Revised Interim Deficiency Rept Re Pressurizer Missing Lockwires on Cover Plate Cap Screws,Originally Reported 811203.Submittal of Final Rept Delayed to 820421 Due to Extensive Investigation & Evaluation
ML20069C160
Person / Time
Site: Palo Verde 
Issue date: 02/19/1982
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Faulkenberry B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
10CFR-050.55E, 10CFR-50.55E, ANPP-20221-GHD, NUDOCS 8203080289
Download: ML20069C160 (2)


Text

[6j.

Docket Nos. 50-528/529/530

,3 JI 50 55(e) Report e

g YY$$

$5YY Y$YhY $$$N.$$

P. O. B O X 2l0 6 0 PHOENIX. Am2ON A 85036 February 19, 1982 ANPP-20221-Gild /BSK U. S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210

^<' // /Jp Walnut Creek, California 94596-5368 FEB 26 1982 co Attention:

Pr. B.11. Faulkenberry, Chief g

Reactor Construction and Engineering Support Branch SgggI1f 0

Subject:

Time Extension for Report - DER 81-45 b

M4R g 082Aj A 50.55(e) Potentially Reportable Deficiency Relatin

-7) to Unit 1 Pressurizer Missing Lockwires on Cover Pla 9 Cap Screws File: 82-019-026 g

D.4.33.2 g

Reference:

(A) Telephone Conversation between J. Eckhardt and B..Kaplan on December 3, 1981 (B) ANPP-19808, dated December 31, 1981 (Interim Report)

Dear Sir:

The NRC was notified of a potentially reportabic deficiency in Reference (A) and an Interim Report was transmitted by Reference (B).

At that time, it was estimated that a Final Report would be available by March 3, 1982.

Due to the extensive investigation and evaluation required, it is now expected that this infor1 nation will be finalized by April 21, 1982, when a complete report will be submitted.

There is no new information or change to the Interim Report a thi 4

Very truly ours, Ch ql E. E. Van Brunt, Jr.

APS Vice President Nuclear Projects ANPP Project Director EEVBJr/ Gild:ske cc: See Attached Page 2 1EO F203080289 820219

~

/ /

PDR ADOCK 05000528 S

PDR J}&g -/j)

+

.e U. S. Nuclear Rcgulatory Commission Attention: Mr. B. H. Faulkenberry, Chief ANPP-20221-CHD/BSK February 19, 1982 Page 2 cc:

Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.

20555 J. A. Roedel D. B. Fasnacht G. C. Andognini F. W. Hartley J. M. Allen A. C. Rogers B. S. Kaplan W. E. Ide J. Vorces J. A. Brand A.

C.~ Cehr W. J. Stubblefield W. C. Bingham R. L. Patterson R. W. Welcher R. M. Grant D. R. Hawkinson L. E. Vorderbrueggen R. L. Greenfield Assistant Attorney General Bataan Memorial Building Santa Fe, New Mexico 87503 Ms. Patricia Lee Hourihan 6413 South 26th Street Phoenix, Arizona 85040 i