Rev 1 to Monthly Operating Rept for Sept 1993 for Comanche Peak Steam Electric Station Unit 2
ML20062N836
Person / Time
Site: Comanche Peak  
Issue date: 09/30/1993
From: Julie Hughes
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
Shared Package
ML20062N829 List:
References
NUDOCS 9401240112
Download: ML20062N836 (2)


Text

__

j

kttachment to TXX-94003 Page 10 of 13 i

COMANCHE PEAK STEAM ELECTRIC STATION, UNIT 2 NRC MONTHLY OPERATING REPORT REVISION 1 DOCKET NO -

50-446 UNIT CPSES 2 j

t DATE 01/14/1994 i

COMPILED BY Janet Hughes j

TELEPHONE.

817-897-5331 l

OPERATING STATUS 1.

REPORTING PERIOD: SEPTEMBER 1993 GROSS HOURS IN REPORTING PERIOD: 720 I

2.

CURRENTLY AUTHORIZED POWER LEVEL (MWt): 3411 MAX DEPEND. CAPACITY (MWe-Net): 1150' i

DESIGN ELECTRICAL RATING (MWe-Net): 1150 j

f 3.

POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): NONE 4.

REASON FOR RESTRICTION (IF ANY):

THIS MONTH YR TO DATE CUMULATIVE l

I S.

NUMBER OF HOURS REACTOR WAS CRITICAL 430 1,117 1,117 6.

REACTOR RESERVE SHUTDOWN HOURS 290 290 290 i

7.

HOURS GENERATOR ON LINE 406 1.093 1,093 3

8.

UNIT RESERVE SHUTDOWN HOURS 0

0 0-9.

GROSS THERMAL ENERGY GENERATED (MWH) 1,317.156 3,644,602 3,644,602

10. GROSS ELECTRICAL ENERGY GENERATED (MWH) 441,350.

1,223,967 1,223,967 11.

NET ELECTR! CAL ENERGY GENERATED (MWH) 417,205 1,168,939 1,168,939-12.

REACTOR RESERVE FACTOR 59.8 79.4 79.4 f

13. REACTOR AVAILABILITY FACTOR 100.0 100.0 100.0 14.

UNIT SERVICE FACTOR 56.4 77.8 77.8 15.

UNIT AVAILABILITY FACTOR 56.4 77.8 77.8 i

16. UNIT CAPACITY FACTOR (USING MDC) 50.4 72.3 72.3 i

17.

UNIT CAPACITY FACTOR (USING DESIGN MWe) 50.4 72.3 72.3

18. UNIT FORCED OUTAGE RATE 0.0 0.0 0.0 19.

SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):

20. IF SHUTDOWN AT END OF REPORTING PERIOD, ESTIMATED DATE OF STARTUP:
21. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

FORECAST ACHIEVED '

i INITIAL CRITICALITY 930320 930324 l

INITIAL ELECTRICITY 930330 930409' COMMERCIAL OPERATION 930801 930803 i

ESTIMATE I

i i

9401240112 940114 PDR ADOCK 05000445 R_

PDR m

Attachment to TXX-94003 Page 11 of 13 UNIT SHUTDOWNS AND POWER REDUCTIONS PEVISION 1 DOCKET NO 50-446 UNIT CPSES 2 DATE 01/14/1994 COMPILED BY Janet Hughes TELEPHONE 817 897-5331 REPORT MONTH: SEPTEMBER 1993 METHOD OF TYPE SHUTTING DOWN F: FORCED DURATION THE REACTOR OR NO DATE S: SCHEDULED (HOURS)

REASON REDUCING POWER CORRECTIVE ACTIONS / COMMENTS 15 930917 S

313E8 8

1 Repaired valve leaks (steam generator 2-03 l

feedwater split flow bypass valve in containmera and feedwater full flow recirculation valve in the turbine building).

t i

1) REASON 21 METHOD A: EQUIPMENT FAILURE (EXPLAIN)

E: OPERATOR TRAINING AND UCENSE EXAMINATION 1: MANUAL B;MAINT OR TEST F: ADMINISTRATIVE 2: MANUAL SCRAM C: REFUELING G: OPERATIONAL ERROR (EXPLAIN) 3: AUTOMATIC SCRAM D. REGULATORY RESTRICTION H:OTHER(EXPLAIN) 4:OTHER(EXPLAIN)

-.. - ~..

. - - -.