Responds to NRC 820322 & 0702 Ltrs Re Violations Noted in IE Insp Rept 50-285/82-02.Corrective Actions:Requalification Exams Will Commence in Fall 1982 Using Randomly Selected Questions from Training Dept Bank
ML20062D771
Person / Time
Site: Fort Calhoun 
Issue date: 07/15/1982
From: William Jones
OMAHA PUBLIC POWER DISTRICT
To: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML20062D768 List:
References
LIC-82-257, NUDOCS 8208060216
Download: ML20062D771 (1)


Text

O Omaha Public Power District 1623 HARNEY E OMAHA. NESRASMA 68102 e TELEPHONE 536 4000 ARE A CODE 402 July 15, 1982 LIC-82-257 Mr. W. C. Seidle, Chief Reactor Project Branch 2

~ i U. S. Nuclear Regulatory Commission uh Region IV

$ @ $b1[O '., [1 bl

~

lin ton xa g gg g k

Reference:

Docket No. 50-285 L

IE Inspection Report 82-02

Dear Mr. Seidle:

Resolution to the Potential for Compromise of Operator Requalification Examinations Issue The Commission's letters dated March 22 and July 2, 1982 asked Omaha Public Power District to respond to Open Item 8102-05 of the referenced Inspection Report regarding District actions to prevent potential compromise of Fort Calhoun Station operator requalification examinations. The District's response and actions regarding this item are detailed below.

Cormlencing with the fall 1982 requalification examinations, the District will utilize a bank of questions for each of the five sections to the Reactor Operetor (RO) and Senior Reactor Operator (SRO) exami-nations. The District's Training Department will randomly select questions from this bank to comprise a full five section examination for each examinee. This method will provide for individualized examinations, with no single candidate knowing all potential questions within each section. The District will also maintain the bank of examination questions and completed examinations in a locked, fire-proof cabinet and will administer the annual requalification examinations during a six week time frame, instead of the previous extended examination periods.

The District believes these actions are sufficient to preclude the com-promise of R0/SRO requalification examinations.

Sincerely, R208060216 820802 IJ f.$' ([

I PDR ADDCK 05000 W.C.ynes

[

0 Divisio Manager Production Operations I

cc: LeBoeuf, Lamb, Leiby & MacRae 1333 New Hampshire Avenue, N.W.

l Washington, D.C.