Forwards Insp Repts 50-373/93-23 & 50-374/93-23 & Notice of Violation.Violation of Concern Because Corrective Actions for Previous Problems W/Radiological Housekeeping & Radworker Performance Were Not Effective
ML20059K638
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 11/03/1993
From: Beverly Clayton
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Murphy W
COMMONWEALTH EDISON CO.
Shared Package
ML20059K642 List:
References
NUDOCS 9311160134
Download: ML20059K638 (3)


See also: IR 05000373/1993023

Text

, k--

NOV F 1993 \C b

Dh

Dw.2t No. 50-373

Docket No. 50-374

Commonwealth Edison Company

ATTN: Mr. Warren P. Murphy

LaSalle Site Vice President

LaSalle Nuclear Station

2605 North 21st Road

Marseilles, IL 61341

Dear Mr. Murphy:

This refers to the inspection conducted by D. Hills and C. Phillips of this

office, and by J. Roman of the Illinois Department of Nuclear Safety, on

August 27 through October 15, 1993. The inspection included a review of

authorized activities for your LaSalle County Station, Units 1 and 2,

facility. At the conclusion of the inspection, the findings were discussed

with those members of your staff identified in the enclosed report.

Areas examined during the inspection are identified in the report. Within

these areas, the inspection consisted of selective examinations'of procedures

and representative records, interviews with personnel,.and observation of

activities in progress.

During this inspection, certain of your activities appeared to be in violation

of NRC requirements, as specified in the enclosed Notice of Violation

(Notice). This item is of concern because your corrective actions for

previous problems with radiological housekeeping and' radworker performance

were not effective in preventing this violation. We noted your actions near

the end of the inspection period to provide immediate short term improvements.

However, it is important that your final corrective actions provide permanent

performance improvement in this area.

You are required to respond to this letter and should follow the instructions

specified in the enclosed Notice when preparing your response. In your

response, you should document the specific actions taken and any additional

actions you plan to prevent recurrence. After reviewing your response to this

Notice, including your proposed corrective actions and the results of future

inspections, the NRC will determine whether further NRC enforcement action is

necessary to ensure compliance with NRC regulatory requirements.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of

this letter, the enclosures, and your response to this letter will be placed

in the NRC Public Document Room.

'

3.5'143

9311160134 931103

[ 1

PDR ADDCK 05000373

O PDR

-- ___

.

..

NOV 3 1993

Commonwealth Edison Company 2

The responses directed by this letter and the accompanying Notice are not subject

to the clearance procedures of the Office of Management and Budget as required

by the Paperwork Reduction Act of 1980, PL 96-511.

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

we6pind SiRnm) b r n at Clayton"

Brent Clayton, Chief _

Reactor Projects Branch 1

Enclosures:

1. Notice of Violation

2. Inspection Reports

No. 50-373/93023(DRP);

No. 50-374/93023(DRP)

3. Attachment

cc w/ enclosure:

L._DelGeorge, Vice President, Nuclear

Oversight & Regulatory Services

J. Schmeltz, Acting Station Manager

J. Lockwood, Regulatory Assurance

Supervisor

D. Farrar, Nuclear Regulatory

Services Manager

DC/LFDCB

Resident Inspectors LaSalle

Dresden, Quad Cities

R. Hubbard

J. W. McCaffrey, Chief, Public

Utilities Division

Licensing Project Manager, NRR

R. Newmann, Office of Public

Counsel

State Liaison Officer

Chairman, Illinois Commerce

Commission

bec: PUBLIC (IE01)

See Previous Concurrences.'

RIII Rlll RIII RIII RIllg

McMurtray Hague Snell Hausman Clayton

_ - _ _ _ _ _ _ -

. . , , ,

-

-

...

,

.i

'

NOV. 3 1993

. Commonwealth Edison Company

'

2

.

The responses directed by this letter and the accompanying Notice are not

subject,to the clearance procedures of the Office of Management'and Budget'as ,

required by the Paperwork Reduction Act of 1980, PL 96-511.

We will gladly discuss any questions you have concerning this inspection.

Sincerely, I

H. Brent Clayton, Chief '

Reactor Projects Branch 1

i

Enclosures:  !

1. Notice of Violation ,

2. Inspection Reports .

'

No. 50-373/93023(DRP)-

No. 50-374/93023(DRP) l

3. Attachment

i

cc w/ enclosure: l

W. Murphy,. Site Vice President-  ;

J. Schmeltz, Acting Station Manager  !

J. Lockwood, Regulatory Assurance

Supervisor

D. Farrar, Nuclear Regulatory- 3

Services Manager  ;

OC/LFDCB '

Resident Inspectors LaSalle

Dresden, Quad Cities .

Richard Hubbard

J. W. McCaffrey, Chief, Public  :

Utilities Division i

Licensing Project Manager, NRR

Robert Newmann, Office of Public

Counsel

State Liaison Officer >

Chairman, Ill- lis Commerce

Commission  ;

bcc: PUBLIC (IE01)

i

<

RIII RIII RIII[C-

S RJlJ

L6 )U

VLA

McMurtray ague kgll

ne

Hausmgn

Clay ton

~,

!

to 49-43 +/jygry p/>f/s> phi 6 4

7f3

/

+

-. - .