ML20059D353

From kanterella
Jump to navigation Jump to search
Insp Rept 50-382/93-33 on 930914-1007.Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Evaluate Corrective Action,Operability & Reportability Determinations Re Containment Spray Valve
ML20059D353
Person / Time
Site: Waterford Entergy icon.png
Issue date: 10/26/1993
From: Stetka T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20059D331 List:
References
50-382-93-33, NUDOCS 9311020220
Download: ML20059D353 (13)


See also: IR 05000382/1993033

Text

..

..]

'

l

l

APPENDIX

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Inspection Report:

50-382/93-33

License:

NPF-38

Licensee:

Entergy Operations, Inc.

'

P.O. Box B

Killona, Louisiana

.

Facility Name:

Waterford Steam Electric Station, Unit 3

Inspection At:

Killona, Louisiana

Inspection Conducted: September 14 through October 7, 1993

Inspectors:

L. J. Smith, Senior Resident Inspector

E. J. Ford, Senior Resident Inspector

,

Jennifer Dixon-Herrity, Resident Inspector

'

Approved:

/

Tid

/o/8/93

u,

Thomas F. Stetka, Chief, Project Section D

Date

,

Inspection Summary

Areas Inspected: This special inspection was performed to evaluate the

corrective action, operability, and reportability determinations related to

the failure of containment spray Valve CS-125A to open on September 13, 1993.

The related testing, requests for enforcement discretion, and subsequent

request for an exigent Technical Specification change were also reviewed.

,

Results:

Two apparent violations were identified:

(1)

The first apparent violation involved the failure to satisfy the

requirements of Technical Specification 3.6.2.1.

On September 25,

Train A of the containment spray system was determined to have

been inoperable.

This inoperability was significantly in excess

of the allowed outage time of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (Section 1.8).

,

(2)

The second apparent violation involved the failure to promptly

identify-and correct the inoperability of the containment spray

,

system as required by 10 CFR Part 50, Appendix B, Criterion XVI.

The appropriate level of management attention was not directed at

4

resolving this problem until 11 days after unexplained system

q

9311020220 931026

i

{DR

ADOCK 050003B2:

PDR ^

\\

r

1-

-

..

-2-

anomalies were identified (Section 1.8).

In addition, Valve CS-

125A maintenance history indicated some degradation. Based on

test results, the degradation would probably not have prevented

the valve from opening against expected differential pressures.

However, the degradation would have prevented the valve from

i

opening against design differential pressures. This degradation

was not properly identified and is considered to be a second

-

example of this apparent violation (Section 2.3).

Valve CS-125A and, therefore, Train A of the containment spray

system was probably inoperable since the end of Refueling Outage

RF5 (November 1992) and may have been inoperable before that time

(Section 4.2).

Because of pressures significantly in excess of the nominal design

,

pressures, Train B of containment spray was degraded to the extent that

detailed evaluations were required to determine its operability

-

(Section 3.2).

Licensee efforts to determine the operability of Valve CS-125A were

,

effective after September 24, 1993, when Site Directive W4.101,

"Nonconformance/Indeterminance Analysis Process," was invoked

(Section 1.8).

,

Pressures significantly in excess of the nominal design pressures were

found to exist on both trains of containment spray during conduct of

special tests (Section 1.6).

Summary of Inspection Findings:

Inspectim' rollowup Item 382/9333-01 was opened (Section 1.6).

Apparent Violation 382/9333-02 was opened (Sections 1.8 and 2.3).

'l

Apparent Violation 382/9333-03 was opened (Section 1.8).

!

Attachments:

Attachment A - Persons Contacted and Exit Meeting

Attachment B - Simplified Diagram of Containment Spray System

'I

.

.

l

1

. .

.

- . . .

_

_

. .

.

_

'

.

1

e

-3-

DETAILS

1

1 SEQUENCE OF EVENTS

1.1 Failure of Valve CS-125A to Open Followina Surveillance Testing

On feptember 13, 1993, the valve.and pump portion of Surveillance

-

Procedure OP-903-094, "ESFAS Subgroup Relay Test - Operating," for Containment

Spray System Train A was performed. Following the testing, an attempt was

made to fill the containment spray riser by opening air operated containment

spray Header A isolation Valve CS-125A. This valve, a 10 inch WGN solid wedge

gate valve, which uses air to open and a spring to close, failed to open.

'

As the result of this failure, the shift supervisor declared containment spray

Train "A" inoperable at 1:39 a.m. on September 13 and entered Technical Specification 3.6.2.1.

The shift supervisor contacted the maintenance

superintendent who was the duty plant manager. The maintenance superintendent

suggested the problem might be related to a hydraulic lock due to pressure

buildup occurring in the pipe header between Valves CS-117A and CS-125A (see

Attachment B). The licensee believed that the pressure occurred as the result

of the conduct of the engineered safety featu e actuation system (ESFAS) relay-

-

test, OP-903-094, which started and ran the containment spray pump against a

shutoff head.

The header was subsequently vented, the valve stroked satisfactorily, and the

Technical Specification action statement was exited at 2:50 a.m.

1.2 Condition Identification (CI) and Reportina

On September 13 CI 287289 was initiated to document that the valve would not

The CI indicated that Valve CS-125A had a 300 psid pressure across it.

.

open.

This 300 psid pressure was the result of a 370 psig pressure upstream of the

valve and an approximately 70 psig pressure downstream of the valve caused by

a 180-foot containment spray riser header that was maintained in a full

condition.

Engineering was asked to evaluate this condition to determine why

the valve would not open with a 300 psid pressure across it. The condition

was given a resolution priority of T4, which meant that the item was Technical

Specification related with an urgency such that it should oe completed within

7 days. The bulk of the engineering effort during the period of September 13-

17, 1993, was focused on determining how the valve worked and attempting to-

identify the cause of the apparent degradation.

On September 17 the inspector questioned licensee personnel about short-term

.

corrective actions to ensure Train B would not unknowingly be similarly

effected by elevated differential pressures induced during testing.

The

licensee-speculated that the high differential pressures always may-have been

present; however, it probably was not a problem because the upstream check

valves (CS-Il7A/B) leaked sufficiently, thus allowing the built-up pressure to

1

H

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -

_ .

,

l

.

-4-

,

decay rapidly. However, recent check valve maintenance apparently slowed the

pressure decay in the line and allowed the line pressure to remain high.

I

As the result of discussions with the inspector, on September 17, the system

j

'

engineer wrote a letter to the operations superintendent recommending that the

containment spray header be vented after each run of the respective

containment spray pump.

Following receipt of the letter, the operations

department initiated Standing Instruction 93-07, which provided guidance to

'

operations personnel directing them to vent the headers following pump runs.

The system engineer wrote Condition Report (CR)93-156 later the same day to

identify the fact that Valve CS-125A would not open with a 300 psid pressure

across it, which was in conflict with it's design and procurement

specification which stated that the valve would open under emergency

conditions with a 300 psid pressure across it. The failure of Valve CS-125A

to open was not understood at the time.

Since Valves CS-125A and CS-125B were

identical valves (one in each train), the potential existed that both valves

could be affected by the hydraulic lock phenomenon.

The inability to open

either of these two valves could have prevented the fulfillment of the

containment spray safety function. The condition was determined to be

reportable in accordance with 10 CFR 50.72 (b)(2)(iii)(D) on September 17 at

,

4:45 p.m.

On September 22 the licensee also determined that this event should

be reported as a licensee event report in accordance with

10 CFR 50.73(a)(2)(v).

1.3 Initial Containment Spray System Evaluations

On September 22 during a conference call with NRC personnel, the licensee

stated that the containment spray pump shutoff head was 620 feet or

approximately 275 psig. Chart Recorder CS-IPR-0303X- records the pressure on

the inlet of Shutdown Cooling Heat Exchanger A, which is upstream of stop

check Valve C5-117A. This recorder indicated a peak pressure of 370 psig for

this event with a decay to 314 psig after approximately 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and 15 minutes.

Further, the licensee stated that, during November 1992 the same chart

recorder had recorded pressures as high as 500 psig. Operation at 500 psig

was later determined by the licensee to have occurred when shutdown cooling

was placed in service at the end of Refueling Outage RF5 and, therefore, not

related to this event.

The licensee also stated that the pump would start

from 1-1/2 to 2-1/2 seconds following the signal- to open the valve during

emergency conditions. They also stated that it was expected that, during loss

of offsite power, the pump start would lag the valve opening by 11-1/2 to 12-

1/2 seconds and, therefore, they did not consider that the hydraulic lock

condition would occur during an actual containment spray system demand.

NRC

personnel requested the licensee to assure that there were no other potential

operating configurations that would allow the pump to start prior to the valve

opening.

On September 23, following additional reviews in response to the NRC

questions, the licensee concluded that, in an accident situation, both the

containment spray pumps and the containment spray isolation valves (CS-125A/B)

l

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

. _ _ . . .

.

.-

J

"

-.

.

'.

-5-

"would actuate at about the same time and that, therefore, they could not

conclusively state that the valve would open prior to pump start.

1.4 Initial Evaluation of Valve CS-125A Degradation

'

Preliminary evidence of valve degradation became evident on July 13, 1993, on

the basis of diagnostic data taken for another purpose (see Section 2.2).

Some disagreement existed within the licensee's technical staff as to what was '

the appropriate estimate of the degradation. On September 24 at 5 p.m. the

licensee considered the condition of containment spray Valve CS-125A as

indeterminate in accordance with Site Directive W4.101, "Nonconformance/

Indeterminate Analysis Process." This was 11 days after it was identified

that containment spray Valve CS-125A would not stroke with a 300 psi

differential pressure across it.

1.5 Special Testing of Valve CS-125A

On September 25, Revision 0, of Special Test 01113735, " Test of Containment

Spray Header," was performed for Train A.

The test was written to determine

the length of time each containment spray header stays pressurized after

securing the respective containment spray pump and to identify the source of

indicated pressure above the pump shut-off head in the piping. During

testing, pump discharge pressure measured 260 psig.

Pressure at the inlet to

the shutdown cooling heat exchanger measured 308 psig. The pressure just

upstream of Valve CS-125A was measured at 469 psig. This pressure stabilized

'

at 450 psig.

Fluid transient effects were observed as containment spray pump

discharge check Valve CS-111A, slammed shut. Based upon these test results,

Containment Spray Valve CS-125A was considered to be inoperable for the

containment spray function.

Technical Specification 3.6.2.1 was entered at

3:05 p.m., September 25.

1.6 Unexpected Pressure Suroes due to Air Entrainment

On September 27 Nonconforming Condition Identification (NCI) 287461 was

written to document the unexpected pressure surge and fluid transient in

Containment Spray Train A.

The design rating of the line was 300 psig and the

licensee conservatively hypothesized that pressures as high as 570 psig may

have previously existed in the line. The licensee performed engineering

'

evaluations that demonstrated the structural integrity of the containment

spray system and conducted system walkdowns to ensure that no damage had

occurred. Air entrainment, coupled with an impulse wave phenomenon, was the.

suspected cause of the unexpected pressure surge and fluid transient.

The licensee evaluated the piping configuration for both trains of containment

1

spray. Train A was determined to have twice as much pipe as Train B.

Further, approximately 18 feet of high point piping upstream of Valve CS-125A

1

'

was identified without a high point vent. NCI 287462 was written to address

the air entrainment. A high point 1-inch vent valve was installed on

September 27. The licensee completed a series of sweeping and venting

operations, repeated special testing in accordance with Special Test 01113735,

-- -

-

-

.

.

-6-

" Test of Containment Spray Header," and performed ultrasonic testing. As the

result of this testing, a second air bubble was identified.

,

On September 28 the licensee believed that significant air accumulation did

not exist on Train B.

The licensee requested a time extension of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> for

Techanical Specification 3.6.2.1.

NRC granted enforcement discretion so that

the licensee could install a second vent on Train A.

,

A second vent was installed on September 29 using NCI 287462, Revision 1, as

the authorizing document. NCI 287492 was also approved to add a second

solenoid valve to the actuator of Valve CS-125A for the purpose of decreasing

the stroke titre. The system was filled, vented, and retested in accordance

with Special Test 01113735, " Test of Containment Spray Header.". The peak

pressure testing was repeated several times, with similar results. The

shutdown cooling heat exchanger inlet pressure peaked at approximately

320 psig and leveled off at 270 psig in less than 4 seconds.

Local peak

,

pressure upstream of Valve CS-125A was now approximately 337 psig.

The licensee planned to evaluate their nominal design pressure rating and

corresponding hydrostatic test specifications in light of the recent special

test results. Their evaluation will be tracked as Inspection Followup

Item 382/9333-01 and reviewed during a subsequent inspection.

1.7 Significant Degradation Measured for Valve CS-125A

,

On September 29 and 30 the peak pressure test was repeated and Valve CS-125A

,

was tested against the differential pressure determined to exist one second

after the peak, i.e., 320 psig upstream of the valve with a riser level of

170 feet. The valve did not open at 320 psig or at 310 psig. The valve

-

successfully stroked twice at 300 psig and then failed to operate two times

during subsequent consecutive strokes.

Pressure was lowered to 290 psig and

the valve stroked successfully. During subsequent testing, a 15-minute

interval was instituted beween valve strokes. When this interval was

implemented, the valve successfully stroked at both 290 psig and 300 psig.

The licensee theorized that valve heating due to multiple stroking operations

<

'

was a factor in the previous failures at 300 psig. The licensee evaluated

this data and determined that they were unable to demonstrate operability of

Valve CS-125A.

,

'

'

On September 30 the licensee submitted Emergency Technical Specification

Change Request NPF-38-143. The proposed change was approved by the NRC to

allow containment spray isolation Valves CS-125A and/or -B to be maintained in

the open position. The licensee opened Valve CS-125A and declared Train A to

be operable.-

1.8 Conclusions

Valve CS-125A was apparently inoperable at least since September 13, 1993, and

continued to be inoperable even after system venting. This was an apparent

violation of the Technical Specification 3.6.2.1 because the allowed outage

,

y

,

,,

,

,wn

-- +>

-

.

.-

-

.

.

-7-

time of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> was exceeded without taking action to restore the containment

spray system to operable status or to shut down the plant (382/9333-02).

The appropriate level of. management attenticq was not directed at resolving

this problem until 11 days after unexplained system anomalies were identified.

.

As a result, the inoperability of containment spray system Train A was not

corrected promptly. This was an apparent violation of 10 CFR Part 50,

Appendix B, criterion XVI wnich states, in part, that conditions adverse to

-

quality, such as failures and malfunctions, are promptly identified and

<

corrected (382/9333-03).

.

Licensee efforts to determine the operability of Valve CS-125A were effective

after September 24, 1993, when Site Directive W4.101,

"Nonconformance/Indeterminance Analysis Process," was invoked.

2 PRIOR MAINTENANCE HISTORY - VALVE CS-125A

2.1 Valve Maintenance

On May 16, 1991, the licensee completed Work Authorization 01056121. The work

4

authorization was initiated because Valve CS-125A leaked by the valve seat

under normal system pressure. A new stem was fabricated by the licensee and

installed with new seats for the valve. The root cause was determined to be

galling on the seat and gate.

On March 10, 1993, Work Authorization 01106349 was completed. The work

authorization was initiated because the valve did not stroke smoothly while

opening to fill the containment spray riser. The licensee ap)1ied neolube

through a port opening and on the. exposed shaft.

Following tie lubrication,

licensee personnel stroked the valve six times and concluded that the valve

operator was working satisfactorily. The root cause was determined to be

!

'

inadequate lubrication on the piston stem.

During Refueling Outage RFS, the containment spray header was drained and

refilled for work on another valve.

The clearance for the valve maintenance

work was removed on October 8, 1992.

The maintenance superintendent stated he was investigating a report from the

mechanics that they were called during November of 1992 regarding problems

'

with Valve CS-125A following ESFAS testing. The nature of-the problem or the

mechanics response has not been determined.

The licensee will be interviewing

personnel and reviewing records in this area.

2.2 Riser level Anomalies

The licensee stated that riser level instruments on both containment spray

,

headers were drifting out of calibration. On May 25, 1993, the as-found value

of the riser level on containment spray Header B was below the Technical

Specification required level. CR 93-059 was written and the licensee replaced

the Train B level indicator.

.

-

..

.

.

-8-

On July 13, 1993, as a part of the investigation for CR 93-059, instrument

technicians performed valve performance testing on Valve CS-125A. The

technicians were attempting to determine if valve performance had some impact

on riser level instrument calibration problems. The licensee believed that

rapid pressure changes, following the opening of Valve CS-125A or CS-1258,

caused the needle to move rapidly and knocked it out of calibration. The test

results indicated some sluggish valve operation during the first stroke. The

valve appeared to travel smoothly on the second stroke.

However, the licensee '

stated that it was not possible to determine a valve factor from the graphs

because the tests were not performed with a differential pressure across the

,

i

valve. The licensee also stated that the test equipment was new and the test

results were not reviewed by engineers assigned responsibility for valve

'

performance data collection at that time.

2.3 Conclusions

The degradation of Valve CS-125A was evident in the maintenance history, and

precursors of this degradation occurred on March 10 and July 13, 1993. On the

basis of the test results, it appeared that the degradation would probably not

have prevented the valve from opening against expected differential pressures;

.

however, the degradation would have prevented its opening against design

,

differential pressures. This degradation was not properly identified and is

considered to be a part of the apparent violation of 10 CFR Part 50,

Appendix B, Criterion XVI (382/9333-03).

i

3 TEST AND EVALUATION OF CONTAINMENT SPRAY TRAIN B

3.1 Peak Pressure Test and Valve CS-125B Stroke Test

On October 2, 1993, Special Test Procedure STP-01113917, " Test of B

Containment Spray Header," was initiated. The peak pressure of 409 psig,

,

measured upstream of Valve CS-125B following a containment spray pump. start,

exceeded licensee expectations. The test pressure rig was not capable of

testing at that pressure so the valve stroke test was performed with an

.

initial pressure of 365.6 psig, i.e., the maximum capability of the test rig.

The valve stroked satisfactorily during this test.

Following the test, the licensee placed Valve CS-125B in the open position

pending evaluation of the test results and development of a retest. On

October 5 the engineering evaluation of the test results was completed. The

licensee determined analytically that the valve was capable of operating at

pressures exceeding the 409 psig line pressure witnessed during the

performance test.

Further testing was performed on October 6.

During that test Valve CS-125B

opened against a 412 psig pressure measured upstream of the valve with a

corresponding riser level of 172 feet. These results empirically confirmed

the analytical results.

l

.

.

.

..

.

.

_g_

3.2 Conclusions

Because of pressures significantly in excess of the nominal design pressures,

Train B of containment spray was degraded to the extent that detailed

evaluations were required to determine its operability.

4 PRIOR OPERATING HISTORY

,

4.1 Train A Shutdown Coolina Heat Exchanger Inlet Pressure

The inspector reviewed copies of the charts from Chart Recorder CS-IPR-0303X

provided by the licensee for periods before and after Refueling Outage RF5.

The licensee stated that the charts indicated that the pressure transient

problem was worse after the refueling outage. The event that occurred on

September 13, 1993, was the most significant in terms of peak pressure and

time to decay. Other periods of elevated pressure with slow pressure decay

were evident, both before and after Refueling Outage RF5.

4.2 Conclusions

The Train A containment spray piping design made it probable that air bubbles

of some magnitude were in the piping since construction. Variations in

venting methods may have changed the amount of air trapped in the system.

The

potential existed that Valve CS-125A and, therefore, Train A of containment

spray was probably inoperable since the end of Refueling Outage 5 (November

,

1992) and may have been inoperable before that time.

4

..

.-.

-

.

_

-

.

.

..

ATTACHMENT A

,

1 PERSONS CONTACTED

Licensee Personnel-

R. Azzarello, Design Engineering Director

R. Barkhurst, Waterford 3 Vice President, Operations

0. Bulich, Mechanical Design Supervisor

R. Burski, Nuclear Safety Director

-

J. Houghtaling, Technical Support Manager

L. Laughlin, Licensing Manager

D. Packer, Plant Operations General Manager

W. Pendergrass, Licensing Shift Superviscr

R. Peters, Electronic Maintenance Supervisor

D. Vinci, Operations Superintendent

'

The personnel listed'above attended the exit meeting.

In addition to the

personnel listed above, the NRC inspectors contacted other personnel during

'this inspection period.

2 EXIT MEETING

An exit meeting was conducted on October 8, 1993. During this meeting, the

NRC inspectors reviewed the scope and findings of the report. The licensee

had no comments or questions regarding the inspection findings. A followup

exit was conducted via telephone with the Plant Operations General Manager on

October 15, 1993, to discuss the licensee's plans to evaluate the containment-

spray system hydrostatic test requirements as a result of the recent pressure-

test results.

Proprietary valve internal drawings were reviewed by the NRC

inspector and are'not included in this report.

.

.

ATTACHMENT B

.

5

FIG.

01

CONTAINMENT

SPRAY

SYSTEM

=

E

WNT

STANDBY MODE

-

4e

(REF. LCU-1564-G-163)

h

b

"#

VACUUM

S 347

BREAKERS

GM GL

in

CAPACITY

4'

1

~

S

Sl

21B

21A

  1. ^

1068

-

O

nnn

N

,

S

M

M S

1208

120A

CS 1 I

II CS

l

nnn

-

-

S

118B J L

h 118A

_

_ OE

m

.

CS

CS

CS

1108

110A

1283

,

_

, CS

129B

CS 1170

-

CCW

B3-S

CS 1118

%

%C

1 P yCS

CS 1250

CS

d L . .%128A

'

l

N'

,,

129A

V CONT. SPRAY

CS 117A ; CS 125A

_

4

PUWP B

4-

pqb.

CS

CS

CS

.j

'C3

1068 1078

(r

?I

1258; L

SD

HX +------

SS SUMP

CONT. SPRAY

~

XCS

'

RISER PUMP B

NOM SDC

41B

IPS1 PUMP O

,

1 P'

CCW

A3-S

CS 111 A

S

"

$

M

W $

s

'dCONr. SPRAY

602A

6028

)-

PUMP A

TO SDC

C

HC

"8*

CS

CS

s

s

c3

ShAJ L -

SDCHX

W

7

g,

,

^

S

CONT. SPRAY

412A-

f

[CS .

pgSER PUMP A

FROM

C

,

y

101A

LPS! PU

A

-

-

TR A %

8

.Y ,S-

0

~

_.

,.

I.

-

.

'

"

aa

-

.-

- . -

-

- . .

,

--

-

- .

.. .

.

. - . -

,

.

.-

.

.

.

,

ENCLOSURE 2

l

.,

30762

Federal Register / Vol. 57. No.133 / Friday. July 10. 1992 / Notices

..

__

aaaar*=re Sendmmments to: The

Secretary of the Comminaion. U.S.

Nuclear Regulatory e---en.

Two-Yene Trial Program for

Washmgton. DC 20555. ATTN:

%m

Docketmg and Sernce Branch.

Conferences; Poucy Statement

Hand deliver comments to: Ons White

AGesect: Nuclear Regulatory

Flint North.11555 Rockville Pike.

Commission.

Rockville. MD between 7:45 a.m. to 4:15

Acnom: Policy statement.

p.m Federal workdays.

,

Copies of comments may be exammed

stnessARY:The Nuclear Regulatory

at the NRC Public Document Room. 21::0

Commissmn (NRC) is issums this policy

L Street. NW. (Lower 14 vel).

statement on the implamentat2on of a

Washmgton. DC

two-year tnal program to allow selected

a y m ,,,,.Ana cow n

.

enforcement conferences to be open to

James Ueberman. Director. Office of

attendar.ce by all members of the

Enforcement. U.S. Nucler.r Regulatory

general public.This policy statement

Commission. Washmgton. DC 20555

destnbes the two-year tnal program

(3014-2741b

and informs the public of how to get

informacon on upcommg open

suPPtasstTARY INFOfIssATION:

enforcement conferences.

Background

cavat This trial program is effective on

g g.,

,

July 10.1992. while comments on the

enforcement conferences is addressed in

pmgram am kung meerd Submit

Secuan V of the latest revision to the

comments on or before the completion

of the tnal program scheduled for July

., General Statement of Policy and

Procedure for Enforcement Actions."

n.1992. Comments received after this

date will be considered if it is practical

(Enforcement Policy)10 CR part 2.

to do so, but the Commission is able to

appendix C that was pubhshed on

aasure consideration only for comments

February 18.1992 (57 FR 5791).The

received on or before this date.

Enforcement Pohey states that.

" enforcement conferences will not

nonnally be open to the public"

'

However, the Comnussion has decided

to implement a trial program to

determme whether to matntain the

current policy with regard to

enforcement conferences or to adopt a

new policy that would allow most '

enforcement conferences to be open to

attendance by all members of the public.

Policy Statement

Position

The NRC is implementing a two-year

trial program to allow public

observation of se'octed enforcement

conferences. The NRC will monitor the -

program and determine whether to

establish a permanent policy for

conductmg open enforcement

conferences based on an assessment of

the following cnteria:

(1) Whether the fact that the

conference was open impacted the

NRC's ability to conduct a meanmgful

conference and/or implement the NRC's

enforcement program:

(2) Whether the open conference -

impacted the licensee's participation m

the conference:

(3) Whether the NRC expended a -

sigmficant amount of resources m

-akme the conference public: and

(4)The extent of public interest in

........s...r........

~.

.~

.

.

.

Federal Regater / Vol 57, No.133 / Friday, July 10, 1992 / Nodcas

gjg3

!. Criteria For Selocams Open

three categones oflimnaees wdl be

subject to peroommel screensag, that

signs, baamers,poesmen.etc netlarger

Erdoecament Codesences

commernal operaung reactora.

.

Enforcement conferences will not be

hospitals, and omer h== wasch

man W be W e 6 at

open to the public if the enforcement

mu cessat at the renammg types d

esmtm pareams may be mueved,

licensees.

Each regnemal alba wel === a.n=== to

acnon bem matem%,

cmdact the enfeecamentsamfammes

(1) Would be takan asamat an

Conferences % Ope t Enforemment procee&nes a

mth mammal

II. A

individmaL or d the acuan, thougn not

pmcude enfansment emismom

taken agamst anindividual. turns on

As soon as it is determmed that an

wdl contmee tobe a messung between

whether an mdindualhas can:ntued

enforcement conference ml! be open to

the NRC and the hcenese.While the

wmn@"""

public observanon, the NRC wd1 orally

edorcemesa canieressea

for<

(2 Invoi

a

notify the licansee that the enforr* ment

public observacon.it is not open for

g

c aferen e wdl be open to public

public perucipanas.

that the mdividualfs) involved be

observation as part of the agency,a tria,

Persona atteamns open enforcement

'

param aWeM b Ucensa a copy d mnfennces am naamded that(1) the

Isb

onth

ncs of an NRC

this Federal Respster notice that outhnea apparent violanone A=====d at open

O

v

uo

a

the program.1.fcensees mil be asked to

edorcemmt codenmcas am subect to

y y

Privacy Act inintmanon. or other

[t[b

"

ot enf

t

r nee

ge

o y

ung

informanon which could be consuiered

so that the NRC can scheoule an

enforcement acnon and (2) the

propnetary.

appropnately stzed conference room.

statements of views or exps===uma of

Enforcement conferences involving

The NRC wdl also nonfy appropnata

opinion made by NRC employees at

medical misarimetrations or

State liaison officers that an

open enforcement conferences or the

overexposures will be open assnmmg

enforcement conference has been

lack thereof, are notintended to

' ' "l'd and that it is open w pu' iic

represent final detunnmanons or beliefs.

n

tho

a amg

p d

au

"""*"

Individual's name. In addition.

The NRC intends to announce open

ea

8n pgnun in acm&ce

enforcement etmierences mil not be

enforcement conferences to the puolic

"""

        • E*"

open to the puolic tf the conference mi! normaily at least 10 working days m

auendq open enbcament hs

be conducted by telephone or the

advance of the enforcement conference

m epm e an ppatunitym

conference mil be conoucted at a

through the followmg mecsansma,

subst wnnen connetits anmymo, y

relatively small!1censee's facility-

(1) Notices posted in the public

      • ~""~"*

Finally, with the approval of the

Document Roosn:

mH suWumW be knMed to the

Executive Director for Operations.

(2) Toll-free teleobone messeees: and

e

o e

ca Enfa n - atim

enforcement conferences wdl not be

(3) Toll-free eiectrome bulletta coaro

open to the ouolic in special cases

messanes.

where good cause has been shown after

Penomg establishment of the toll-free

Dated at Roctride MD. ttas 7th day alluly

balancmg the bensfit of public

messaee systems. the puolic may call

1991

observanon agammi the potannalimpact (301) 497a73: to obtain a recormng of

For the Nucinar Reguaneory h==ma.

on the agency a enforcement acuca m a upcoming open enforcement

Samuni 1. Chilk.

particular case.

conferences. The NRC wdl isroe another Secremryof the Co- -

The NRC will stnve to conduct open

Federal Reester notice after the toll-free [FR Doc. E-16233 Flied 7-0-94 eas a.m4

enforcement conferences dunna the

messene systems are established.

sause cooe me.c.m

two. year tnal program m accornance

To assist the NRC In maxmg

mth the followmg three gosta:

appmpnate arrangemems to support

(1) Approximately 25 percent ci all

public observauon of enforcement

ehgible ensorcement conferences

conferenas,inamduais interesten m

concucted by tne NRC wdl be open for

attenmng a parucular enforcement

public observaoon:

conference should confy the momdual

(2) At least one open enforcement

identifiedin the meermg nonce

cocierence will be conducted m each of announcma the open enforcement

the reinonal offices: and

conference no later tnan tive busmess

(3) Open enforcement coniczences

days pnor to the enforcement

wul be conoucted with a venety of the

conference.

o av

poi ual bias in the

III. Conduct of Open Enforcement

Coolerences

seleenon process and to attempt to meet

the tnree roais stated above,everv

in accordance mth current crecuce.

fourta chinoie enforcement conference

enforcement centerences mil contmue

involymg one of three catesones of

to normally be held at theNRC remonal

licensees wn! normady be open to me

offices. Members of the puolic wul be

puolic danns the tnel prouram,

allowed access to the NRC remonas

However, in cases wnere there is an

offices to artend open enforament

ongomg aciudicatory pwmi mth

conferences m accoroance wrta the

one or more sterrenors. enforcemmt

" Standard Operstma F

a For

conferences mvorymg tasues related to

Pnmdma Secunty Stroport fer NRC

the subiect mauer of the ocoruna

Heanngs And Meetmas ' published

adjudicanon may also be openea.For

Novemoer 1.195r1158 m 562511. nasa

the purposes of thisinniprogram,the

proceoures provide that visitors may be

,