{{#Wiki_filter:* COEEECTED COPY i i D. Of7J ATING DATA _REf0RT DOCKET NO.* 050-455 l UNIT: Byron Two DATE: 07/09/90 COMPILED BY: K. Orris TELEPHONE: (815)234-5441 y x2444 OPERATING STA*IUS 1. Reporting Period: June, 1990. Gross llours: 720 2. Currently Authorized Power Level 3411 (MWt) Design Electrical Rating: 1175 (MWe-gross) Design Electrical Rating: 1120 (MWe-net) Max Dependable Capacity: 1105 (MWe-net) I 3. Power Level to Which Restricted (If Any): N/A 4. Reasons for Restriction (If Any): i THIS MONTH YR TO DATE CUMULATIVE
- 5.
Report Period Hrs. 720 4,343 25,080 6. Rx Critical Hours 720 4,276 22,341 7. Ru Reserve Shutdown Hours 0 0 0 8. Ilours Generator on Line 720 4,268 21,953 9. Unit Reserve Shutdown flours 0 0 0
- 10. Gross Thermal Energy (MWH) 2,075,512 13,394,131 58,961,740
- 11. Gross Elec. Energy (MWH) 714,035 4,609,749 19,954,b49
- 12. Het Elec. Energy (MWH) 674,032 4,373,978 18,764,114
- 13. Reactor Service Factor 100 98.4 89.1
- 14. Reactor Availability Factor 100 98.4 89.1
- 15. Unit Service Factor 100 98.2
.87.5
- 16. Unit Availability Factor 100 98.2 87.5
- 17. Unit Capacity Factor (MDC net) 84.7 91.1 67.7
- 18. Unit Capacity Factor (DER net) 83.6 89.9 66.8
- 19. Unit Forced Outage Hrs.
0 26 845
- 20. Unit Forced Outage. Rate 0
0.6 3.3
- 21. Shutdowns Scheduled Over Next 6 Months:
1 - September
- 22. If Shutdown at End of Report Period, Estimated Date of Startup: N/A
- 23. Units in Test Status (Prior to Commercial Operation): None
- Note - The cumulative numbers do not reflect power generated prior to commercial se.vice.
(0625M/0062M/9) 9008170269 900810 POR ADOCK 05000454 =R PDC}}