- CENTEnson ENERGY PERRY NUCLEAR POWER PLANT Mad Address:
. Robert A.Stratman 0
~
~
10 CENTER ROAD RR O 10 44081 PERRY, OHIO 44081 (216) 259 3737 April 15, 1994 PY.-CEI/NRR-1787L U. S. Nuclear Regulatory Commission i
Document Control Desk Vashington, D.C.
20555 Perry Nuclear Power Plant Docket No. 50-440 Honthly Operating '.spo r t Gentlemen Attached is the March 1994 Honthly Operating Report for Perry Unit 1.
This report is submitted in accordance with Technical Specification 6.9.1.8.
If you have questions or require additional information, please contact Henry Hegrat-Regulatory Affairs at (216) 280-5606.
Ver u r_ul yours, i <t RASILKR sc Attachment cc
.NRC Project Manager NRC Resident Inspector Office NRC Region III Director, Office of Resource Management 940419oo72 946331 PDR ADOCK 05000440 R
PDR Operahng Compon.cs 1
Cleveland Electrte muminohng
/
l I
' 70iedo Edison
)
i
.\\
.o i
CLEVELAND ELECTRIC ILLUMINATING COMPANY PERRY NUCLEAR POWER PLANT -
March 1, 1994 - March 31, 1994 MONTilLY OPERATING REPORT TO NRC DOCKET NUMBER : 50-440 LICENSE NUMBER: NPP-58
i.t p.g I
- +
-a
.. g -.-
i
.i t
Table of Contents Average Daily Unit Power Level.................... l' 2-Operating Data Report 3
Unit Shutdowns and Power Reductions.
h t
d 1
I 4
V
--4 4
s y
-r 4un--
r v
=
o-1 Average Daily Unit Power Level DOCKET NO.
50-440 UNIT Perry-1 DATE 04/15/94 Contact L.K. Routzahn Telephone (216)280-5781 MONTH Harch 1994 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POVER LEVEL (MVe-Net)
(MWe-Net) 1 0
17 0
2 0
18 0
3 0
19 0
4 0
20 0
5 0
21 0
6 0
22 0
7 0
23 0
8 0-24 0
9 0
25 0
10 s'
26 0
11 0'
27 0
12 0
28 0
0 13 0
29 0
14 0
30 15 0
31 0
16 0
t 8
e E-
Operating Data Report UNIT:
Perry-1 DATE:
04/15/94 OPERATING STATUS 1.
Docket:
50-440 2.
Reporting Period:
March 1994 3.
Utility
Contact:
H. L. Hegrat 4.
Licensed Thermal Power (MVt):
3579 5.
Nameplate Rating (Gross MVe):
1250 6.
Design Electrical Rating (Net HWe):
1191 7.
Maximum Dependable Capacity (Gross MVe):
1225 8.
Maximum D(pendable Capacity (Net MVe):
1166 9.
If changes occur in capacity ratings (Item Numbers 4 through 8) since
+
last report, give reasons:
None
- 10. Power Level To Which Restricted, If Any (Net MVe):
100%
- 11. Reasons for Restrictions, If Any:
OPERATING LICENSE This Month Yr-to-Date Cumulative
- 12. Hours In Reporting Period 744 2,160.0 55,812.0
- 13. Hours Reactor Was Critical 0
805.5 38,336.8 0
0.0 0.0
- 14. Reactor Reserve Shutdown Hours _ _ _
0 785.3 36,920.9
- 15. Hours Generator On-Line
- 16. Unit Reserve Shutdown Hours 0
0.0 0.0
- 17. Gross Thermal Energy (HVH) 0 2,705,376
.125,586,136
- 18. Gross Electrical Energy (MVH) 0 939,406 43,164,398
_19. Net Electrical Energy (HVH) 0 887,676 40,980,605
- 20. Unit Service Factor 0
36.4%
66.2%
- 21. Unit Availability Factor 0
36.4%
66.2%
- 22. Unit Capacity Factor (Using HDC Net) 0 35.2%
63.6%
- 23. Unit Capacity Factor (Using DER Net) 0 34.5%
61.7%
- 24. Unit Forced Outage Rate 0.0%
6.7%
12.3%
- 25. Forced Outage Hours 0
56.2 5,195.0
- 26. Shutdowns Scheduled Over Next 6 Henths (Type, Date and Duration of Each):
FEBRUARY 5, 1994, Refuel Outage #4.,
Duration of the outage is 117 days.
- 27. If Shut Down at end of Report Period, Estimated Date of Startup:
06/02/94 i
CODED /8144 J
i
.I
UNIT SHUTDOWN AND POWER REDUCTIONS' DOCKET.NO. 50-440 7.
UNIT NAME Perry -1
~~ '
REPORT MONTH March 1994 DATE 03/15/94 CONTACT L. Routzahn' i
TELEPHONE (216) 280-5781. "
7
?
ce dLicensee E
c N
'i No-Date c
'o 'a Event u o ot Action to e
a u o
ed C
Report "u
Prevent Recurrence j
c.
es a:
.= u g
y yo uj gy gj.
e ov e
rmax u
94-03 02/05/94 S
744.0 C
4 Refuel Outage #4
-?
t i
s
SUMMARY
- On 02/05/94 the unit shutdown to commence refueling. outage #4.
'F:
Forced keason:
Method:
' Exhibit G-Instructions for
'S:
Scheduled-A-Equipment Failure'(Explain)
.pManual Preparation of Data Entry j
B-Maintenance or Test 2-Manual Scram Sheets-for Licensee Event
-C-Refueling 3-Automatic Scram Report (LER) File OWREGIO22)'
D-Regulatory Restriction 4-Continued 5 Exhibit 1-Same Source E-Operator Training &-
.5-Reduced Load-
. License Examination 9-Other F-Administrative l
.G-Operational Error (Explain)
.H-Otherj(Explain) z-
..=.
~-
-