Interim Deficiency Rept DER 82-38 Re Henry Pratt 8-inch Containment Isolation Valves W/Loose Actuator Bolts & W/O Specified Torque.Initially Reported on 820713.Vendor to Review & Evaluate Deficiency.Final Rept Due on 821105
ML20063A099
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 08/11/1982
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
10CFR-050.55E, 10CFR-50.55E, ANPP-21604-GHD, DER-82-38, NUDOCS 8208240192
Download: ML20063A099 (3)


Text

_

d.,

Docket Nos. 50-528/529/530 50.55 (e) Report 2; @e iso p n

IPrAMEUD 6&affFRDLui @@3hTPN,,

M;3227Bi1A y

//

, /

f.

PHOENIX, ARIZON A 85036 P. O. B O x 216 6 6 August 11, 19P2 M.,,,'

ANPP-21604-G',' 'BSK '

U. S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 Attention:

Mr. T. W. Bishop, Chief Reactor Construction Projects Branch

Subject:

Interim Report - DER 82-38 A 50.55(e) Potentially Reportable Deficiency Relating to llenry Pratt 8" Containment Isolation Valves For Unit 3 Were Received With Actuator Bolts Loose, No Torque Specified File: 82-019-026 D.4.33.2

Reference:

Telephone Conversation between T. Bishop and G. Duckworth on July 13, 1982 1

l

Dear Sir:

The NRC was notified of a potentially reportable deficiency in the referenced telephone conversation. At that time, it was estimated that a determination of reportability would be made within thirty (30) days.

Due to the extensive investigation and evaluation required, an Interim Report is attached.

It is now expected that this information will be finalized by November 5,1982, at which time a complete report will be submitted.

Very truly yours, Lh MM E. E. Van Brunt, Jr.

APS Vice President Nuclear Projects ANPP Project Director EEVBJr/ Gild:db Attachment CC:

See Attached Page 2 820 8 24 0 IRQ )

U. S. Nuclear Regulatory Commission August 11, 1982 Attention:

Mr. T. W. Bishop, Chief ANPP-21604-Gild /BSK Page 2 cc: Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 T. G. Woods, Jr.

J. A. Roedel D. B.

insnacht G. C. Andognini A. C. Rogers B. S. Kaplan W. E. Ide J. Vorces J. A. Brand A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patter, son R. W. Welcher R. M. Grant D. R. Hawkinson L.

E. Vorderbrueggen G. A. Fiorelli Lynne Bernabei, Esq.

Harmon & Weiss 1725 "1" Street, NW Suite 506 Washington, D. C. 20006 R. L. Greenfield Assistant Attorney General Bataan Memorial Building Santa Fe, New Mexico 87503

INTERLM REPORT - DER 82-38 POTENTIAL REPORTABLE DEFICIENCY ARIZONA PUBLIC SERVICE COMPANY (APS)

PVNGS UNIT 3 I.

POTENTIAL PROBLEM Four (4) 8" butterfly valves supplied by llenry Pratt were received at the jobsite with loose bolts holding the actuator to the gear box.

During receiving inspection, one bolt from each of two valves was 4

found completely detached and lying on the shipping pallet (s).

Contact with the vendor disclosed that no_ torque values have been established for the four (4) hex head bolts securing the SMB to IIBC unit.

The valves are the containment purge system isolation valves.

II.

APPROACll TO AND STATUS OF PROPOSED RESOLUTION This deficiency report is being transmitted to the vendor for review and evaluation.

This condition will not preclude the valves from being installed.

III.

PROJECTED COMPLETION OF CORRECTIVE ACTION AND SUBMITTAL OF Tile FINAL REPORT Evaluation of this condition and submittal of the Final Report is forecast to be completed by November 5, 1982.

,