4

_EY Log # TXX 91004 C

.=

Fi1e # 10035 Z

C-909.2 TI1 ELECTRIC Ref. -# GL 89 13 Wilham J. Cahill Jr.

Esewave ike hesident i

U. S. Nuclear Regulatory Commission Attn: Document Control Desk 7

. Washington, D C.

20555

SUBJECT:

.C0HANCHE PEAK STEAM ELECTRIC: STATION (CPSES):

DOCKET NO. 50 445 AND 50-446 NRC GENERIC LETTER 89 13-SERVICE WATER PROBLENS AFFECTING SAFETY RELATED EQUIPHENT-REF: _1) TV Electric letter TXX-90031 -from W.' J.~ Cahill, Jr. to USNRCl dated January 26, 1990.

2) TU Electric letter TXX-90186 from W.. J. Cahill, Jr. to USNRC dated May 21, 1990.
3) TU Electric' letter TXX 90347 from W.:J. Cahill, Jr. to USNRC dated September 21 -1990.

Gentlemen:

TU Electric, via reference 1 and 2, responded -to NRC Generic Letter (GL) 89-13

" Service Water Sys'.em Problems Affecting Safety Related Equipment." Reference 3 provided.the sctelule for baseline data collection-for designated Service-Water System examination sites.

On. December 31,.1990,1TVlElectr.ic-orally' notified the NRC of a change _to the schedule provided-in Reference 3; In response to GL.89 13. Recommended Action III. TU. Electric informed the NRC that-the " Corrosion Honitoring Program, Service Water Section" had-been developed to provide a means by which samples of= Service Water-System piping wall thickness would be per_lodically measured and trended.

Reference (2) notified the NRC-that TU. Electric had. completed implementation of the requirements of GL 89-13 for Unit 1.

CPSES Unit 1 baseline data collection:for_the designated Service _ Water System examinatioti sites-is expected to be completed-during the Unit 1 mid-cycle outage. This outage is presently scheduled for April,.1991, q

PDR ADOCK 0500045S, j-p PDR

(( fj h.

400 North Olive Street LD. 81 -- Dallas, Texas 75201

4 TXX 91004 Page 2 of 2 Implementation of the Corrosion Honitoring Program, including the collection of baseline data for Unit 2 remains unchanged.

Sincerely, William J. Cahill, Jr.

By:

D. R. Woodlan Docket Licensing Hanager JDS/gj c - Mr. R. D. Hartin, Region IV Resident Inspectors, CPSES (3)

Mr. J. W. Clifford, NRR I