Text
.
y
,
e
.-
_
.
.
.
JAN I i 1994
Docket No. 50-293 -
Mr. E. Thomas Boulette, PhD
Senior Vice President - Nuclear
Boston Edison Company
Pilgrim Nuclear Power Station
Rocky Hill Road
Plymouth, Massachusetts 02360
Dear Mr. Boulette:
SUBJECT: PILGRIM INSPECTION 93-20
This refers to the safety inspection conducted by Messrs. J. Macdonald, A. Cerne, and D. Kern,
of this office on November 2 to December 6,1993 at the Pilgrim Nuclear Power Station,
Plymouth, Massachusetts. Areas relevant to the health and safety of the public examined during
this inspection are described in the enclosed report. Our findings were based upon observations
of performance and independent evaluations of safety systems and quality records.
The
preliminary results were been discussed with Mr E. Kraft and other members of your staff at
the conclusion of the inspection.
This report includes a detailed inspection of the high pressure coolant injection and reactor core
isolation cooling systems, which found that the systems are well maintained. The Betterment
Program established by your staff following poor response by both systems during a September.
i
1990 feedwater system transient has been effective in resolving longstanding system deficiencies,
and in correcting risk-significant failure modes. System engineers were also found to be
knowledgeable in the design, operation, and status of the systems and were observed to actively
seek industry and vendor operating experience.
No reply to this report is necessary, and your cooperation with us is appreciated.
Sincerely,
. Original Signed By'
James C, Linville
'
James C. Linville, Chief
_
'
Projects Branch No. 3
Division of Reactor Projects
Enclosure: NRC Inspection Report No. 93-20
OFFICIAL RECORD COPY
O f
9401210 14 9
til
ADOCK 05000293
/
t
G
I %
.
.
.
. .
.
- -
-
-.
..
-
.
. - _ .
. _ .
.
. _. .. _-_-__
-
- .;
L'
JAN I I N.z
l-
Mr. E. Thomas Boulette, PhD
2
cc w/ encl:
E. Kraft, Vice President, Nuclear Operations and Station Director
L. Schmeling, Plant Department Manager
R. Fairbank, Manager, Regulatory Affairs and Emergency Planning Department
D. Tarantino, Nuclear Information Manager
G. Basilesco, Acting Compliance Division Manager
'
R. Hallisey, Department of Public Health, Commonwealth of Massachusetts
R. Adams, Department of Labor and Industries, Commonwealth of Massachusetts
The Honorable Edward M. Kennedy
The Honorable John F. Kerry
The Honorable Edward J. Markey
The Honorable Terese Murray
l
The Honorable Peter V. Forman
B. Abbanat, Department of Public Utilities
l
Chairman, Plymouth Board of Selectmen
l
Chairman, Duxbury Board of Selectmen
Plymouth Civil Defense Director
Paul W. Gromer, Massachusetts Secretary of Energy Resources
Sarah Woodhouse, Legislative Assistant
A. Nogee, MASSPIRG
l
Regional Administrator, FEMA
Office of the Commissioner, Massachusetts Department of Environmental Quality
Enginecting
Office of the Atemey General, Commonwealth of Massachusetts
T. Rapone, Massachusetts Executive Office of Public Safety
j
Chairman, Citizens Urgintt Responsible Energy
Public Document Room (PDR)
Local Public Document Rooro (LPDR)
Nuclear Safety Information Center (NSIC)
K. Abraham, PAO (2 copies)
NRC Resident inspector
1
Commonwealth of Massachusetts, SLO Designee
Paul Blanch
1
!
l
L
l
l
OFFICIAL RECORD COPY
,
!
e
.
--
-
-!
,
j
..
i
JAN 1 1 1994
- .
l
Mr. E. Thomas Boulette, PhD
3
bec w/ encl:
Region I Docket Room (with concurrences)
E. Kelly, DRP
J. Shedlosky, DRP
,
M. Oprendek, DRP
D. Vito, ORA (section 3.4)
l
'
bec w/enci (VIA FeMAIL):
W. Butler, NRR