ML20062B334

From kanterella
Jump to navigation Jump to search
Summary of 781016 Meeting Re Util Evaluation of Reactor Recirculation safe-end Exam Results.Util Will Notify Region II Whether Nov Insp Can Be Deferred
ML20062B334
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 10/20/1978
From: Blake J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20062B333 List:
References
NUDOCS 7810270272
Download: ML20062B334 (2)


Text

.

UNITED STATES

  1. 8"84 o, NUCLEAR REGULATORY COMMISSION

,( ,

REGloN 11

{

.c g T

101 M ARIETT A STRE ET. N.W.

ATLANTA. GEORGI A 30303 o, [

%, *... /

License Nos.: DPR-62 and DPR-71 Docket Nos.: 50-324 and 50-325 Licensee: Carolina Power and Light Company 336 Fayetteville Street Raleigh, North Carolina 27502 1 and 2 Facility: Brunswick Stea= Electric Plant

Subject:

BSEP Reactor Recirculation Safe-End Examination Results 16, 1978 Summary of Meeting with CP&L on October On October 16, 1978, representatives of Carolina Power and Light Company met with NRC Region II and Headquarters personnel in Atlanta, Georgia to discuss CP&L's Evaluation The primaryofobjective the BSEP of theReactor Recirculation meeting was to deter- Safe-En Examination Results. 1 mine if additional volumetric nondestructive examinations of the Unit "D" jet pump riser safe-end should be done during or before the period of Novembe.1 22-26, 1978, or if the additional examinations could be The deferred uittil the next scheduled refueling outage in March,1979.

attendance list is attached as Appendix A to this susanary,

1. General Discussion a.

CP&L made an oral presentation of their inspection results and rationale for def erring additional inspections until the refueling outage.

b.

Af ter the completion of the presentation a question and answer session was held to explore the bases for the assus9tions which were presented to support the argument to defer the inspections.

c. The ultrasonic examination data were reviewed by NRC personnel and NRR consultants.

1$/6270 :92)

i

2. Results
a. NRC informed the licensee that there was a question that remained unanswered froo the discussion and that had to do -

with the change of location of the maximum primary and secondary stressed between the Duane Arnold and Brunswick designs. CP&L i

agreed to research this specific question.

b. Based on the discussions, CP&L management will inform Region II of their position as to whether or not the November inspections can be deferred.

J. J. Blake Metallurgical Engineer

Enclosure:

Appendix A cc: N. Moseley, Director, HQ C. Murphy, Chief, Construction Branch, RII F. Long, Chief , Operations Branch, RII R. Beishman, Chief, Construction Branch, RIII A. Herdt, Chief, Projects Section, RC&ESB, RII D. Danielson, Chief, Engineering Support Section No. 2, RC&ESB, RIII l T. Conlon, Chief, Engineering Support Section No. 2, RC&ESB, RII J. Collins, Chief. Effluent Treatment Systems Branch, HQ J. Blake, Metallurgical Engineer, ESS#2, RC&ESB, RII B. Riley, Reactor Inspector, RONSB, RII V. Noonan, Chief Enginser, DDR 1

( ,.

i s

r i

i l

l

l l

l

. i APPENDIX A Attendance at the CP&L-NRC meeting on October 16, 1978, at the NRC i Region II Office.  :

1. Licensee Representatives t

A. Carolina Power and Light Co.

H. R. Banks, Manager Nuclear Generation S. P. Grant, Principal Engineer, Technical Services W. M. Tucker, Superintendent, Technical and Administrative, BSEP N. J. Chiangi, Manager Engineering and Construction QA C. R. Osman, QA Specialist, Level III UI E. L. Betz, QA Specialist, Level III RT A. Bishop, Plant Engineer, BSEP B. CP&L Consultants S. A. Wank, Southwest Research Institute T. G. Lambert, Technical Manager, Ufr Inc.

C. General Electric H. T. Watanabe, Principal Licensing Engineer D. W. Diefenderfer, Manager, BWR Product Service A. R. McIlree, Senior Engineer

2. NRC Reoresentatives ,

A. Region II I J. P. O'Reilly, Director, Region II F. J. Long, Chief, Operations Branch, RII A. R. Hardt, Chief, Projects Section, ECESB, RII T. E. Conlon, Chief. Engineering Support Section No. 2, RCESB, RII N. Economos, Metallurgical Engineer, ESSi2, RCESB, RII P. K. VanDoorn, Metallurgical Engineer, ESSi2, RCESB, RII J. J. Blake, Metallurgical Engineer, ESSi2, RCESB, RII L. Modenes, Reactor Inspector, RCESB, RII B. W. Riley, Reactor Inspector, RONSB, RII D. G. Hinckley, Reactor Inspector, RONSB, RII

3. Headquarters V. S. Noonan, Chief Engineer, DOR K. K. Klinot, NRR Consultant. ORNL J. H. Gieska, NRR Censultant, Sf41A

[