Rev 1 to Monthly Operating Rept for Sept 1993 for Comanche Peak Steam Electric Station Unit 2
ML20062N836
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 09/30/1993
From: Julie Hughes
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
Shared Package
ML20062N829 List:
References
NUDOCS 9401240112
Download: ML20062N836 (2)


Text

__

.l j

kttachment to TXX-94003  !

Page 10 of 13 i COMANCHE PEAK STEAM ELECTRIC STATION, UNIT 2 NRC MONTHLY OPERATING REPORT  ;

REVISION 1  ;

DOCKET NO - 50-446 ,

UNIT CPSES 2 j t

DATE 01/14/1994 i COMPILED BY Janet Hughes j TELEPHONE . 817-897-5331 l OPERATING STATUS

1. REPORTING PERIOD: SEPTEMBER 1993 GROSS HOURS IN REPORTING PERIOD: 720  !

I

2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 3411 MAX DEPEND. CAPACITY (MWe-Net): 1150' i DESIGN ELECTRICAL RATING (MWe-Net): 1150 ,

j

3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): NONE f
4. REASON FOR RESTRICTION (IF ANY): .

THIS MONTH YR TO DATE CUMULATIVE l S. NUMBER OF HOURS REACTOR WAS CRITICAL 430 1,117 1,117 I

6. REACTOR RESERVE SHUTDOWN HOURS 290 290 290  ;

i

7. HOURS GENERATOR ON LINE 406 1.093 1,093 3
8. UNIT RESERVE SHUTDOWN HOURS 0 0 0- ,
9. GROSS THERMAL ENERGY GENERATED (MWH) 1,317.156 3,644,602 3,644,602
10. GROSS ELECTRICAL ENERGY GENERATED (MWH) 441,350. 1,223,967 1,223,967
11. NET ELECTR! CAL ENERGY GENERATED (MWH) 417,205 1,168,939 1,168,939-
12. REACTOR RESERVE FACTOR 59.8 79.4 79.4
13. REACTOR AVAILABILITY FACTOR 100.0 100.0 100.0 f
14. UNIT SERVICE FACTOR 56.4 77.8 77.8
15. UNIT AVAILABILITY FACTOR 56.4 77.8 77.8 .

i

16. UNIT CAPACITY FACTOR (USING MDC) 50.4 72.3 72.3 i
17. UNIT CAPACITY FACTOR (USING DESIGN MWe) 50.4 72.3 72.3 '
18. UNIT FORCED OUTAGE RATE 0.0 0.0 0.0
19. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH): ,
20. IF SHUTDOWN AT END OF REPORTING PERIOD, ESTIMATED DATE OF STARTUP: .
21. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): FORECAST ACHIEVED ' i INITIAL CRITICALITY 930320 930324  !

l INITIAL ELECTRICITY 930330 930409' ,

COMMERCIAL OPERATION 930801 930803 i ESTIMATE I i

i 9401240112 940114 ,

PDR ADOCK 05000445 >

R_ PDR m ,

Attachment to TXX-94003 ,

Page 11 of 13 UNIT SHUTDOWNS AND POWER REDUCTIONS ,

PEVISION 1 DOCKET NO 50-446 UNIT CPSES 2 .

DATE 01/14/1994 COMPILED BY Janet Hughes TELEPHONE 817 897-5331 REPORT MONTH: SEPTEMBER 1993 METHOD OF TYPE SHUTTING DOWN F: FORCED DURATION THE REACTOR OR NO DATE S: SCHEDULED (HOURS) REASON REDUCING POWER CORRECTIVE ACTIONS / COMMENTS 15 930917 S 313E8 8 1 Repaired valve leaks (steam generator 2-03 feedwater split flow bypass valve in containmera l and feedwater full flow recirculation valve in the turbine building).

t i

1) REASON 21 METHOD A: EQUIPMENT FAILURE (EXPLAIN) E: OPERATOR TRAINING AND UCENSE EXAMINATION 1: MANUAL B;MAINT OR TEST F: ADMINISTRATIVE 2: MANUAL SCRAM C: REFUELING G: OPERATIONAL ERROR (EXPLAIN) 3: AUTOMATIC SCRAM D. REGULATORY RESTRICTION H:OTHER(EXPLAIN) 4:OTHER(EXPLAIN)

__ .. . _ _ - _ . . . _ _ . _ - _ _ _ - - _ . _ . , _ . . . - . . . - _ - . - _ _ . - _-- ... ., _ _ _ . - _ . _ - - - - - -, - _ . . _ . . _-- . . _ - . . - ~ . . _ . - - _ . - - - .