Emphasizes Importance of Submitting Accurate & Complete Info to NRC by Licensee & Applicants.Info Submitted Must Be Substantiated by Data & Calculations.Licensee Must Notify NRC of Any Inaccuracies or Enforcement Action Will Result
ML20062G400
Person / Time
Site: Millstone, Hatch, Vogtle, 05000426, 05000427  Southern Nuclear icon.png
Issue date: 12/06/1978
From: Jennifer Davis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To: Scherer R
GEORGIA POWER CO.
References
NUDOCS 7812280170
Download: ML20062G400 (2)


Text

"

P

" y M it a0,$)/

'o UNITED STATES

~

8"'

NUCLEAR REGULATORY COMMISslON MPDG

[**b' g

f W ASHINGTON, D. C. 20555 DEC 6 57B DocketNo(s).:

50-321/336/424/425/

426 and 427 Georgia Power Company ATTN: Mr. R. W. Scherer, President P. O. Box 4545 i

l Atlanta, Georgia 30302 Gentlemen:

{-

The purpose of this letter is to direct your attention to our continuing concern for the accuracy and completeness of information submitted to the NRC by licensees and applicants.

Our statutory responsibilities require that infomation received as part of the regulatory process be accurate and complete.

This includes infomation provided in license applications, responses to licensing questions, enforcement letter responses, event reports, and IE Bulletin responses.

As you know,10 CFR 50.30 requires that an application for a license, or amendment thereto, be provided under oath or affimation.

While other infomation is not required to be provided under oath or affirmation, this in no way detracts from the necessity that all information submitted to the NRC be accurate.

The information submitted should be substan-tiated by data, records, calculations and sound technical judgment. The required promptness of reply may, under certain circumstances, contribute to an inadvertent submittal of incomplete or inaccurate information.

(

Under such circumstances, we expect your prompt detection and imediate L

NRC notification of any inaccuracies and incompleteness in the informa-tion supplied to the NRC.

You are no doubt aware that failure to meet the expected standards of accuracy and completeness has resulted in enforcement action.

Enforce-ment action will continue to be considered for inaccurate or incomplete infomation amounting to material false statements. Such action is necessary, as inaccurate or incomplete infomation'could lead to deci-sions which adversely affect the health and safety of the public.

781228onO 5 & /or f

%l%7g

It is imperative that licensees and applicants meet their responsibility of positively assuring the accuracy and completeness of all infortnation provided to the NRC.

It is expected that each licensee and applicant will have an active program to assure an awareness at all levels in their organization that nothing less than complete and accurate information is acceptable.

{

l Sincerely, A

J Harold R. Denton g

hn G. Davis Director Acting Director Office of Nuclear Office of Inspection p