Interim Part 21 Rept Re Missing Records from NSSS Support Steel Document Packages,Initially Reported 820125.Review of Affected Weld Seams Continuing.Next Rept Will Be Submitted by 821119
ML20063E165
Person / Time
Site: Marble Hill
Issue date: 07/02/1982
From: Shields S
PSI ENERGY, INC. A/K/A PUBLIC SERVICE CO. OF INDIANA
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
REF-PT21-82-673-000 10CFR-50.55E, PT21-82-673, PT21-82-673-000, S82-01, S82-1, SVP-0011-82, SVP-11-82, NUDOCS 8207130322
Download: ML20063E165 (2)


Text

- - _ - _____ _ _ _ _ _ _

l

_ d' PUBLIC SERVICE INDIANA July 2, 1982 S82-01 S. W. Shiehls SVP-0011-82 Senior Vice President Nuclear Division Mr. James G. Keppler, Docket Nos.: STN 50-546 Regional Administrator STN 50-547 U.S. Nuclear Regulatory Commission Construction Permit Nos.:

Region III CPPR - 170 799 Roosevelt Road CPPR - 171 Glen Ellyn, Illinois 60137 Marble Hill Nuclear Generating Station - Units 1 and 2

Dear Mr. Keppier:

On January 25, 1982, Mr. T. D. Geib of Public Service Company of Indiana Inc. (PSI) notified your office of a potentially reportable item as required by 10 CFR 50.55(e). Review of the Nuclear Steam Supply System (NSSS) support steel document packages supplied by Lakeside Bridge &

Steel Co. revealed that records were missing from several packages and the quality of the affected supports was therefore indeterminate.

PSI conducted a review of NSSS support steel document packages and retrieved many of the missing records from files at Lakeside Bridge and Steel's Shop. Review of certain retrieved radiographic records has necessitated the weld repair of some of the support steel delivered to the site. PSI's review also identified 307 weld seams for which documentation of required Nondestructive Examination (NDE) was not retrievable. Of these weld seams 244 have been examined at the site and accepted. PSI will address the remaining 63 weld seams once difficulties with accessibility are resolved.

This letter is intended to fulfill the requirements of an interim report as defined in 10 CFR 50.55(e). A further report will be filed on or before November 19, 1982.

I B207130322 820702 PDR ADOCK 05000546 S PDR g gg P, O. Box 190, New Washington, Indiana 47162 812. 289.3000 ,

4 SERVICE j inmasa Letter: J. July 2, 1982 l

S82-01 SVP-0011-82 If you have any questions on this report, please feel free to contact me.

Sincerely,

. W. Shields SWS/TDG/bak cc: Director of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 J. E. Konklin J. J. Harrison