of coolant accident SRV = safety / relief valve The curves for the SSE are obtained by doubling the acceleration values of the corresponding OBE curves.
When one type of equip-ment is located at several elevations and/or in several buildings, the governing response spectra are specified.
3.10.1.3 Seismic Qualification Program The qualification program for Seismic Category I instrumentation and electrical equipment is designed to conform to the require-ments of IEEE 323-1974 as modified and endorsed by Regulatory Guide 1.89.
In addition, the program is intended to meet the criteria contained in IEEE 344-1975 as modified and endorsed by Regulatory Guide 1.100.
Regulatory Guide 1.100 endorses IEEE 344-1975 with the exceptions of using a static coefficient of 1.5 without justification, the use of a test response spectrum (TRS) that does not envelop the RRS for single frequency tests, the use of the sine sweep test method, and the lack of malfunction data in the test documentation.
This qualificat on program satisfies 4
s t these requirements b oIk g/
- f )
i co m bs'Y w.kh d d <3 Gwsda. L.t4% M tM I"
l u
Swb L. %. t 4 9.
e 3.10.2 Method and Procedures for Qualifying Electrical Equipment and Instrumentation
(
l The following subsections describe the methods and procedures used to qualify by test or analysis Seismic Category I instrumen-tation and electrical equipment for operation during and after an 3.10-3
~
GESSAR II Rav. 16 238 NUCLEAR ISLAND April 1981_
Regulatory Guide 1.148, Revision 0, Dated 9
1.8.148 Assemblies Functional Specification for Active Valvein Syste Plants
Title:
tion and operability This guide delineates requirements for funcfety.
This guide for valve assemblies in systems important to sain systems important i
will be applied to active valve assembl espower plants.
to safety in light-water-cooled nuclear Evaluation s
ide by using the The GESSAR II design complies with this gu following GE interpretation:
ifications for Position C.l.c (ll - GESSAR II design specirements without valves include all needed operability requ having to reference other documents.
the GE design docu-Position C.1.'c (2l - Not needed, since
" flow of require-mentation system is based on a " top-down,
~
ments to assure requirement traceability.
d not be specified Position C.2.d - Seat leakage limits nee t s the conse-for BWR safety / relief valves since GE evalua eChapter 15, an quences of " stuck-open" valves in FSARk open" valve.
leakage could never be higher than the "stac -
O A-P%M i
L_
- _?
i l
~
)
l 1.8.148-1/1.8.148-2
GESSAR II
- 22A7007, 238 NUCLEAR ISLAND Rev. g p9 3.10.2.1.4 Final Test Report (Continued)
(3) calculation of equipment damping coefficient if there is resonance in the 1-60 Hz range or over the range of the test response spectra; y
~
(4) test equipment used; 7
'N 7 o s y mn sst a
(5) approval signature and dates; I-% $
(6) description of test facility; (7) summary of results; 2nd *-
(8) conclusion as to equipment seismic (including hydro-dynamic loads) qualification ~ees d
- 3m 3
- M
\\
(9)
Nw s h b e d o w d o c u s s a 5sk' le N3s A -ka d. J w &s f3 sh.-for a t t s kom S w<.nnse.
s 3.10.2.2 Qualification by Analysis The procedures presented in the following subsections apply to the qualification of equipment by analysis.
3.10.2.2.1 Analysis Methods Dynamic analysis or an equivalent static analysis is employed to qualify the equipment.
In general, the choice of the analysis is 1
)
based on the expected design margin, since the static coefficient method (the easiest to perform) is far more conservative than the dynamic analysis method.
If the fundamental frequency of the equipment is above the input excitation frequency, the equipment is considered rigid.
In this case, the loads on each component can be determined statically by concentrating its mass at its center of gravity and multiplying the values of the mass with the appropriate maximum floor 3.10-9
. -.