O CD&L Carolina Power & Light Company December 6, 1982 Office of Nuclear Reactor Regulation ATTN:
Mr. D. B. Vassall;, Chief Operating Reactors Branch No. 2 United States Nuclear Regulatory Commission Washington, D.C.
20555 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-325 AND 50-324 LICENSE NOS. DPR-71 AND DPR-62 REQUEST FOR INFORMATION EMERGENCY OPERATIONS FACILITY
Dear Mr. Vassallo:
On December 2, 1982, NRC's Project Manager for Carolina Power &
Light Company's (CP&L) Brunswick Plant verbally requested that certain information be confirmed to NRC via letter. The requested information is in regard to the Faergency Operations Facility (EOF).
The enclosure to this letter summarizes the requested information and our responses. The information provided in the enclosure is based on our understanding of SECY 82-111.
Please contact my staff should you have any questions.
Yours very truly,
,;.'?tx=
S.
Zimmerman i
Manager Licensing & Permits l
JAM /lr (5821C2T3) l Enclosure 1
l cc:
Mr. D. O. Myers (NRC-BSEP)
Mr. J. P. O'Reilly (NRC-RII) l Mr. J. A. Van Vliet (NRC) 8212100032 821206 p
PDR ADOCK 05000324 p
PDR 411 Fayettevitte Street
- P. O. Box 1551
- Raleigh, FL C. 27602
e CAROLINA POWER & LIGHT COMPANY REQUEST FOR INFORMATION EMERGENCY OPERATIONS FACILITY BRUNSWICK PLANT, UNITS 1 AND 2 1.
What is the date of CP&L's response to Generic Letter 81-10, dated February 18 19817 Response : CP&L's response is dated April 9, 1981.
2.
What is the primary EOF location?
Response
On-site What is the back-up EOF location?
Response: None planned. The primary EOF is designed to the same criteria as the Technical Sapport Center and will provide acceptable habitability for occupants.
3.
What is the interim primary EOF location?
Response: The interim primary EOF location is the Training Building.
The interim back-up EOF is the Bolivia County Offices which is approximately 12 miles from the plant site.
4.
Will the primary EOF have HEPA filters?
Response
Ye s 5.
What is the primary EOF strincture?
Response: Concrete 6.
What are the Protection Factors for the primary EOF 7 Response: Approximately 50 (estimated from Figure 4.4-3 from the Brunswick Emergency Plan, October, 1981) l 7.
What is the start date of construction of the primary EOF 7 Response: Grading work began on July 19 1982.
Building construction began on October 4, 1982.
8.
What is the percentage of completion for the primary EOF 7 Response: The building is 15% complete.