Responds to 781006 NRC Ltr Re Violation Noted in Inspec Rept 50-219/78-24.Corrective Actions:Replaced Prints W/Latest Rev in Document Center.Compliance Achieved 780922
ML20064F569
Person / Time
Site: Oyster Creek
Issue date: 10/30/1978
From: Ross D
JERSEY CENTRAL POWER & LIGHT CO.
To: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML20064F565 List:
References
NUDOCS 7812010131
Download: ML20064F569 (2)


Text

-

Jemey Central Power & Ught Compani

~a

.i L h~

f Madison Avenue at Punch Bowt Road Mornstown. New Jersey 07960 (201)455-8200 October 30, 1978 Mr. Eldon J. Brunner, Chief Reactor Operations and Nuclear Support Branch United States Nuclear Regulatory Commission Region 1 631 Park Avenue King of Prussia, Pennsylvania 19406

Dear Mr. Brunner:

Subject:

Oyster Creek Nuclear Generating Station Docket No. 50-219 l&E inspection Report No. 50-219/78-24 This is in reply to your letter dated October 6, 1978 to Mr. Ivan R. Finfrock, Jr.

regarding the inspection conducted by Mr. J. Higgins on September 19 through September 21, 1978 at the Oyster Creek Nuclear Generating Station.

In Appendix A to your letter, there is noted one activity that was not conducted in full compliance with NRC requirements.

The specific infraction identified and our response to it are given below:

Infraction: The set of drawings used in the Control Room for operation of systems on the QASL was not control!ed and was not up-to-date as of September 20, 1978.

t

Response

1.

The immediate corrective action was to remove unnecessary prints from the Control Room print book, review the remaining prints for the latest revision, and replace all superceded prints with the latest revision in the Document Center. All prints in the Control Room print book have been verified to be the latest revision available.

2.

The permanent corrective action will be to place controlled copies of the drawing index and microfilmed drawing #ile in the Control Room and remove the print book. The operators will then have access to the latest prints and will have the means to verify the most recent revision of a print is being used, as required by Section 5.6 of Quality Assurance Procedure 2009,

" Control and Olstribution of As-Built Drawings".

Both items have been requested and are in preparation. As a temporary measure, until drawing control is established in the Control 781201om

..__.. ~

..-,m_.._.

,, _. ~ _ _..... _. _.. m _,o. - _..., _ c.

s Mr. Brunner October 30, 1978 Room with the controlled index and drawing file, the Train-Ing Coordinator will verify each print in the Control Room print book is the latest revision upon receipt of each change to the drawing index.

3 Full compliance was achieved on September 22, 1978.

Very truly yours, j

/

W Donald A. Ross, Manager Generating Stations-Nuclear f